From:Michael Garza
Sent:Wednesday, December 18, 2013 4:33 PM
To:Rhonda Adloo
Subject:RE: 2 more things
Ill touch base with Eastlake.
I had told Ali and his contractor that he didn’t need a permit through us or a pre-con, I told him just to pull a permit
through building inspections.
Michael Garza, P.E.
Assistant Director of Engineering
City of Coppell
972-304-7019
From: Rhonda Adloo
Sent: Wednesday, December 18, 2013 4:28 PM
To: Michael Garza
Subject: 2 more things
1)Eastlake (BT Land Dev) still hasn’t brought their checks in from last Friday’s pre-con, said
they would be here Monday, then yesterday…
2)Ali Amlani paid the road & park fees for Shadowridge Est 5 & wants to get the pre-con
scheduled ASAP
Rhonda Adloo
Administrative Technician
City of Coppell Engineering Dept.
972-304-3682