E-Care Coppell-CS140217 Adams
February 17, 2014
Mr. Michael Garza, P.E. via email: mgarza @coppelltx.gov
Assistant Director of Engineering
City of Coppell
265 Parkway Blvd,
Coppell, TX 75019
RE: Texas Bank Addition Lot 1R2-R Block A (E-Care)
Construction Plan Review Comments
Dear Mr. Garza,
We are in receipt of the review comments dated February 14, 2014. We reviewed the
comments and have revised the submission or provided comment as follows, please note the
original comment numbers correspond to the below revised comment numbers.
CONSTRUCTION PLAN REVIEW COMMENTS:
GENERAL:
1. Remove all city details from plan set; the contractor is required to have a copy of our
details onsite at all times. Keep only project specific non-city details in the plan set.
City Details removed as requested.
2. Add the legal description to cover sheet.
Added as requested.
UTILITY PLAN (SHEET 6.0):
1. Include the fire vault and water meters in a utility easement.
Note added for utility easement as requested.
910 S.Kimball Avenue• Southlake.Texas 76092 City of Coppell
817.328.3200•FAX 817.328.3299
TBPE Reg.No.F-1002;www.adams-engineering.com
Adams
City of Colwell — Final Construction Plans
1. Three (3) sets of the revised 24"x36"Construction Plans
Please forward any comments to jack.garner @adams-engineering.com. Thank you for your
time and consideration regarding this project. Please do not hesitate to contact us with any
questions.
Sincerely,
ADAMS NGINEERING
Jack H. Garner, Jr., P.E.
Project Manager
Cc: Jeffery Medici, Medici Development Partners (email: jeff @medicidp.com)
Craig Wedeman, Curtis Group Architects (email: CWedeman @cga-arch.com)