CF-TownC CHC-CN 850521GINN, INC. May 21, 1985 CONSULTING ENGINEERS Honorabl~ayor Lou Duggan Coppe/1, TX 75019 Re: Change Order Drilled Piers -- Town Center Dear Mayor Duggan: This is to confirm conversations between Steve Goram and yourself and Steve Goram and our office concerning the addition of four drilled piers for the foundation of the above referenced project. We have verbally instructed Rick Bertani of O'Brien, O'Brien, & Callaway to prepare a change order for approximately $2,000 to cover the above change, which was requested by the Architect. The drilled piers were inadvertantly omitted from the project plans. The change is necessary for the completion of the project and immediate approval will save approximately $700 in additional move-in costs. We have, therefore, authorized the work per your concurrence, subject to approval by the full Council. Please feel free to contact me concerning the above. Sincerely, · Wankum, P.E. /st cc: /s{eve Goram