CF-TownC CHC-CN 851204GINN, INC.
December 4, 1985
Mr. Frank Proctor, City Manager
P.O. Box 478
Coppell, TX 75019
Re:
Town Center
Coppell, Texas
co S [I'LTING E(NGINEERS
Dear Mr. Proctor:
We are enclosing five (5) copies each of Change Orders No.
2, 3, and 4 to the Contract, which increase the Contract sum
to $161.00, $500.00, and $1,200.00 respectively. We have
reviewed these items with the Architect and recommend that
the City accept them.
If you agree..with these Change Orders, please execute them
and ~etUrn-them .to. the Architect~_~
If you have any questions, please feel free to call.
Sincerely,
J K/HWG/s r
Enclosures
cc: Ed Powell
16135 Preston Road · Suite 106 · Dallas, Texas 75248'· Phone 214/386-6611
December 3, 1985
,ARCHITECTURE
PLANNING · INIERIORS
Mr. Wayne Ginn, Inc.
16135 Preston Road, #106
Dallas, Texas '75248
Re: Coppell Town Center
Project No. 8457
Dear Wayne:
Following up our recent conversation about the proposed changes for the
Coppell .Town Center we would like to recommend that you accept the following
as Change Orders:
Change Order No. 2 in the amount of $161.00 to add electronic
hinges to the jail entrances.
Change Order No. 3 in the amount of $500.00 to alter the
monumental stair steel columns.
Change Order NO.' 4.in the amount of $1,200.00 to purchase
additional applied ceiling trim finishes as manufacturered
by Ragland Manufacturing.
We apologize for.the delay in this letter in that we were hoping to clear up
the lighting fixzure- situation in this group of proposed changes.
The electrical subcontractor has not been very responsive nor cooperative in
giving proper credits on the major expense fixtures. We will keep you updated
as to our final decision'on.this matter.
As always,'if yon'have any questions, please don't hesitate to call.
Sincerely,
Project Manager
MLH/mvl
cc: John Karlsruher
Rick Berta=i