Project Name: Village Parkway Pump Station Additions
Contractor: North Texas Municipal Construction Co., Inc. Superintendent: Mr. Bill Bigham
Number Construction
Men Working: 0 Hours: to Time Allotted: 420 Used: 488
Weather Conditions: Clear Site Conditions: O-K.
WORK DESCRIPTION
1. There was no activity at the jobsite to repair Pump No. S & 6 which failed during the weekend of 14 through I5. The pumps
are currently turned off.
2. Mr. Larry Davis indicated that TEAM Controls was at the jobsite on 6\16\97. TEAM was not at the jobsite this morning.
3. Mr. Larry Davis indicated that a final walk through will not be scheduled until Pumps 5&6 are operating satisfactorily and
the preliminary punch list items are complete. He suggested the City and S~F go through the preliminary pump station punch
list items to determine what work remains incomplete.
cc: Mr. Larry Davis
)':%C'gppall\941 .~6XL%,Const\Co~,t 14 dec