MA1009-EM130809 Opinion of Probable Construction Cost Client:City of CoppellDate:9-Aug-13 Project:Andy Brown Park Ph. 2 - Erosion Control Improvements Prepared By:NAA tnp no.:CPL12149Checked By:KJD 60% Design - Wall Around All Segments Sheet:1 of 1 Spec No.ItemItem DescriptionQuantityUnitUnit CostItem Cost 1Mobilization and Site Preparation1LS$75,000.0075,000$ 2Furnish and Install Project Sign1LS$500.00500$ 3Dewatering/Pumping to lower lake level1LS$50,000.0050,000$ 4Concrete Segmental Retaining Wall (Diamond Pro Stone Cut)18,700SF$40.00748,000$ 5Embankment & Grading (30% Import)3,200CY$12.0038,400$ 66" Reinforced Concrete Trail (10' wide)2,830SF$5.5015,565$ 718" Thick Rock Rip-Rap60CY$100.006,000$ 8Geoweb Slope Protection150SY$45.006,750$ 9Safety Rail for Wall600LF$45.0027,000$ 1030" Reinforced Concrete Pipe55LF$110.006,050$ 112 - 10'x2' Reinforced Concrete Box Culvert1LS$25,000.0025,000$ 12Restore Disturbed Areas (sod)9,700SY$4.0038,800$ 13Tree Removal2EA$500.001,000$ 14SWPPP1LS$10,500.0010,500$ 15Proposed Overlook Point (Sta 22+42)1LS$65,000.0065,000$ Construction Subtotal1,113,565$ Contingencies (15%)167,035$ Base Total1,281,000$ No Design Completed Preliminary Design Final Design