WA9302A-CS 990701 MOORE ROAD CLOSURE
The sequence of procedures the contractor intends to perform in the
Moore Road intersection is listed below. To accomplish these tasks the
intersection will be closed for three weeks beginning July 6~, 1999. The
attached exhibit shows in yellow the areas where the utility construction
will occur.
The numbers on the exhibit correspond with the numbers listed below.
1. Remove existing sanitary sewer manhole that is in conflict with proposed
30" waterhe.
2. Install 30" waterline east bough the intersection to approximately 50' east
of Moore Road.
3. Extend the storm drainage laterals to the existing 66" RCP in Moore Road.
4. Remove the existing storm sewer laterals & storm drainage manhole.
5. In~ll new 66" RCP.
6. Construct new storm drainage manhole.