From:Brashear, Kimberlie <kimberlie.brashear@dallascityhall.com>
Sent:Wednesday, February 06, 2013 11:29 AM
To:Brashear, Kimberlie; Keith Marvin; Bobby Brady
Cc:Parks, Kyle
Subject:RE: Carrollton Dam construction
Keith and Bobby,
The next 5-6 days the contractor will be in a period of intense work to move construction to the East side of the
dam. We may have early morning work as well as late evening work in order to have the river shutdown for the least
amount of time.
Let me know if you have any questions.
Kimberlie West Brashear, P.E. - Project Manager
City of Dallas Water Utilities
Water Facilities Project Management
214-948-4249
From: Brashear, Kimberlie
Sent: Tuesday, October 09, 2012 3:48 PM
To: 'Keith Marvin'; 'Bobby Brady'
Cc: Parks, Kyle
Subject: FW: Carrollton Dam construction
Just to let you both know – we are starting construction in earnest. The next 72 hours are going to be continuous
construction. Kyle Parks, our security coordinator for the water department, has talked to Carrollton Police
Department. If he needs to talk to the Coppell Police just let us know.
Thank you.
Kimberlie West Brashear, P.E. - Project Manager
City of Dallas Water Utilities
Water Facilities Project Management
214-948-4249
From: Brashear, Kimberlie
Sent: Tuesday, October 09, 2012 3:10 PM
To: Librio, Frank
Cc: Baptista, Cesar; Engelbrecht, Darrell; Payton, Randall
Subject: Carrollton Dam construction
Frank,
Starting early tomorrow morning (around 2-3 am) the contractor will be mobilizing at the Carrollton Dam (Sandy Lake
Road at Trinity River). The construction will be 24 hours a day until they are complete with cofferdam construction
around Friday evening or before.
The activities will include:
1
Temporarily stop the flow over the dam to accommodate construction of the cofferdam base in the river bed below the
dam.
Perform fish relocation as required by the Texas Parks and Wildlife Department (lake management firm is doing this
relocation activity in coordination with our contractor, Archer Western Contractors).
Install base, cofferdam, temporary water control piping, access road, and other necessary items to accommodate
construction.
Resume water flow over dam.
Normal construction activity will be 6 am to 11 pm after this time except when we move the weir to accommodate
construction activities on the left bank (right bank construction is first) and when we remove the cofferdam. Estimated
times for these are the end of November and late December or early January.
I will refer media requests to you unless otherwise directed.
Thank you,
Kimberlie
Kimberlie West Brashear, P.E. - Project Manager