MA1009-CS130402 (2)
Halie Hernandez
From:Marie Castellon <marie@jdkassoc.com>
Sent:Tuesday, April 02, 2013 8:45 AM
To:Keith Marvin
Subject:RE: Andy Browne Project - JDK Associates, Inc.
Keith,
If we are able to provide the signed contracts at the scheduled preconstruction meeting, what would
be the expected turn around for JDK to receive a signed contract? This piece of information is
necessary for us in projecting our expected start date.
Thank you,
Marie Castellon
JDK Associates, Inc.
Contracts Administrator
940-686-6236
940-686-6318
From: Keith Marvin [mailto:KMarvin@coppelltx.gov]
Sent: Monday, April 01, 2013 2:23 PM
To: Marie Castellon
Subject: RE: Andy Browne Project - JDK Associates, Inc.
Marie,
Here is our sample agenda for our pre-construction conferences. We will discuss this information in addition to any
project specific issues the parks folks may want to discuss.
I hope this helps.
Keith Marvin, P.E.
City of Coppell
972-304-3681
From: Marie Castellon [mailto:marie@jdkassoc.com]
Sent: Wednesday, March 27, 2013 10:44 AM
To: Keith Marvin
Subject: Andy Browne Project - JDK Associates, Inc.
1
Good morning,
Was the documentation approved and if so, when can JDK expect contracts?
Thank you,
Marie Castellon
JDK Associates, Inc.
Contracts Administrator
940-686-6236
940-686-6318
2