WA9301-CS 980414 (2)MEETING MINUTES COPPELL 2 METERING STATION CONSTRUCTION PROGRESS MEETING NO. 2 April 14, 1998 Attendees Bar Constructors: City of Coppell: DWU Water Facilities: Sam Arrambide, Joe Arrambide Ted Duff, Larry Davis, Curtis Snow Jennifer Cottingham, John Mathis, Robert Barron 1. SCHEDULE Bar Constructors did not bring their updated schedule. Requested that the coreractor provide an update of the schedule at each meeting to track progress. Action: Bar Construcwrs, Inc. SUBMrrTALS Bar Constructors, Inc. inquired about the stares of the paint and meter calibration testing submittals. Action: DWU Design Requested that Bar Constructors, Inc. submit RFI No. 8 on correct form for record only. Bar Constructors, Inc. verbally requested permission to use cement stabilized sand in lieu of flowable fill and were told to put their request into an RFI. Action: Bar Constructors, Inc. SHUT DOYVN Bar Constructors requested an additional shut down of approximately one to two days of the Coppell 36 inch supply line to accomplish work of installing the new 42 inch supply line around two existing 45 o bends in the 36 inch line. Coppell requested that Dallas supply water through the ROFC directly into the old 16 inch supply line. A test of this suggestion is scheduled to begin at 8 am Monday April 20. The shut down is tentatively scheduled for 9 am Tuesday, April 21. Another shut down will be required to tie in the new 42 inch pipe with the existing 36 inch supply line. Action: Bar Constructors, Inc., DW'U and Coppell TELEPHONE COORDINATION Need to know a date to tell ECI so that GTE can install the phone lines into the new metering station for the SCADA and voice lines. Action: Bar Constructors, Inc. TRAILER CLEANING Contractor needs to dean the trailer at least once a week. Contractor also needs to repair the toilet in the trailer. Action: Bar Constructors, Inc. OTtIER BUSINESS Coppert requested that the contractor make repairs to the temporary bi-pass road in Sandy Lake Road and also requested that the barricades are cleaned up. Action: Bar Constructors, Inc. G.' NEXT MEETING: MONDAY = 2 pm= APRIl, 20 CharHe Stringer, Ken Griffin, Dennis Cave, John Wilson, Tonia Lichtenburg Steve Hardy, Richard Wagner, Hank Niblo Attendees, File 94-81 MEETING MINUTES - COPPELL 2 METERING STATION - PAGE 2