Gateway BP(3.1)-CS131031
DEVELOPMENT REVIEW COMMITTEE
ENGINEERING COMMENTS
ITEM:
Gateway Business Park No. 3, AAA, Lot 1R, Block A, Site Plan Amendment,
to allow a 10,790-square-foot addition to the two existing buildings to combine
into an 248,980-square-foot, two-story office; to add an enclosed service area and
to revise the parking and landscaping on 18.07 acres of property located at the
northwest corner of Freeport Parkway and IH 635, at the request of SP4 750
Canyon, LP, being represented by Erik M. Hauglie, P.E., Pacheco Koch
Consulting Engineers.
STAFF REP.: Gary Sieb PROJECT ID# SPR-13-0075
DRC DATE:
October 31, 2013 and November 7, 2013
CONTACT:
Michael Garza, P.E., Asst. Director of Engineering, 972-304-7019
COMMENT STATUS: PRELIMINARY FINAL REVISED
AFTER P&Z
1. There may be additional comments during detailed engineering plan review.
2. Is there any interest in putting up escrow for a traffic signal?
DEVELOPMENT REVIEW COMMITTEE
ENGINEERING COMMENTS
ITEM:
Gateway Business Park No. 3, AAA, Lot 1R, Block A, Replat,
being a replat
of Lots 1 & 2, Block A, to combine the two lots into one and to revise existing
fire lanes and easements to allow a revised site plan to accommodate a 248,980-
square-foot building on 18.07 acres of property located at the northwest corner
of Freeport Parkway and IH 635, at the request of SP4 750 Canyon, LP, being
represented by Erik M. Hauglie, P.E., Pacheco Koch Consulting Engineers.
STAFF REP.: Gary Sieb PROJECT ID# RPNR-13-0076
DRC DATE:
October 31, 2013 and November 7, 2013
CONTACT:
Michael Garza, P.E., Asst. Director of Engineering, 972-304-7019
COMMENT STATUS: PRELIMINARY FINAL REVISED
AFTER P&Z
1. There may be additional comments during detailed engineering plan review.
2. Is there any interest in putting up escrow for a traffic signal?