GENERAL REPORT
Report Date June 20, 1994 Inspection Date June 17, 1994
Client City of Coppell
Project W.T. Cozby Library
Coppell, Texas
Identification Reinforcing Steel Inspection
Method of Test Visual Inspection Page #1 of 1
Results
On June 17, 1994, reinforcing steel was inspected at the following locations by a
representative of GEE Consultants, Inc.:
1~t floor slab on-grade-west half of building
The following discrepancies were noted and called to the attention of Charlie, a
representative of J.L. Burney Construction:
1. Dowels in construction joint to be placed later
2. Chairs to be placed later
The above discrepancies will be corrected as noted prior to concreting. Concreting not
scheduled on this date.
Technician: K.Mc.
cc: Gary Sieb - City of Coppell
Larry Davis - City of Coppell
Mike Sherpinskas - Diversified Construction Services, Inc.
Jim Bullock - F & S Partners
Russell Williams - Brockette Davis Drake, Inc.