Keith,
In response to JDK’s change order request below for Unit A1, Pay Item 6 - Unclassified Channel Excavation, I offer the
following:
Given that we have topographic survey for the lake bottom within the grading limits, I would expect the plans quantity
to be fairly accurate. That said, the change order quantity suggested below for Unit A1 appears to coincide fairly closely
with the volume of spoil to be expected as part of the wall construction (1,000 CY change vs. 1,120 calculated). If
structural excavation is in fact the reason for the change order then the following specification items indicate this is not
a valid change order request.
NCTCOG Item 701.2 (Structural Excavation) states…“Structural excavation shall be considered subsidiary to each
bid item for which structural excavation is necessary.”
Pay Item Description 6 (Unclassified Channel Excavation) states …”The plans quantity was calculated based on
the difference of the existing grade and proposed grade around the lake edge (in front of wall face) and along
the canal (between wall faces).
Pay Item Description 9 (Construct Concrete Segmental Retaining Wall) states…”This work includes the complete
in place construction of…wall.”
The volume of structural excavation should be similar to the volume of structural backfill, since much of the wall is
located at the pre-project lake edge. Approximate calculations for the volume of structural backfill are shown on the
attached PDF.
Please let me know if you have any further questions or require additional information. Thanks
Kyle Dykes, P.E., CFM
StormWaterGroup
1100 Macon Street
Fort Worth, Texas 76102
817.336.5773 Main
817.665.7171 Direct
kdykes@tnpinc.com
From: Keith Marvin [mailto:KMarvin@coppelltx.gov]
Sent: Thursday, July 25, 2013 1:15 PM
To: Kyle Dykes
Subject: Fwd: Addition to change order
Kyle,
1
Call me to discuss this
Keith Marvin
City of Coppell
Begin forwarded message:
From: Tonya Finley <tonya@jdkassoc.com>
Date: July 25, 2013, 11:36:30 AM CDT
To: <kmarvin@coppelltx.gov>
Cc: <steve@jdkassoc.com>
Subject: Addition to change order
Additional change order item will be to A-1 Parks #6 increase by 1,000 CY @ $18.27 pcy.
Please let us know if you have any questions.
Thanks.
Tonya Finley
Controller
JDK Associates, Inc.
940-686-6236
940-686-6318 Fax
2
Volume Calculation (approx.) Unit A1 Structural Backfill (7/25/13) Andy Brown Park Ph-1
Unit A1 Canal section
Structural backfill volume:
400CY
V=3.0 x 6 x 300(lf) x 2 (banks) => 10,800(cf) ÷ 27 =
Unit A1 Canal section
Structural backfill volume:
720CY
V=2.0(w) x 3.5(h) x 2770(lf) => 19,390(cf) ÷ 27 =
Total Volume = 400 + 720 = 1,120 CY
1,000 CY change order