CF-TownC CHC-PL-860711COPPELL TOWN HALL PUNCH LIST PROJECT NO. 8457 JULY 11, 1986 e t e and in numerous instances especially at the upper radius the caulking has already begun to deteriorate and 1 to 1 1/2" gaps are present. At the limestone sills under the window units at the second floor the underside edge at the drip edge needs to be cleaned of excess mortar. As a typical note there.are numerous cracks visible in the wood cornice area. The General Contractor also needs to insure that the backside of all wood cornice material has been properly primed. Refer to previous field reports which indicate that on both the north and west sides of the building the backsides of the wood cornice were nOt primed prior to installation. Towv~L~,, the left and Fight of the main entry arc:~ the second ~. ~ .... ~ e~ ~*al "~-~ ~ by ....... ~,,~ grani , .-- ....................... gn ....... -'~ ...... te is ~ncorrect ~ ~^ ~-~ ~ ..... ' ..... '-" ..... ~-" ..... submitted os*~ --~-' daslgn fc ..... ~,- T~ p.~ in paFticular is +~- coler'-'hich was ~ ~: . factory =~-~:~ ¢~-~ --~ ..... t~ match +~-~ ~¢olo,-uF ~,,: 1~ ...... , .......... ect .... I be §~van t~ thc .~-c,qcr&l CunLr'dctor on Ch'~s item. The limestone columns still have strong color variations between the pieces. This was previously discussed with the General Contractor. These columns also need to be cleaned thoroughly to remove any stains which occurred during their storage on the job site and during transit to the job site. <&st ot~ ~ =-~ also at - "n ..... - The wood storefront in this area has only been prime painted but' prior to receiving final painting numerous areas need to be caulked especially the joint between the brick and wood storefront and also all dings, nicks, chips, etc. need to be repaired and this entire unit needs to be sanded. This is a typical note for both sides of the building and also refers to the panelized window above each main entry. The construction on these wooden units is not of good quality and much remedial work will be required to make these acceptable. At main entry doors adjust threshold. ~ 10. Clean all limestone columns and bases and all limestone in general. ~" should near the h~ndis~pped r~mp ...... ~rOa that this concrete -~+~,n~_ ....... ~ r~m~-~.., i" p!~s.. :.sd dots off ~' F;,,~ the .... ~ ~ ........ warranty 2erinH 12. At the main entry area the concrete stairs show that they have been chipped, nicked and patched in numerous areas. Refer to previous field reports of some.eight months ago when the General Contractor was advised that these concrete steps'in the main landing in front of the building should be protected and not used as a storage area for steel products. It is requested that the Owner review this installation as to it's acceptability. The General Contractor has much remedial work to make this item acceptable. 13. At the wood cornice area all inside and outside corner joints need to be caulked and any damage or split wood needs to be removed and re~laced. 15. At main entry area install graphics once they arrive on site. 16. During the cleaning of all limestone insure that the joints between limestone pieces are thoroughly cleaned and also any mortar which has smeared over on the face of limestone pieces is thoroughly cleaned or this will'cause a very spotty appearance during the weathering process at the main entry area west end approximately 16' above finish floor the mortar joint color appears to be- inconsistent and needs to be redone. The General Contractor needs to insure that when pointing up the brick joints that the color of mortar matches the surrounding mortar joints in color. WEST SIDE OF THE BUILDING 3, All notes on the north side of the building appear valid for this area. Also especially the splotchiness in the roofing color, the cleaning of all limestone, pointing up of all brick and the caulk!~ng ........ items. Complete the installatiOn of brick and provide the manufacturers~~.~--~ recommended escutcheon around the roof drain drip flanges. At the joint between the sidewalk and brick wall and/or limestone sills insure that the form lumber which has been used is recessed and that this joint is caulked. Also at the ends of each sill the concrete and wood which is exposed needs to be removed and a smoothed concrete surface needs to be installed in this 3 x 3 void area. 4.? At exterior door No. 6 the threshold is approximately 3" above the exterior sidewalk. This is not in compliance with the handicapped code and. the General Contractor is requested to rev. iew the value engineering notes which call for a ramp near ~this area. Be The General Contractor should refer to previous field reports ~_-~=-~ when discussions were held on the wood,cornice area and insure that all wood cornice both exposed and hidden from view has been prime painted properly. This is another area where it was noted that this had not occurred. 0 There are still numerous areas where the wood cornice appears to have split, especially near the interior and exterior corners. As a typical note, this elevation also has problems with the metal flashing at the roof line which need to be corrected by the General Contractor. Reprime and paint Door No. 6 along with steel brick shelf above this door location. The General Contractor should refer to Detail 1.103 which is a typical detail of how to'treat the wood or fiberous joints which are located within the sidewalk or at the sidewalk building joint. This typically has not been done around the building. SOUTH ELEVATION The limestone header above the-window unit at the second floor is not consistent between the north and south elevation. This item has been discussed with the General Contractor on numerous occasions and remedial work still is required to insure that these areas are consistent with each other. me All general notes from the north side of the building apply. The light fl'xtures~r th~n entry.doors havevet'to be ~°L~~. instal led.-{-m~-~.~ ~~' , ~ ~/~y.~~ ~~ The s~~'de l'k area and stair area immediately outside-~he~ main entry on the south side of the building needs much remedial work' with regard to the concrete and the.slab needs to be thoroughly cleaned. The General Contractor should refer to Detail 1.103 with regard to the expansion joint treatment and sidewalk area. 10. 11. 12. 13. 14/: 15. 16. 17. 18. 19. The main entry doors have not been painted nor has the panelized window unit at the second floor which is outside of the City Manager's office.. There is much work that needs to be accomplished on both these wooden units to make them acceptable. Numerous areas of caulking around these wooden units will be needed prior'to final acceptance. Point up all brick, especially around the main entry. ~ The metal flashing at the roof area is very wavy and particularly over the main entry 'area a large gap exists between the wood and metal flashing. The metal flashing and head cornice work above the main entry on the south side of the building is not acceptable. The IVP roofing work on the south side of the buildi§~'is extremely blotchy and as stated earlier the General ContractoF'has been previously advised of this and remedial action will be required. Also the ridge tiles do not extend far enough over the edge at the outside corners to protect this work. There appears to be much remedial work required to make the roofing and metal flashing acceptable. Repair or replace all damaged or stained limestone. The ridge tiles of the IVP roof should align with the outside corners of the wood cornice and metal roof flashing and should not be offset as seen during this inspection up to 3". Insure that all exterior doors have been caulked between door frame and surrounding masonry. It appears that most doors need to be adjusted with regard to the thresholds and weather stripping~ and also the exterior doors need to be painted. Clean all granite surfaces_.--_~ Point up all brick.o~ ~ (/ As a typical note there are numerous chipped brick on this elevation which will need replacing. At the wood cornice work the joints are very pronounced between assembly pieces. Remedial work Will need to be accomplished to make these acceptable. At Door No.3 install strike plate. At Door 13 adjustment is needed to threshold and strikeplate. At Door 13 install strikeplate and adjust threshold. light mixture. 20. 21. There is still much remedial work that needs to be done. With regard to the metal flashings at the roof area especially the metal flashings exPosed near the wood cornice area. The limestone.columns at the south face of the building need to be cleaned tO remove all staining which had occurred during storage of these materials and also there is a pronounced color difference in the sections of columns which wasi.previously discussed with the General Contractor prior to installation. 22. The General Contractor has rubbed and patched the exposed grade beam at the ramp area located east of the south entry area and already it is showing signs of cracking and separation. The General Contractor needs to redo this work. .23. At thc §ar. cr:to,, the Architect will ve~-ify whathcr ~ concrete ~j:us~keepin~ nad wa~ tn h~ ..... to +ho r~q,,~ infn~ation .....unit hms h~n sci-arched ~n nu~ei-ou5 ai-:=~ and__~rustmny ,,o: u~,, ~L. EAST SIDE OF THE BUILDING 1. All notes from the north, south and west elevations apply. 2. Remove tar and drywall splatter from the brick surfaces. Set flush the cleanout which is set in the concrete paving immediately outside of Door 10 and also the cleanout between Doors 10 and g. Clean all limestone. Install light fixture at Door 10.-~~~O-y~ SJ~~~q~ Properly treat joint between concrete ~pavink~ and brick along east elevation. e The height of the thresholds at both Doors 10 and 9 exceeds the Code requirements. Point up all brick. _0~ There are numerous areas where the limestone is damaged or chipPed and remedial work needs to be accomplished. This is a typical not around the entire project and the General Contractor needs to address this ~ck~as possible. 'q~' ~A~ -~o ~~/)~ .~--~ 10. 11. ~12. 13. There is a gap that exists between the~I;~ roofing shingles and the top edge of the metal flashing at this elevation which needs to be repaired. The'~l~ roofing system has a splotchy appearance.~-~- There are tar stains on the ~_roofing system which are visible from this elevation. 14. 15. There appears to be the same flashing problems on this elevation as we have had around the north, south and west elevations. It appears that some of the IVP shingles are not installed properly and are standing up on edge. This needs to be checked by the roofing subcontractor. There are also numerous tiles which are damaged by tar in this area. SITE WORK .1. , F~,,~,, l~t'- r~n ~,,: aite pavan§, :~. w;il ,ut bo ~--~_.._ mt this %im~_ ~co~plete ~u,ch list on the site work will be prepar:d once' ~he ..... "~"- ~et striping .___~nne~artu~ml. :~. rcouirCm~nts. _ h:ve uccn meL, i.e. v ....... = · INTERIOR PUNCH LIST MECHANICAL ROOM AT PENTHOUSE 1. A thorough cleanup of this area is required. Along the west wall at the concrete curb this area needs to be rubbed to eliminate the honeycombing. 3. All over spray and dirt needs to be removed from the mechanical equipment. 4. Seal all penetrations through gypsum drywall. 5. Seal joint between drywall and concrete deck or exposed steel angle. 6. Install door between mechanical room and stairway. 7. Prime, paint and final paint all exposed steel members. ~v~ ,~a]~_:~.~Fsyste,,n &nd clcctric !ight~- Thi~ item nmmd~, to be reviewed_ ,be prepared by James Johnston & Associates. STA I RWAY A 1. Paint all exposed metal or handrails, risers and stringers of ~ stairway. ~'~! door k^+ ...... ,T,~c',ai-,~cal -~m ~nH ~+~ ..... ~ IS~~F~~) Varify that a~le6tri~al conducted ,,,,~,,- -2. e 9. 10. Seal around all penetrations through drywall. Seal joint bctwaan ,,n~tal staiY landin§ and drywa! Tt~e hraand~ail at the landtingSviSr ~neSt~lr~dn i~COxr~enCtliYnsand need~.~~ w p ar enough out o co e h ' ge e e s'o . ~/~ At the penthouse level the lowest intermediate railing enclosure~~ is not Within-code tolerance. The distant center line between - intermediate rails is to be no more than 6". The distance between the finish floor and lowest intermediate rail is 12"-~u~ A thorough cleanup of this area is required. Repair damaged gypsum drywall. Tape, bed and paint as required. Seal joint between drywall and other metal stringers or concrete deck at landings, typically. 11. At the up stairwell from the second floor to penthouse a gap exists between the metal landing and first riser which needs to be welded shut. 12. Replace damaged light fixture lens. 13. Paint all metal doors entering into stairwell.-- ROOM 231 - LIBRARY DIRECTOR 1. Clean all windows.-- ~/7~~~j/m~_~-~. 2. A thorough cleanup of this space is required. Cleanup caulking and bedding around window units. Rebed and repaint outside corner near entry door. Replace damaged ceiling tile at sprinkler head and adjacent to ceiling lights. install Raco trim track at south wall.~.,~~ Properly 10. 11. 12. Straighten paint edge at joint between aluminum window unit and drywall surround. Level ceiling. At window units properly set glazing gaskets. Install door stop before entry doorl Repair drywall around electrical outlets typically. LOUNGE - 232 8. 9. 10. 11. 12. 13. A thorough cleanup of this area is required. Repaint west wall above countertoP and upper cabinets. Repaint cabinets. It appears that the touchup work which was done in this room is unacceptable and this room needs to be thoroughly repainted. ..... ..... general ,,vt= wi th ....... cu .... -FF I , ~ ~ ~ ............ .~ ~mbe piovided~ a wa ' .... ' ..... 'ally around ' Recaulk joint between metal windows and drywall enclosure. Clean all windows. O~ Properly install vinyl base at southeast corner. Clean and seal all vinyl floor covering. ~/~~-~-~~ Remove all paint and drywall material from trim around light fixtures. Repaint ceiling. Level light fixtures in ceiling so that they fit as originally designed and are not flush on one side and overlapping on another. This will be a typical note. LIBRARY - 229 1. Replace damaged ceiling tile. T~c,, ..'~^!!ing grid layout -~ i"~nrr~rt .......... ~nd remedial wn~u..~-~...~ ~ accemp!i~d. Thi~ i~ in reg~r~ te the !cc~ti~n~ ~f light .~~_.~s which ar~ rorrect in thc ceiling grid which has boo,,~-- 'altcrcd tc accc:~d~te them in adjacent tile. Replace stained ceiling tile. 4. At the d~wall enclosure around columns G9 and E9 the General Contractor needs to rework the joint condition between the top of the gypsu~._m- drywall column and ceiling grid to eliminate any gapping.~ 5. Rework d~wall around electrical outlets. ~-~/~.'~~--- 7. The gypsum d~wall enclosure around the'window units ~pically needs to be reworked and in some instances cracking has already begun and water infiltration is present. 8. Clean all windows.~ 9. A thorough cleanup of this area is required. 10. The carpet seaming appears to need rework especially on the north end of this room. i,,qt taking ,h= typical 12. Rework joint betWeen ceiling grid and drywall ceiling between columns along west end of room at atrium. 13. Set all sprinkler heads flush with ceiling tile. 14. 15. Remove all paint and glue stains from carpeting. RewOrk joint between metal windows drywall enclosure around window units. 16. Level ceiling and align main tees. 17. Approximately 6' east of Column E9 there is an apparent water leak which has shown up in the ceiling tile. 18. Complete the installation of all sprinkler covers. 19. As a general note the sprinkler subcontractor needs to 'submit to the City prior'to release of retainage the approved set of sprinkler plans as stamped by the State Board of Insurance. 20. 21. 22. 23. 24. 25 .? A concrete slab along the south and north walls appears to be very wavy and corrective action will be necessary to level this area and also the carpeting along the south wall needs to be reworked as it has previously been cut too short and gapping exists. electrical cover plates 'flush with wall. ~ Set all Provide rubber termination strip between carpe}_~d vinyl floor covering between Library and Computer Room 238. Paint metal do rs at door location 115 and 116 former Mechanical Room 237. Rework wood base west side of r~o_~_~ Caulk all voids. 'Sand all joints and repain~ as required.~ The painted wood sill at the banister assembly appears not to be level and needs much rework. 26. Remove stailns from pickled oak finish at handrail west side of room. collumns west side of room. ~ 27. Repaint 2~. At ~iu~L~-i~ol outlets in column en~l~urcs w~st side of roo~ is ~electric~! !eut!~t~ w~r~ tobe centered in c~ch co~,Jmn., 29. At the column enclosures at location G9 and E9 the carpeting has been cut too short and gaps exist between the carpet and vinyl'ibase. Much rework is required to the carpeting to make it acceptable. 30. Reset glazing gaskets in all window units. 31. The Owner has requested that thumb,latches be installed on the int_erior surface of Doors 104 and 99.-- I~ 0~~ - ~,A~~)~ ~ COMPUTER ROOM - 238 A thorough ~le~nup of this area is required. Repaint door and frame 117. ~ The floor ~ile on this room shows extensive scratches which have occurred and it may be prudent to replace the tile in this room., 3. Replace damaged ceiling tile. me At Door 118 rework door head and provide filler pieces at corners of jambs to seal opening. ~Fr'~me is ~ppruxima~eiy i" ' ' '" | I~/I ~, Install weather striping at Door 117 along with door bumpers.~ 7. The installation of 'vinyl base at the southwest corner is incorrect. 9 10. This flooF ~ppea-:- . _ +~.v ~ vcry ~'y _.._--a_c~kEEp.~Y~P~-action.m-''..,.~ _~ toque. around electrical outlets. Rework drywall Replace damaged ceiling grid. MECHANICAL ROOM - 237 1. Paint and repair Doors 115, 116 and 117 and install weather striping.~ 3. 4. 5. 6. Seal all penetrations through drywall. Properly label all electrical panels and 'clean drywall mud from surfaces.~(~ Permanently number all circuits and main panel H2E. ~ A thOroUgh cleanup is required in this area. ~ Seal all unused penetrations through concrete floor slab. Provide metal J molding at termination of drywall near Doors 116 and~~ 117. The drywall work along the north wall needs rework to make it acceptable. '-8 · ~p~nt +,,~=~ly _ .~..= A thorough cleanup of'this area is required. O~ The floor drain appears to be plugged and not func'tioning prope[l~^~--~-~/ and the concrete floor slab needs to be reworked in this area. 11. 12. Seal all penetrations through drywall and seal around all piping. Install rubber termination strip between carpet and concrete floor deck at Door 116. 13. Insure that the fallback insulation is properly installed under roof structure. There are numerous areas where the metal decking is exposed to view and this needs to be sealed off. 14. 15. 16. neer for the projecq ~l] visi~_~ ther. James Johnston, the mechanical engiist on this room. site and prepare a complete punch l Prior to Owner checking over the space al~ f_jlters as required by Contract need to be changed out. The date of this change out wiJl_~be established between the Owner and General Contractor. WORKROOM - 236 1. A general cleanup of this area is required. 2. Rework and repaint drywall exposed between door frame and ceiling grid at Door 112. 3. Replace damaged ceiling tile. 4. Same general note at wood sills and With regard to setting glazing gaskets and caulking joint between gypsum drywall and aluminum window~V"~ frames. :5. 6. 7. 8. 10. 11. 12. Rework joints in vinyl base. Rework drywall around electrical outlets. ~ A thorough cleanup is required in this area. ~ Caulk joint between drywall and perimeter c~eil_~_ing grid track as there is mUch waving and gaps are present. ~ a~ ov+~r~or-eo~-n~;- conditions th~ vinyl b~ ~-~-~-~ Relevel and straighten main tees at ceiling. Verify location of sprinkler head at southeast corner of this room.~~ Set sprinkler heads flush with ceiling tile. 13. 14. 15. Conceal sprinkler head missing at southwest corner of room. Door stops are missing at all doors. O~ The top head of Door 110 is not complete nor is it leveled with the top head of Door 113 and this needs to be resolved to make it acceptable. 16. Complete the installation of vinyl base at northwest corner. 17. Clean stain from Door 114. 18.? There appears to be a dip in the concrete floor at the southwest corner of the room which is extremely visible. A thorough cleanup of this area is required.~ 19. MULTI-PURPOSE ROOM - 228 1. Replace damaged ceiling tile. 2. Repaint nOrth wall where repairs have occurred. ~ ~.. ;.~;r ;; t.' ~-'~-- ........ T:-~ :~? = ....... .... ~--'~'-J -' ..... 4. Replace damaged ceiling grid. It appears that ceiling tile in this area h~s warped and may need to be replaced in some Instances. ~ ~ Replace stained ceiling tile. Complete the installation of doors into storage room 227, Door 106.~J~ Set downlights flush with ceiling tile and eliminate gap where light is visible between trim ring and ceiling tile. Align Raco trim track with head trqck so no offset joints exist.. A thorough cleaning of this room and all surfaces is required. 11. Remove all paint from hardware and electrical fixture coverplates. 12. 13.. 14.? 15. 16. Touch up painting is required on almost every wall in this room. Door.bumpers have yet to be provided at all door locations. ~ RePair chipped and damaged Raco doorlframes. /L~, Properly install all vinyl base. ~, There is a bulge in the wall at the vinyl base area located near Door 106. 17. 18. 19. Much carpet rework is required in this room as the carpet does not meet the gypsum drywall. The vinyl base does,nOt adhere properly to the drywall and numerous gaps exist. The carpet seaming'in thi-s] room needs some rework. STORAGE ROOM - 227 4. 5. ~6.? Level ceiling. Replace damaged ceiling tile. ~ Clean all paint and glue from concrete floor slab.-~i~F-~. Gypsum drywall is to extend to floor slab and be sealed at that point, e~ Rework drywall at ceiling grid perimeter. This is a typical note.~ At the northeast corner of room the concrete floor slab has cracked and it appears that remedial work will be required to repair this a rea. Seal joint between drywall and Raco toptrack. ~ Rework drywall and ~e~paint arbund electrical outlets and electrical switches. 0~1.~.~'~ A typical note, a thorough cleanup is required and all debris removed. VESTIBULE IN THE LIBRARY AT DOORS 104 1. Properly install vinyl base in this enclosure. ~ 2.corner Rework of joint thisbetween~area, and drywall ceiling and at southwest 3.aRepaint~d°°rrea, and exterior clean and repair door in thi's 4. Properly install vinyl base. ~ 5. The joint between the drywall and Raco toptrack needs to be reworked.~ 6. Replace damaged ceiling tile on this small area. ~ 7.? The carpet seaming under the door between the '-~horough cleanup of th'is area is required. e The carpeting installation along the north wall is unacceptable as a gap of about 1/2" exists between the drywall and carpet edge. Level all window sills. This also appears to be a typical note as the window sills we have seen so far indicate a + or - 1/2" to 3/4" variation in height. O~ ' At the southeast corner of the room the vinl~base has not been ~ installed. 5. At Door 98 the doorstop has not been installed. AREA IMMEDIATELY ADJACENT TO ROOM 217 TO THE EAST o Properly install vinyl base. O~ Once again the carpeting has been cut'too short and a gap exists along the north wall. Rework d~wall at ceiling line.~long west wall and east wall to' eliminate ragged joint. Rework ceiling grid to eliminate gaps between main tee joints. The wood Window sill in this area varies from end to end by 1/2" Clean window.~ ........~+ ..... ~ ~;,,,~ S~ll rounded ~ges shoulu b~ ~ ..... ....... ~ at si!! A thorough cleanup of this area is required. 9. Replace damaged ceiling grid and align ceiling grid. PERSONNEL OFFICE - 1. The carpet at the southeast corner is stained. 2. Complete the installation of electrical outlets and cover plates. 3. Rework drywall joint between drywall and ceiling line on the ~ southeast and west walls. Complete the installation of the Raco door and window system along the south wall. 5. Replace damaged ceiling tile. 6. At the empty conduit and boxes for telephone ~cal subcontractor has not provided pull Cable. 7. A thorough cleanup of this area is required. ~ CONFERENCE ROOM - 21t 1. Replace damaged ceiling tile. ~ 2. Repaint all walls. ~ 3. Complete the installation of sprinkler head covers. ~ 4. Seal joint between downlight trim rings and ceiling tile. Bo The door frames were to be full height and are not. There is approximately 3/4" gap above the head of each door and ceiling. e w 10. 11. Rework drywall above head of doors typically. Door stops have yet to be provided for Doors 89 and 90.0,~ Touch up all scratches and prefinished door frames 89 and 90. ~ At the head of each door close off the gap which occur~,~,~~q~~ corner condition between the head and stile. Complete the installation of vinyl base at northeast corner.¢~, Once again there are stains in the carpet and the carpet seaming · needs to be reworked in the center of the room. Also the carpet appears to have been cut short and needs additional rework to make this acceptable. 12. Align ceiling grid. WORKROOM - 213 ? 1. This room cannot be punched at this time as work is in progress. COPY STORAGE - 212~ 1. This room cannot be punched at this timeiincework is in progress. STAFF ROOM - 210 1. Replace damaged ceiling tile. 2. Complete the installation of upper track along south wall. ~ 3. Rework drywall joint between gypsum drywall and ceiling tile at east wall. Clean all windows. Level all window sills. Set sprinkler heads flush with ceiling tile. A thorough cleanup of this area is required. Complete the installation of cover plates at electrical outlets. At column enclosure repaint drywall and also rework drywall at ceiling joint. 10. As a typical note the carpeting once again has been cut too sho~t around this column and along the south wall. 11. At the wood window sill the ends need to be rounded not square cut. ROOM 207 5. 6. 7. 8. 9. 2. 3. 4. 5. 6. 7. Set sprinkler head covers flush with ceiling tile. Repaint and rework drywall around electrical outlets and switches., There are stains on both of the east and south walls. Rework the installation of Slot diffusers at perimeter of room. The Raco top track does not sit flush with 'the ceiling. A thorough cleanup Df this room is required. In the closet area for this room the shelf needs to be reworked and the installation of the clothes rack needs to be installed properly. Once again as a typical note, seal gap between perimeter ceiling grid and drywall. Replace damaged ceiling tile. 10. Relevel ceiling grid and replace bowed and defective tile. 11. Rework carpet along north wall to eliminate gap between carpet and vinyl base. 12. Repaint wood trim at window sills. 13. Level all window sills. 14. The coating in the glass along the south wall appears to .be defective. There are numerous pinholes and scratches. This glass will need to be replaced and this is a typical note. 15. Typical note, a separate punch list will be prepared for the condition of the glazing. It is quite noticeable in this room that there are numerous panes of glass which will need to be replaced. CITY MANAGER'S OFFICE - 201 1. Sand and repaint panelized window unit to exterior. 2. Rework gypsum drywall return near this window unit. 3. Rework ceiling grid to create an aligning pattern so as not to be offset at the light locations toward the south end of the room. Rework carpet at Raco glass wall on the north side of room. Rework joint between Raco top track and ceiling grid at east and west wallS'. Rework ceiling grid entirely in this room to eliminate gapping between grid pieces. Replace damaged ceiling tile. The sprinkler head cover should fit snugly to ceiling tile. A thorough cleanup of this area is required. From this room looking to the north at the railing area where the railing terminates into the drywall column typically, these need to be reworked and are presently unacceptable. The General Contractor needs to rework the slot diffuser over the panelized window unit along the south wall. Snug up trim rings for downlights to ceiling tile. e e 8. 9. 11. 12. 13. The carpeting needs to be reworked aroundlthe perimeter of room to eliminate gapping and the rolling effect of the floor which is apparent between the carpet and vinyl base and also at the Raco system. 14. The joints at the sill of the Raco system along the north wall behind Door 81 have gotten very wide and are unacceptable. OFFICE AREA IMMEDIATELY WEST OF THE CITY MANAGER'S OFFICE 1. Replace damaged ceiling tile. 2. Align Raco top track along east wall. 3. Repair j~ints and inside corners at vinyl base along south wall. 4. Replace dings and defects in gypsum drywall alOng south wall~ 5. Rework joint .between gypsum drywall ceiling between columns and ceiling grid to create a smooth transition. 6. This area typically needs to be repainted with regard to the gypsum drywall. 7. Align ceiling grid. 8. Rework carpet at base and complete the installation of vinyl base at the northeast corner of room near decorative column. MECHANICAL ROOM - 206 1. Refer to mechanical room 207, same notes apply. 2. Paint Doors 84 and 85 and complete their installation. VAULT AREA - 205 2. 3. 4. 5. 6. Drywall is to extend to deck and is to be sealed at base. Repair gouges in drywall ceiling area. Remove excess glue from concrete floor and seal as required. ~ns-t~tt entry, door to this room. A thorough cleanup is required in this area. The wood trim board which has been installed in the northwest corner is not indicated on the plans and the General Contractor needs to explain the situation with regard to this. 7. All walls need to be repainted due to numerous stains and gouges. CENTRAL FILING - 209 1, Replace damaged ceiling tile. 2. Set sprinkler heads flush with ceiling tile. 3. Rework ceiling grid so it is level and the main tees are aligned. Rework joint between perimeter suspended acoustical ceiling grid and gypsum drywall ceiling between columns to create a flush appearance. The joint which is present now is totally unacceptable and is out of line. Much rework will be required to make this an acceptable installation especially since the General Contractor has gone ahead and doubled up on the perimeter angle thus making this mistake very noticeable. Be Complete the installation of electrical outlet covers and rework drywall around outlets. Level wood sill at window unit along south wall. It is approximately 1/2" off end to end. 7. At wood sill rounded ends should be provided. Electrical outlets in columns along east side of room are to be centered in columns. All columns around the atrium area need to be repainted. The touchup which has been accomplished does not appear to be satisfactory on the column nor the overhead. 10. Sand and repaint wood base around banister unit to smoothly roll through joints without accentuating them. 11. A general cleanup is required in this area. 12. There are numerous stains in the carpet especially outside of the conference room near Door 89. 13. The typical carpet problems exist with regard to gaps being apparent between the carpet and vinyl base at walls. 14. ReWOrk dryWall around electrical outlets. 15. Remove paint from all door hardware. This is a typical note. 16. Rework drywall at Raco top track trim. There are problems with this particularly over Door 99. 17. Adjust closers on Door 99. 18. 19. 20. Rework wood base around atrium area as it appears to ~ary in height. It appears that the ga~ between the upper wood cap at the wood base and the reveal section varies as much as 1/2" in an 8' run. This problem needs to be resolved to make this work acceptable. At the pickled oak railing between column and the atrium where the railing terminates to each column the drywall enclosure needs to be reworked and repainted to make it acceptable. It appears that the perimeter ceiling grid is.not level and gapping as much as 1/4" to 3/8" as present. This may also be a problem caused by warping ceiling tile and this needs to ~erified with the General Contractor. 21. Set all sprinkler heads flush with ceiling. 22. The carpeting needs to be reworked near the northeast coKner of this room. It is apparent that it is installed incorrectly and some bagging has occurred in it's installation. 23. The seams in the carpet joints need to be reworked to make them' acceptable. 24. There are numerous stains in the carpet which need to be removed. 25. The entry doors to this area located at the northeast corner of the room may need to be replaced due to the numerous scratches, chips and dings and for sure they need to be repainted. CORRIDOR - 224 1. Properly set all sprinkler heads at ceiling. 2. Paint ceiling. Repair drywall joint condition between drywall ceiling and walls and also above Raco top track. 4. Repaint all walls. 5. Properly trim out around water cooler. 6. Repair water cooler, it is leaking. 7. Complete the installation of all electrical switches. At the cased opening between the lobby and this corridor prepare door frame and rebuild as required. The door frame has numerous gouges and at the mitered corners they do not lay flush and flat. Also at the head condition the wood used for the head of the door has been cracked and should be replaced. The carpet seaming needs to be reworked..The vinyl base installation is unacceptable and is of poor quality. Generally, a thor.ough cleanup of this area is required along with quite a bit of remedial work to make this an acceptable area. VESTIBULE - 223 1. Set downlight trim rings flush with ceiling. Repaint all walls in this area. Follow-all typical notes as noted in Area 224. JANITOR'S AREA - 225 1. .Seal joint between gypsum drywall and concrete floor. 2. A thorough cleanup of this area is required. .Remove all tape, bed and paint from door hardware, sink, smoke detector, light fixtures, etc. 4. Install hardware for Door 100. The plastic veneer facing on this door has been scratched and i~ some instances has been stained. This needs to be reviewed with the General Contractor and corrective'action taken. 6. The drain piping for the Janitor's sink has begun rusting. e Provide sealer to concrete floor. The walls and ceiling' need to be painted as called for in the room finish schedule. This area will need to be repunched when the General Contractor has completed all remedial actions. WOMEN'S RESTROOM - 221 Plastic vanity countertop is loose and is not properly supported at west wall. This wall will need to be taken apart and the proper steel supports added to secure this in position. Properly trim out around parabolic light diffuser at ceiling above mirror. 3. The vinyl wallcovering installation needs much repair especially at joint conditions. At vinyl wallcovering on patterned wall the ...... pattern between joints does not align'and needs to be redone. 4. A thorough cleanup of this area Will be required. The location of clean outs in the west wall nearest the vanity does not appear to be acceptable nor does it show this on the plans to be located here. 8. 9. 10.' tl. 12. 13. 14, 1~, 16. 17. 18. 19. 20. 21. 23. Complete the installation of all hardware for Door 101. Screws are missing from the pushplate. No doorstop has been provided at Door 101. Repaint ceiling. Flush up all sprinkler heads with ceiling. All light fixture trim rings are to sit flush with the ceiling. Repair drywall around downlights. The vinyl wallcovering in the restroom is marred and damaged in numerous locations and will need much corrective action. There appears to be a bow in the ceiling along the east wall at the light trough area. This needs-to be resolved. Complete the installation of sprinkler head covers. Rework the ceramic floor tile around the floor drain. It appears that the floor drain sits up higher than the surrounding floor ara thus preventing proper drainage. There is a wave in the ceramic tile base at the floor area west wall. Also the grouting of all ceramic tile is of poor quality and needs to be'redone. There are areas where gapping exists between the ceramic tile and vinyl wallcovering. All ceramic tile needs to be thoroughly cleaned. Under the vanity area complete the installation of wallcovering. The plastic laminate countertop has been stained and needs to be repaired. The General Contractor should verify that the mounting location of the paper towel dispenser meets the handicapped code and is as shown in the plans. At the toilet partitions the base trim needs to be secured. The metal toilet partitions show numerous, scr_a~ches which need to be repaired especially in the handicapped stall. As a typical note for all restrooms, the plumbing piping is not properly secured and the flush valves move easily. This was previously brought to the attention of the General Contmactor to have remedial work completed. 24. The location of the water closet and handicapped stall was set at 16" from the south toilet partition when it should have been set 18". This item will have to be moved to be in compliance with the handicapped code and in .compliance with the plans, Plan 1301. 25. It should be noted that the dimensioning at the offset due north of the vanity and the thickness of the dimising wall between the vanity area and toilet stalls is not. in compliance with the plans. The overall dimension for these two items should be 1'-10" and is presently 1'-6". 26. Once again, there is much rework that needs to be accomplished in this restroom and a~repunch will be accomplished once the General Contractor makes significant progress. MEN'S RESTROOM - 222 On the east wall the paper towel dispenser is set apprOximately 10" too high. 2. A general cleanup of this area will be required. Numerous areas where tile needs to be reworked were noted especially around the base condition and the wing wall between the vanity counter and entry door. The vinyl wallcovering needs much cleaning to remove stains. Complete the installation of ceramic tile base adjacent to Door 102. e Complete the installation of all hardware. Properly align and square up return air grill located due west of entry door. 8. Properly trim out around parabolic light trough at west wall. 9. Repaint ceiling. 10. Complete the installation of sprinkler heads. 11. 12. Repair drywall and flush up downlight trim rings. Square up ceiling air conditioning diffuser over vanity area. 13. 14. Paint access hatch and ceiling northeast corner of room.- A thorough cleanup is required in this area. 15. .Complete the installation of wallcovering under vanity. 16. There appears a roll in the floor under the urinals and this has thrown off the joint pattern significantly. This area needs to be reworked. 17. On the west wall the location of the urinals is incorrect. The far south urinal is located too close to the wall and the north most urinal has not been properly located. 18. The flush valve tie-in assemblies are crooked and loose and remedial work needs to be accomplished. 19. The location of the hendicapped toilet is incorrect. It is to be located 18" from the south toilet partition and is only 15". This will need to be removed and reinstalled in it's proper location. 20. All toilet partitions need to be cleaned up and repaired as necessary. There are numerous scratches which need to be taken care of. 21. 21. Once again this room has numerous problems which need remedial action by the General Contractor and a complete punch list will be prepared once this area becomes substantially complete. Typical note for both restrooms - Complete the installation and termination of 'carpet at both restrooms. LOBBY AREA - 226 Replace damaged and stained ceiling tiles. Insure layout of all downlights adn 2 x 2 florescent fixtures as per plans. 3. Rework drywall around all electrical outlets. 4. Rework all carpeting seams. Be At the northeast corner of this area and northwest corner of this area there appears there is roll in the floor which needs to be floated out. The wood used to case the opening into Corridor 224 needs'much remedial work and is presently of poor quality with numerous dings, chips and split wood pieces. At landing of grand stair area the floor slab slopes up approximately 1/2" from the main landing to the first stair tread which could be.m- a point of problems later on and possible liability by the City. The General Contractor should remove the carpet and float out this area so as not to have a very abrupt slope. Be Properly install the Raco trim track so no gaps exist between the drywall and trim. 9. Properly install the slot diffusers along the north wall. 10. Much rework will.'be required to the panelized window unit on the north wall and a final coat of paint needs to be provided. 11. Plushup all sprinkler heads with ceiling tile. 12. Complete the installation of light fixtures to' eliminate the painting. 13. Repaint all doors which enter onto this area. They are all marred and scratched. 14. The decorative wood trim around all doors needs much rework especially at themitered joints and/or edges at the door casing around Door 99, north side. This style needs to be replaced as it was milled incorrectly. 15. Repaint door and frame for elevator. 16. Rework carpet seaming as pattern does not' align outside of Door 99. Once again at the wood base around the grand stair area it appears that there is a variation in the height of the base and also of the width and depth of the reveal. This reveal width needs to.be consistent and the wood base needs to be set level to make it acceptable. 17. The newal caps all need to have remedial work done to them and need to be repainted at the joint between the drywall soffit and the suspended acoustical ceiling~ The transition needs to be reworked and the ceiling grid layout needs to be redone to eliminate the small spliced piece of tile. The layout of this ceiling is not per plan.' As near as I can tell, the plan was to have started the installation from the north wall leaving a spacer tile of approximately 6" at the connection between the gyp board soffit and ceiling tile connection. 18. It appears that there is a roll in the ceiling directly above the grand stair to the west side. 19. At the gypsum drywall sill there is a bow which is very noticeable ~he end-conditions indicate an 8" height above finish floor yet in some instances more toward the center of this window unit this dimension gets down to 7" and is very noticeable. 20. The handrail connection to the newal post needs to be redone as this is an unacceptable finishing technique. 21. 22. All wood base, ballisters.and connection and spliced pieces need to be sanded and repainted to create a smooth, uniform appearance.. At the column enclosure located at grid G-6 the base is not square and is not true. ELEVATOR This item will be punched in the presence of the Owner because at that time the Owner will have to sign off on acceptance. The General Contractor should make arrangements with the Owner to visit the site to review this ite~. FINANCE DEPARTMENT There is a significant roll along the north wall at the northeast corner. The roll on the floor is approximately 1" in height. This area needs to be floated out level. Carpet rework needs to be accomplished at all seams. West wall'the carpet has been cut too short and the vinyl base does not cover. The vinyl base installation has numerous gaps 'between the joints of the vinyl. 4. There are marks and stains on the wall which need to be touched up. 5. It appears that there is roll in the ceiling along the south wall. 6. Complete the installation of sprinkler heads. 7. Replace damaged ceiling tile. 8. Seal joint between gypsum drywall and perimeter ceiling grid. 9. Rework joint between drywall return and aluminum window frame. 10. At Door 43 the door has numerous marrs in it which need to be repaired and this door needs to be repainted. 11. 12. 13. Complete the installation of hardware. Rework drywall around door frame. Rework door frame to eliminate gouges and nicks and also reworks45© miters. 14. Rework and sand smooth the wood panelized window units at the pay counter, much rework is needed to make this item acceptable. 15. 16. 17. 18. 19. 20. Rework drywall around electrical outlets. Repair drywall around all door openings. A thorough cleanup of this item is required. Sand smooth and repaint cabinet doors where thin coating debris has mixed with the painted surface. Clean up and repaint the interior of the cabinets. Complete the carpet installation in the void area that exists between the east/west cabinet-and the main north/south counter. VAULT -126 1. Install entry doorX Ceiling in this area gets painted white not gray. Repair defects in gypsum drywall and repaint around dOor frame. 4. Clean vinyl floor tile which has been stained. There is a significant roll in the floor in the area of the entry door which needs to be addressed and resolved. 6. Snug up the sprinkler head cover to the ceiling. CORRIDOR - 119 1. Replace damaged ceiling tile. 2. Complete the sprinkler head installation. Seal joint between drywall and perimeter ceiling grid. Once again the carpet has been cut too short and a gap exists between the drywall and carpet. Touchup walls. Vinyl base needs to be installed correctly. Presently it is very wavy. ---- The touchup painting which has been accomplished 'in this corridor is unacceptable because the touchup paint used is significantly lighter than the balance of the wall. It appears that the corridor will need to be repainted in it's entirity. A thorough cleaning of this space and all door frames and doors will be required. 10. 11. The terrazzo floor needs to be cleaned and properly sealed prior to final acceptance by Owner. 12. The carpet joint between the carpeting and.the terrazzo floor is unacceptable. It is very rough and wavy and there is differences in the elevations which causes a stumbling block which could be potentially dangerous. Basically the carpeting on the first floor area, the installation to date is. unacceptable especially around the terrazzo. There is variatiOn in the terrazzo floor darker colors and it. appears that in some instances near the column locations the terrazzo is not ground down sufficiently or it was a problem with the mix which has created some very visible light spots. Also at the corner joint adjacent to the stairs it appears that the terrazzo subcontractor did not fully carry his screeds to a termination point, thus allowing for a ragged corner at the northeast corner of the light terrazzo area. From the main lobby area you can see. numerous ballisters which are split and need remedial action. 13.. Rework drywall around the electrical lights at columns. 14. This area needs much rework with regard to the drywall, millwork, and terrazzo and carpeting prior to final acceptance. An additional punch list will be done of this area once the General Contractor has made sufficient progress to justify same. OUTSIDE OF THE FINANCE DEPARTMENT 1. Rework jointing at millwork and repaint. There appears to be scratches in the formica countertop and this needs to be cleaned and inspected prior to acceptance. 6. 7. 8. The installation of the panelized wood windows at the pay counters needs to be reworked. The jointery is of poor quality. The location of the downlights is not centered in the soffit as required. These will need to be relocated. Replace damaged ceiling tile. Complete the installation of sprinkler trim rings. Rework all woodwork as the splicing in the woodwork is very visible. Rework carpet seaming so pinned out pattern aligns. At the southeast corner the drywall needs to be reworked and this area repainted. 10. The joint between the suspended acoustical ceiling and the drywall soffit between columns is unacceptable and needs to be redone. PUBLIC LOUNGE ~ 180 1. Complete the installation of wood base. The wood base and crown mold which has been installed to date needs much remedial work to eliminate nicks, gouges, etc. 3. Properly install ceiling tile around perimeter of this area. 4. Complete the installation of sprinkler heads in this area. The touchup painting which has been accomplished around the base and around electrical outlets does not match and is unacceptable. 6. Rework drywall around electrical outlets. As a general note level up and plumb all electrical outlets and covers so they are straight through. 8. Replace damaged and stained ceiling tiles in this space. LOBBY AREA - 102 1. Rework drywall around downlights at ceiling. Flush all trim rings tight to ceiling for downlights. Flush sprinkler head caps tight to ceiling. Rework all wood cornice column bases and caps to eliminate dings, nicks, improper jointing, etc. Sand. smooth and repaint. 0 It appears that there is also quite a bit of drywall work which needs to be accomplished on the columns on the first and second level to make them acceptable. These columns need to be rebedded and repainted. The.slot d~.f~user around the perimeter of this space both at the first floor and second floor is of a poor installation and needs to be reworked to make it acceptable. 7. Rework drywall around all slot diffusers typically. 8. Complete the installation of light fixtures in this space. FINANCE DIRECTOR'S OFFICE - 117 1, Replace damaged and stained ceiling tile especially around light fixtures. 2. Rework drywall around electrical outlets. 3.. The touchup painting which has been accomplished around the electrical outlets does not appear to match the adjacent wall surfaces and it appears that'repainting of the entire wall may be necessary, 4, There is alot of variation in the floor and the rolls which are apparent, 5, At the northwest corner ceiling line the perimeter ceiling grid does not abutt securely to the gypsum drywall, 6, At the northeast corner above the window unit the Raco trim track is not set plumb, 7, The Raco trim track along the south wall is marred in numerous areas and needs to be repaired. Also all joints need to be abutted tightly together, 8. All sprinkler heads need to be flushed with ceiling. PROGRAMMER - 116 1, The jointing in the vinyl base needs to be reworked to create tight joints, 2, Rework drywall around electrical outlets, 3, Clean all paint from electrical outlets, 4. Complete the installation of sprinkler head trim plates, 5. Close gap between perimeter ceiling grid and drywall, 6, Properly align aluminum window trim at joints particularly at northwest window head, 7. Replace the two pieces of window glass in the west window unit due to scratches and numerous pinholes in the tinted coating surface, 8, Replace window glass in the northeast window unit due to scratches, 9, Replace window glass in northwest unit because of poor film coating. A final punch list will be prepared on all glazing separately, NORTH AREA OF COMPUTER ROOM - 115 1. Properly install vinyl base so no waves exist. 2. Replace damaged glazing in this window unit. 3. Rework drywall at radius above windows. This is a typical note. At all window units the drywall work is unacceptable as the radius is not arched properly. 4. Remove paint from vinyl base. 5. Replace damaged ceiling tile. 6. Flush up sprinkler heads with ceiling tile. 7. Complete the installation of vinyl base on the north side of the entry door where it was cut too short. 8. Clean and repair all defects in the entry door and complete the installation of all hardware and trim. 9. Rework drywall around all electrical outlet boxes. 10. Seal gap between drywall and perimeter ceiling grid typically. SOUTH PORTION OF COMPUTER ROOM - 115 1. Repaint drywall. 2. Properly install vinyl base. 3. There are numerous marks on drywall around vinyl base. 4. The vinyl base does not sit flush with floor. 5. The vinyl floor tile in this area has been scratched in'numerous areas and it appears that some removal may be necessary to make this space acceptable. 6. The southmost wall appears to be out of align and not plumb. 7. Replace all damaged ceiling tile. 8. Complete the installation of-ail sprinkler trim. 9. A thorough cleanup of this area will be required. 10. Per Mr. Ed Powell, the City Engineer for the City of Coppell, the General Contractor had never gotten with the City personnel to discuss the locations of and electrical requirements for their computer system. This needs to be accomplished as soon as possible so as not to delay the Owner's move into this project. 11. As a typica'! note align and level all electrical light switches and outlets. 12. TouchUp all dings and nicks in the Raco door system, CORRIDOR - 111 Rework carpet. Rework drywall around water fountain enclosure. Ail walls in this corridor need to be repainted to make them acceptable as there are numerous scuffs and abrasions to the surface. Replace all damaged ceiling tile. Seal gap between perimeter grid and drywall. Clean all mud from ceiling grid. 7. Clean all doors. Be Complete the installation of vinyl base. Rework all carpet seaming and also carpet where it abutts wall a rea. 10. Near area of Door 27 rework ceiling grid. 11. 12. 13. 14. Set sprinkler heads flush with ceiling. Properly adjust threshold and properly terminate carpet at Door 6. This carpet is stained in numerous areas and will need to be cleaned per manufacturers instructions. Carpet installation at all door openings is unacceptable especially around door stiles. 15. A thorough cleanup of this area is required before it will be acceptable. ELECTRICAL ROOM - 112 A thorough cleanup of this area is required. Seal all penetrations through drywall. Clean all electrical panels and repaint galvanized boxes. 5. 6. 7. 9. 10. Seal concrete floor. Tape, bed and paint behind transformer location. Repair holes in ceiling. Verify sprinkler head location in this room and set sprinkler head flush with ceiling. Label panels L1W circuits 1 - 30 and 31 - 60. Properly label Panel HIW. Clean and seal concrete floor. AV CONTROL ROOM - 123 3. 4. 5. 6. 7. 9. 10. 11. 12. 13. 14. 15. Provide carpet on stairs at entry to room and properly construct wood stairs. Complete the installation of counter in this area. Rework drywall around electrical outlets. Seal joint between countertop and wall. Repaint ceiling. Flush out downlight trim rings with ceiling. Rework furr out around dimmer controls. This was to have been done with a metal box which was to have been vented on all sides.. Properly install trim around window in this room. Properly caulk joint between metal trim and glazing. Properly install carpet around perimeter of room. There is quite a bit of bounce in the wood floorin9 in this area. Rework carpet seamin9. At the door head the gypsum drywall return is approximately one inch too high and needs to be redone. Complete the.installation of vinyl, base. Rework, sand smooth and repaint all wood trim around the countertop area. 16. There are numerous scratches in the formica counter surface. As a typical note the formica countertops in general throughout this project need to be cleaned and reinspected prior to acceptance. CONFERENCE ROOM --108 1. The threshold at Door 29 is incorrect. It is to be a sloping wood threshold at Door 29,21on§ east wall painting will be required at the cornice trim where rework has occurred at wood joints. 2. Rework threshold at double exit doors. Architect to review and come up with an alternate detail for this threshold condition between the exterior and wood flooring. 3. Touchup ceiling where marks have occurred and rework around air conditioning slot diffusers. 4. Clean drywall mud from trim around 2 x 4 florescent fixtures. 5. Rework joints at wood base to eliminate obvious jointing. 6. It appears there is a low spot in the wood flooring at the north west corner. 7. Rework wood flooring around door frame 31. 8. Rework drywall around electrical outlets. 9. Rework and sand smooth and repaint bifold doors at closet. 10. Repaint interior of closet. 11. Repaint ceiling. 12. Rework drywall around electrical outlets. KITCHEN - 109 1. A thorough cleanup of this area is required. 2. Check the mounting height of the electrical outlets in this room. 3. The countertop has been mounted at 36 1/2". The City Inspector has advised that a charcoal filter will be required for the venting of the stove. 5. Repaint all cabinets in this room. 6. Clean and seal all floor tile. 8. 9. 10. 11. 12. 13. 14. Properly install pantry doors and install interior KV brackets. Remove paint from all hardware. Complete the installation of sprinkler heads. Rework drywall ceiling around light fixtures. Provide proper assembly for damper control near east end of room. Properly install dishwasher, it has not been anchored in place. Repaint the interior of all cabinets. Repaint all doors. COUNCIL CHAMBER - 107 1. Replace damaged ceiling tile. 2. Complete the installation of sprinkler heads. 3. Polish all brass. me Properly install, level and true all stair lighting fixtures. Properly install all landing fixtures in tourist area and repaint lighting covers to match carpet. Rework carpeting at terrace area. There are numerous areas where the carpet was miscut and small patches have been installed. This is unacceptable. At the tourist area there is quite a bit of bagging in the carpet at the riser and tread areas. In the tourist area where the seating will be installed the carpeting which has been cut too short needs to be replaced. Complete the installation of vinyl base to the South side of the council chambers. 10. 11. Clean stains from carpet. Numerous areas of rework are required at the carpet area to make this acceptable. A thorough cleaning of this area will be required prior to the final inspection after the seating is installed in this area. 12, Properly install projection screen on southeast wall. 13, Touchup paint all walls, 14. At raised platform area in front of'council di~s this platform is not truly level and there is a gap to the south side at the riser, Also seal gap between carpet platform and drywall in front of d~s, 15, Rework drywall around all electrical outlets, 16, Clean all stains from carpet. 17, Set all downlight trim rings flush with ceiling tile. 18, Complete the sprinkler head'installation, 19, Repaint and clean exit door and properly install carpet at thresholds. 20, 'Properly. install carpet to insure to meets tight to gypsum drywall typically, MECHANICAL ROOM - 104 1, Paint Doors 24 and 26, 2, Install sound threshold under door bottom. 3, The same notes apply as did for the 2nd floor mechanical room. 4, It appears that the floor drain adjacent to the air handling unit is not set low enough thus allowing water to pond around it, 5, Remove rebar from floor slab which is penetrating near drain lines', 6. Thoroughly clean and seal all floor concrete, 7. Replace all filters prior to turn over to the Owner, 8. Thoroughly clean this room prior to acceptance by Owner, 9, Seal all drywall joints andlseal drywall joint to concrete floor slab, TELEPHONE ELECTRIC ROOM 2, 3, 4. Seal all penetrations through drywall, Clean and seal concrete floor. Seal joint between gypsum drywall and concrete floor. Provide access door at ceiling to enclose damper switch. Complete the installation of all door bumpers and door hardware. Thoroughly clean this area. It appears that the penetration through floor for the routing of telephone conduits has been mislocated by .approximately one foot and stands in the center of the room. These areas will be reviewed and the mechanical/electrical/plumbing systems will be checked by James Johnston & Associates and a separate punch list prepared. COMMUNICATIONS ROOM '- 134 2. 3. 4. 5. 0 Replace damaged ceiling tile. Rework drywall around electrical outlets. Touchup paint required near base along west wall. Set floor outlets flush with floor tile. All sprinkler heads have been removed from this room at the direction of Mr. Ed Powell. Thoroughly clean all formica surfaces. The main window unit in the south wall is not level, it is off by approximately 1/2". 8. Clean and seal all floor tile. CLOSET - 136 1. Complete the installation of ceiling tile. 2. Repair all damage to drywall and repaint. 3. Sand, smooth, fill and repaint bifold doors. 4. Rework drywall at Raco trim. 5. Replace damaged ceiling tile. ROOM - 137 1. It appears that the vanity counter top is installed approximately 1" too high. Properly secure flush valve for toilet. A thorough cleanup in this area is required. 4. Replace all damaged~ceiling tile. 5. Complete the installation of sprinkler head. 6. Flush trim rings around downlights t~d, to ceiling. 7. Properly locate exhaust fan so it does not hit on any ceiling grid tee. 8. Rework ceiling grid so it is symmetrical. CORRIDOR - 135 1. Replace damaged ceiling grid. 2. Replace damaged ceiling tile. 3. Seal joint between edge of cabinet and drywall. 4. Clean and seal vinyl flooring. POLICE ADMINISTRATION ROOM - 139 1. Rework drywall radius above window units tYpically. 2. Touchup painting that has been accomplished on north wall around windows is unacceptable. Replace damaged ceiling tile. Clean and seal all floor tile. Install door to what used to be vault area. Rework drywall at ceiling line by Raco trim track. Rework drywall around all electrical outlets at wall. Along south wall rework all wood around panel window units, sand. smooth, fill and repaint. It appears that the formica countertop along the south wall has been scratched in numerous locations. The General Contractor should clean this area for final inspection and approvals. Repaint all cabinets. Complete the installation of all cabinet hardware. Much remedial work is required at the cabinets along the south end of the room to eliminate all gouges, chips and rough edges. 4. 5. 6. 7. 8. 10. 11. 12. 13. Repair and adjust all cabinet door hinges. 14. Set all sprinkler heads flush with ceiling tile. 15.- It appears that there are numerous high and low spots in the floor which is creating a visual problem with the jointing of the vinyl tile. This item needs to be resolved. 16. At the exterior corner conditions outside preformed vinly base should have been used. 17. Above entry door 54 rework Raco track, enclose~all gaps in the top track assembly. 18. As a typical note, there are numerous chips in the side of the plastic laminate coated doors, .especially around the lock areas. 19. Repaint or touch up paint east wall of this room. CRIMINAL INVESTIGATION DEPARTMENT - 141 1. Rework drywall around all electrical outlets and switches. 2. Align Raco top track with ceiling grid typically. 3. Rework all carpet seams. 4. Replace damaged ceiling tile. 5. Flush all sprinkler heads with ceiling tile. 6. Remove stains from carpet. CHIEF'S OFFICE - 143 2. 3. 4. 5. 6. 7. 8. Remove overspray from door frame. Rework plastic laminate bifold door. Clean top track of Raco system in closet. Repaint walls in closet. Repaint wallse~pecially around base area where marred. Replace damaged ceiling tile. Flush tight to wall the trim track at top of wall and ceiling joint. A thorough cleaning is required of this area. 10. Carpet rework is required along the west wall where carpet does not flush tight with vinyl base. This also occurs on the east and south walls. Scratches are apparent in the Johnson Controls cover MEN'S LOCKER ROOM - 177 1. The vanity sinks are not set level and are not properly secured to wall. 2. The electrical outlets adjacent to the sinks are not installed. 3, Complete the installation of sprinkler heads and patch ceilings around sprinkler head locations. J Seal concrete floor. There appears to be a low area in the concrete floor immediat~.l'y outside of Door 23. Set straight and level all electrical outlets and switch plates, A thorough cleaning of this area is required. 8. Clean all lockers. 10. All lockers have been scratched and Will need to be repainted to'make them acceptable. Properly install vinyl base. It appears that this item was rushed and has been done in a haphazard manner. 11. 12. Seal joint between metal lockers and gypsum drywall wingwalls. This area will be repunched once the General Contractor has completed some of the .remedial work. AREA 175 1. A thorough cleaning of this area is required prior to punch. e The General Contractor should note that once again the water closets have been mislocated and are not centered within the toilet stalls.. Remedial work is required. 3. For the balance of this area a final punch will be prepared once the General Contractor has completed the majority of his own items and this area to date is not ready for substantial completion. MECHANICAL ROOM - 178 1. The same notes apply tothis room as all other mechanical rooms. All panels need to be labeled, all penetrations through the wall need to be sealed and automatic door bottom needs to be installed for sound control. A thorough cleaning of this area is required. 2. The gypsum drywall adjacent to the main entry door is severely damaged and this drywall needs to be removed and replaced. This area too is not ready for final punch. The.General Contractor should proceed with remedial action and advise the Architect as to when he will be ready for this area to be once again viewed. POLICE LOBBY AREA - 140 1. Clean all stains from carpet. 2. Complete the installation of ceiling tile. 3. Above Ceiling the insulation around pipes has been removed especially for condensate drain lines and this needs to be repaired. 4. Remove damaged ceiling tile. 5. The joints in the wood trim at the counter along the north wall are unacceptable and need to be repaired and repainted. 6. The formica countertops shows signs of being nicked and marred and is chipped in front of the pay window unit. All brass needs to be shined and polished and lacquer treated. 7. Rework all wood around the panelized window units, patch, sand smooth and repaint all window units. Set all sprinkler heads flush with ceiling tile. Repaint walls as required. Replace damaged ceiling grid and align all ceiling grid. 11. Seal gap and properly level over Door area 52. PHONE AREA 130 Public telephones have yet to be installed. Properly trim out around electric water cooler. Rework drywall around base and around wooden door frame and repaint. The splicing of casing trim at face of doorframe is unacceptable. There are numerous dings and nicks in the wood doorframe. Typically noted, the woodwork on this project needs much remedial work. The carpet seaming needs to be reworked in this area. Snug sprinkler head cover tight to gypsum board ceiling. Snug up downli~ht trim ring to gypsum board ceiling. 9. 10. 9. Repaint ceiling. 10. A thorough cleanup of this area is required.~ VESTIBULE - 129 2. 3. 4. 5. e Properly install vinyl base. The seaming of carpet in this area is unacceptable. Repaint ceiling. Snug downlight trim ring tight to ceiling. There are numerous gouges in the drywall which need to be filled, sanded and these walls need to be repainted. A thorough cleanup of this area is required. ELEVATOR EQUIPMENT ROOM - 128 2. 3. 4. 5. 6. Complete the installation of the sprinkler head. Make operational the smoke detector. Seal all penetrations through drywall. Properly secure equipment to floor as required. Paint all walls as required. Drywall is to seat tightly and be sealed against the concrete deck below. Seal concrete floor. Remove all paint from hardware. A thorough cleaning of this area will be required prior to final acceptance. FIRE CONTROL ROOM - 125 1. 2. 3. 0 Rework floor stab around-floor drain. Seal all penetrations through drywall. Drywall is to be set flush with the concrete slab and is to be sealed at that point. Seal concrete floor slab. 5. Properly secure to wall the extra sprinkler heads and covers and their case. 6. The insulation which has been placed on these pipes has not been done in an acceptable manner and will have to be redone. 7.. A thorough cleaning of this space will be required. BOOK DROP ROOM - 131 1. Seal concrete floor. 2. Drywall is to extend to floor slab and be sealed at that point. 3. Entry door has chip in formica. 4. A thorough cleaning of this space is required. 5. Complete the patching of floor slab near south wall. 6. complete the install'ation of sprinkler heads and rework ceiling around this location. 7. Repaint ceiling and include the painting of the access hatch. 8. As stated on numerous times during this. punch list,.the door frame for this room was to extend from floor to ceiling. Presently there is approximately a 1/2" gap at the head of the door between the head and the ceiling area. 9. A thorough cleaning of this space is required. MEN'S RESTROOM - 132 1. A thorough cleaning of this space is required. 2. At the downlight trim rings flush tight to ceiling. 3. Properly install parabolic lens and trim at light trough over vanity and water closets. 4. It appears that the light trough has been installed incorrectly and is not level in the north/south direction over the vanity a rea. 5. Clean all formica so a final inspection can be made and approvals given. 6. The jointing in the wallcovering needs to be reworked to eliminate the obvious seams. Rework drywall around electrical outlets near vanity. 10. 11. 12. 13. 14. 15. Repaint ceiling. In the handicapped toilet stall, this toilet has been installed at an incorrect location. It is too close to the south partition and does not meet handicapped code. Also in this compartment the south partition is dented and will need to be replaced. The flush valves for all water closets in urinals are loose and need to be tightened. There are numerous scratches and dings in the toilet partition which need to be corrected prior to acceptance. This is a typical note. Complete the installation of sprinklerheads and covers. At the ceiling area prior to the repainting process fill all cracks and patch ceiling as required. Complete the installation of door hardware. This room is not ready for substantial completion at this time. A repuncb will be accomplished at a later date. WOMEN'S RESTROOM - 127 1. Complete the installation of ceiling tile. 2. Flush out trim rings around downlights with ceiling. 3. A thorough cleaning of this restroom is required before final acceptance. 4. As a typical note, in all restrooms where the chrome parabolic diffusers, are in use, all need to be cleaned and shined prior to acceptance by the Owner. Once again, this is a typical note. 5. In the handicapPed toilet stall the handicapped water closet has been installed at an incorrect location and will need to be relocated. 6. As a typical note, the General Contractor shall verify that the grab bars located in all handicapped stalls are set per plans and handicapped code. There-is a variation from 32" to 34" which~ has been noted in individual bathrooms. 7. Clean all grout joints in tile on wet wall. e Once again the toilet partitions are scratched and marred and remedial action will need 'to be taken by the General Contractor to make these acceptable. 9. Caulk joint between water closet and wet walls'typically. 10. Complete the installation of wallcovering under vanity. 11. The vanity face plastic laminate is chipped and cracked on the ends and will need to be replaced. 12. Caulk joint between vanity backsplash and vinyl wallcovering at wing walls. 13. The paper towel holder in this restroom is not consistent with the locatin of the paper towel dispenser in other restrooms in this building. It appears to be much closer to complying with the handicapped codes. The General Contractor will review and respond on this item. 14. Rework parabolic diffusers, trim and light trough in general in. this restroom. 15. Lighting in light trough is not totally operational, it may just be a bulb burned out. 16. Complete the installation of hardware and set all hinge pins. 17. General Note: Properly grout all floor and wall tile. DISPLAY AREA - 105 1. Replace damaged ceiling tile. e Rework ceiling tile around column wrap and around cornice work east, south and west areas of the room. 3. The carpet seaming needs to be reworked in this area. 4. Rework drywall around electrical outlets. The ceiling tile around the perimeter walls is not installed correctly and is not leveled in the grid. e The trim rings around the downlights need to be snug tightly up against the ceiling tile. 7. The same note goes for the sprinkler heads. The wood base needs to be filled, sanded smooth and repainted and any damaged or split wood needs to be replaced. There are numerous dings and dents in the wood base which make it unacceptable at this time. The same note goes for the cornice work. AREA OUTSIDE COMMUNICATION ROOM - 134 1. Replace damaged ceiling tile. 2. Properly set sprinkler heads flush with ceiling. 3. Rework wood trim around door frames and wood base. 4. The wood base along the north wall does not appear to be level and the reveal varies by as much as 1/2". 5. Rework carpet seaming in this area. 6. Remove all construction debris from this area. VESTIBULE 101 1. Work is in progress in this area and a final-punch of these vestibules will be accomplished once the CONFERENCE ROOM - 144 1. Remove stains from carpet. 2. Properly install carpet at base so no gaps exist, 2, Replace damaged ceiling tile, 4. Rework radius above window unit, 5, Replace damaged glass'at'.radius, 6, A thorough cleaning is required in this area, 7, Repaint all shelving, 8. Rework trim track for Raco system at ceiling and provide mitered corners not butted corners at wing wall. LIEUTENANT'S OFFICE - 145 1, Remove construction tools from this space, 2, Replace damaged ceiling tile, 3, Rework drywall radius above window units, 4, Rework drywall around electrical oUtlets and switches, 5, A thorough cleaning of this room will be required. 6, Rework carpeting at vinyl base location. 7, A final punch list of this area will be accomplished once the construction tools have been removed from this space, CORRIDOR AREA OUTSIDE OF INTERVIEW ROOM 147 me Repaint walls. Replace damaged ceiling tile, Clean stains from supply air register immediately outside of gun storage cabinet, Repaint metal gun storage cabinet, Clean paint from drug hopper cover plate, Properly install vinyl base so it aligns properly, 7. Complete the painting of exit doors. 8. Properly install vinyl base so it aligns properly. 9. Complete the painting 6f exit doors. 10. Align ceiling grid. 11. Adjust threshold at Door 9. 12. Rework one-way window at Investigation Room. 13. Seal gap between drywall and trim track at head of wall. 14. Thoroughly clean this area. INTERVIEW ROOM - 147 1. At northwest corner of room the floor tile appears to be coming up. 3. 4. 5. 6. 7. 8. There is also a dip in the floor at this location. PROPERTY.STORAGE ROOM 150 1. Rework hardware so door properly latches. 2. Replace damaged ceiling tile. 3. Flush up sprinkler head cover plates with ceiling tile. 4. Provide vinyl base around base of steel column. 5. Remove stains from vinyl floor covering. 6. At south wall touch up wall near base. 7. Remove paint from all metal door frames. There are marks in the painted wall along the west wall. Clean all paint from trim track at head walls. Rework drywall around one-way glass. A thorough cleaning of this room is required. Remove stains from vinyl flooring. Rework vinyl base at corner conditions typical. Rework drywall around electrical outlets. 8. Repaint north,wall. DRUG HOPPER ROOM 149 1. Complete installation of door hardware and set hinge pins. 2. A thorough clean up of this area is required. 3. Properly finish off at east wall. 4. Repaint all walls in this room. 5. Complete the installation of sprinkler heads. 6. Verify that light fixture which has been installed without diffuser is correct light fixture. INTOXILIZER ROOM - 153 1. Properly patch CMU block around Johnson control unit east wall. 2. Repaint ceiling especially around access hatch. 3. Complete the installation of sprinkler heads and trim. 4. The tooling of CMU joints is very rough on both the north and west walls and all excess .mortar needs to be removed and these walls need to repainted. 5. Complete the installation of deadbolt hardware on entry door. 6. Seal the concrete floor and insure that CMU block is painted right to floor line. 7. This area will be repunched once corrective action has been taken by the General Contractor. CORRIDOR 155 e Rework CMU around electrical outlets and switches especially over counter area. Complete the installation of-sprinkler heads. ~- Flush tight to gypsum ceiling the downlight trim rings. Flush tight to ceiling the metal trim around the 2 x 2 and 2 x 4 parabolic fixtures and rework ceiling around these units. Clean and seal all vinyl floor tile. 6. Caulk all joints around hollow metal frame. 7. Remove~,tape from all labels on labeled doors so UL verification can be seen. STORAGE - 152 1. Complete the installation of hardware in this area. 2.' Seal concrete floor. 3. Finish drywall ceiling. 4. Fill and paint concrete block if required. 5. Seal joint between CMU and hollow metal door frame. STORAGE - 154 1. Set hinge pins at entry door. 2. Repaint entry door. 3. Patch CMU around electrical light switch. 4. Properly caulk at joint between CMU and hollow metal frame. 5. Sand smooth, fill and repaint all cabinets. 6. Clean and seal all floor tile. 7. The CMU which is located under the cabinet which is visible appears not to have been filled with block filler prior to painting. This needs to remedied. BOOKING AREA - 157 1. Rework CMU around electrical outlet. 2. The patching which has occurred around the electrical outlets above cabinet is unacceptable. These outlets are to be set level with each other. 3. The east wall shows indication of water infiltration and staining near upper cabinet. 4. The tooled joints which were to be smooth need some rework and this wall should be repainted. 5. A thorough cleaning of this area is required prior to final acceptance. KITCHEN - 158 1. A thorough cleaning is required. 2. Touchup painting will be required of all cabinets. The electrical outlets which have been installed around the countertop are at an~,in:orrect elevation and need to be redone. 0 The patching of the CMU around the electrical outlets above cabinet is presently unacceptable. J Repaint access panel at west wall. At the direction of Mr. Ed Powell, City of Coppell, the upper cabinet west end, far door, needs to be made operational. A Construction Change Authorization will be processed'and once signed by Mr. Powell work is to commence. 7o The CMU needs to be patched around the drain line for the washer locations. Be The hot and cold water lines are both leaking along the north w~ll. A dryer vent needs to be provided in the east wall as shown on Sheet A-2. 10. Complete the installation.of sprinkler heads. 11. Rework ceiling and snug trim metal pieces around light fixture tight to ceiling. SHOWER AREA - 159 1. Adjust all door hardware. 0 At ceiling line clean joint between concrete ceiling and CMU walls. Rub smooth and repaint. 3. Seal concrete floor at shower. Rework concrete around shower drain. Repaint hollow metal door frame. 6 7 Rework vinyl tile around entry door frame so it fits tight to frame. Clean floor tile. Properly install vinyl base near entry door. Repaint ceiling to eliminate other paint marks. 10. Verify that light fixture which has been installed is the correct light fixture for this space and purpose. JAIL VESTIBULE - 162 1. Rework joint between CMU and concrete deck above. 2. Seal joint between hollow metal frames and CMU typically. 3. Complete the installation of monitor door hinges at Door 75. VESTIBULE AREA OUTSIDE OF MEN'S CELL - 161 1. Seal concrete floor. 2. At the Owner's request an additional florescent fixture will be provided to this area. Once a cost is obtained and approval is given by the Owner this work will commence. 3. Cleanup floor patching at south and east walls of this area. 4. Screw missing from cover plate at ceiling. VESTIBULE AREA OUTSIDE OF THE WOMEN'S CELL - 163 1. Seal concrete floor. 2. Rework repairs to concrete floor at north and east walls. Also seal concrete floor. 3. The hollow metal Door No. 74 is defective and has split and needs to be replaced. This is apparent by looking at the edge condition. 4. Repaint door. MEN'S CELL 1. At this time this is unaccessible, but there will be some punch list items which will need remedial work by the General Contractor once access is available. WOMEN'S CELL 1. At this time this is unaccessible but there will be some punch list items which will need remedial work by the General Contractor once access is available. VESTIBULE - 158 1. At this time this area is also unaccessible and will be punched at a later date. CORRIDOR - 166 1. Replace damaged ceiling tile. 2. Set sprinkler heads flush with ceiling tile. 3. There are numerous areas where the walls have been marred and need to be repainted. 4. The east wall at base is extremely wavy and needs remedial work to be accomplished. This is also apparent on the west base too. 5. Rework ceiling grid. 6. Review installation of access hatch to jail cell area plumbing at east wall. It appears that this should not have been inset but should have been flush with this wall. 7. Replace damaged ceiling tile. NORTH AREA OF COURT MULTI-PURPOSE - 165 1. Rework carpet around floor cover. 2. Rework drywall around electrical outlets. 3. Replace damaged ceiling tile. 4. Complete the installation of ceiling tile. 5. At the projection screen block out properly frame this area in. What the General Contractor has done so far is unacceptable. The metal trim should encase the metal cover of the projection screen and no ceiling tile should abutt directly to this. 6. Remove all stains from carpeting. 7. Rework carpeting at vinyl base area to close all gaps. 8. As a typical note, the splicing in of 1/4" wide carpet pieces into this area is not an acceptable solution to resolving the problem where the carpeting was miscut at the wall location. The vinyl base which has been marred needs--tobe replaced. - 10. This room needs a repunch once the General ContractOr completes remedial actions. SOUTH COURT MULTI-PURPOSE ROOM - 165 1. Replace damaged ceiling tile. 2. Replace ceiling tile which was miscut around sprinkler heads. 3. Rework carpet at vinyl base which had been miscut and where voids are present. Rework drywall around electrical outlets and level and plumb all outlets and switches. 5. At west wall patch, sand smooth and repaint the paneled pay windows and all wood trim. Complete the installation of ceiling tile. Rework arch over pay window. It appears that there are numerous scratches and marks in the formica countertop. This needs to be cleaned thoroughly and prepared for a final inspection. 9. Repaint the cabinetry along the west wall. 10. The door from this room to the main lobby area is missing. 11. Seal joint between perimeter ceiling grid and drywall typically. 12. Provide outlet cover at floor. 13. There are. numerous stains in the carpet which need to be removed prior to final acceptance. 14. This is another area which will be repunched once the General Contractor makes significant progress on repairs. REPORTING AREA - 160 Adjust threshold at Door 12. Complete the installation of all hardware at Door 12. Repaint south wall. Replace damaged ceiling tile. This room is hot, the General Contractor should insure that the testing and balancing is accomplished soon to i~sure that this area cools. Formica countertop has been installed along the north wall and this is not in keeping with the construction plans and obviously was done at the Owner's direction. CORRIDOR - 168 1. Repaint Door 13. 2. At Door 13 complete the installation of all hardware and adjust threshold. e o 2. 3. 4. 5. o 3. Repaint marred walls. 4. Properly set Door 19 and complete the taping, bedding and painting at the door head. It appears that the door head has been damaged and will need to be repaired. 5. Push plate on that door is also not set plumb and needs to be redone. 6. Clean and seal the vinyl flooring in this area. 7. Properly install vinyl base so joints align properly. 8. Complete the taping, bedding and painting of all walls in this area. WOMEN'S LOCKER ROOM - 170 1. Complete the installation .of ground vault interceptor receptacle at west wall near vanities. The vanity sinks are not installed securely. Rework concrete floor slab under vanity units. Seal concrete floor. Repaint ceiling. Rework drywall ceiling around light fixtures. The touchup painting which has been accomplished upon the ceiling and walls does not appear to match and it appears that a complete painting of these areas will be required. The flush valves for the water closets are not secured properly. Rework drywall around napkin disposal units and repaint this wall after repairs are made to the defects. Remove paint from toilet partition and repair all scratching and chips. Seal trim around feminine napkin dispenser. Along north wall clean all excess caulking from CMU block. Properly trim around downlights over water closet area. In the shower area there are nails protruding through the 'drywall which need to be repaired and this wall needs to be patched and repainted. e 3. 4. 5. 6. 7. 10. 11. 12. 13. 14. A thorough cleaning of this entire space is required prior to acceptance. 15. The water closets appear to be set incorrectly. They are to set in the center of the toilet stall compartment, but instead have been located 12" off the partition which is not in compliance with the plans. 16. Complete the installation of ceramic and vinyl base. 17. Door 18 is missing. STORAGE AREA 172 1. Complete the installation of the sprinkler heads. J Verify whether the ceiling in this entire area was to be painted white rather than grey. 3. Rework painting and tape and bed around mirrors. 4. Provide trim strip to terminate vinyl tile under entry door.