WA9302A-CS 971002 SHIMEK, JACOBS & FINKLEA, L.L.P.
CONSULTING ENGINEERS
8333 Douglas Avenue,//820 Dallas, Texas 75225-5816 Fax (214) 361-0204 Phone (214) 361-7900
ROSS L. JACOBS, P.E.
RONALD V. CONWAY, P.E.
JOHN W. BIRKHOFF, P.E.
JOE R. CA~, P.E. October 2, 1997
GARY C. HENDRICKS, P.E.
I. C. FINKLEA, P.E.
Mr. Kenneth M. Griffin, P.E.
City of Coppell
Post Office Box 478
Coppell, Texas 75019
Re: Village Parkway Pump Station Addition
Project No. WA-9302; Bid No. Q1195-02
Dear Mr. Griffin:
We are enclosing three (3) copies of Pay Request No. 15 in the amount of $42,513.92 for work performed by
North Texas Municipal Construction Company, Inc., on the Village Parkway Pump Station Addition project
from July 1, 1997 through September 30, 1997. This project is approximately 98% complete.
As we discussed and as provided by Change Order No. 2, the retainage has been reduced to ~% of the
primary contract amount and 5% of the SCADA contract amount. This should leave ample funds in the
contract to make the necessary adjustments to the final contract amount as anticipated by proposed Change
Order No. 6.
If you concur with this pay request, please have it executed for the City of Coppell and forward one copy
along with the payment due to North Texas Municipal Construction Company, Inc.
Sincerely,
Enclosures
co: Mr. Larry Davis
North Texas Municipal Construction Company, Inc.
J:\Coppell\94156~'ay-RqstXLt~-lS.doc