Eastlake-CS131220
Rhonda Adloo
From:Michael Garza
Sent:Friday, December 20, 2013 8:08 AM
To:Rhonda Adloo
Subject:FW: Eastlake TxDot permit
fyi
Michael Garza, P.E.
Assistant Director of Engineering
City of Coppell
972-304-7019
From: Shane White [mailto:Shane.White@BT-LAND.com]
Sent: Thursday, December 19, 2013 5:56 PM
To: Michael Garza
Cc: mark.harris@kimley-horn.com; joe.riccardi@kimley-horn.com
Subject: RE: Eastlake TxDot permit
Thanks,
Checks are in mail delivery confirmation blackhole, sent to us from Canada and in Dallas somewhere, hopefully get it
tomorrow, anxious to start clearing
Shane White
BT LAND DEVELOPMENT, LLC
Mobile | 972-489-7292
Email | Shane.White@BT-LAND.com
Website | www.BT-Land.com
From: Michael Garza [mailto:MGarza@coppelltx.gov]
Sent: Thursday, December 19, 2013 5:41 PM
To: Shane White
Cc: mark.harris@kimley-horn.com; joe.riccardi@kimley-horn.com; shane.white@BT-LAND.com
Subject: Re: Eastlake TxDot permit
Txdot has informed me that they probably won't get to the plan review until after the first of the year.
Also, we are still waiting for fees to be paid to allow you to get started.
Michael Garza, P.E.
Assistant Director of Engineering
City of Coppell
972-304-7019
1
On Dec 17, 2013, at 3:22 PM, "Shane White" <Shane.White@BT-LAND.com> wrote:
Michael,
I just wanted to follow up on our brief discussion at pre-con over the requested TxDot permit for
Eastlake and the timeline of our development schedule. I will start Wet Utilities in early to mid Feb.
2014, so the need for permit is just around the corner.
Please let us know the latest and how we can support the task of securing this permit for Eastlake.
Thanks in advance
Shane White
BT LAND DEVELOPMENT, LLC
Mobile | 972-489-7292
Email | Shane.White@BT-LAND.com
Website | www.BT-Land.com
<image003.png>
2