CF-Cozby Library-LR 940426
PIER INSPECTION REPORT Report Date: April 26, 1994 Inspection Date: April 22, 1994 Client: City of Coppell Project: W.T. Cozby Public Library Identification: Straight Shaft Piers Method of Test: Visual Inspection Depth to Bearing Pier Shaft Strata Req'd Actual Total Bearing Casing # Size (Pene.) Pent. Pent. Depth Material Depth Remarks E.2-12 18" 19' 7" 10' 0" 10' 2' 29' 9" Gray Shale 18' 3" Clean, Plumb, Dry B-12 18" 20' 1" 6' O" 6' 1" 26' 2" Gray Shale 17' 8" 1" of water, Plumb, Clean H-12.7 18" 18' 5" 6' O" 7' 8" 26' 1" Gray Shale 18' 1" Clean, Plumb, Dry H-II.8 18" 16' 10" 6' 0" 6' 2" 23' 0" Gray Shale 13' 10" Clean Plumb, D~ B-II.4 18" 18' 2" 6' 0" 7' 1' 25' 3" Gray Shale 16' 11" Clean. Plumb, Dry J-I 1.8 18" 16' 8" 6' 0" 6' 7" 23' 3" Gray Shale 16' 7" Clean, Plumb, Dr)' J.4-8 18" 19' 1" 6' 0' 6' 5" 25' 6" Gray Shale 17' 9" Clean, Plumb, Dry J.4-7.5 18' 18' 4" 6' 0" 6' 5" 24' 9" Gray Shale 18' 5" Clean. Plumb, Dry J.4-6.5 18" 18' 3" 6' 0" 6' 2" 24' 5' Gray Shale 18' 1" Clean. Plumb, Dry J.4-6 18" 18' 2" 6' 0" 6' 5" 24' 7" Gray Shale 17' ti" Clean. Plumb, Dry C-I 1 24" 19' 0" 5' 0" 5' 0" 24' 0" Gray Shale 16' 10" Clean. Plumb, Dry cc: Gary Sieb - City of Coppell Mike Sherpinskas - Diversified Construction Jim Bullock - F & S Partners Russell Williams - Brockette Davis Drake