Below please find the numbers Steve worked up this morning on the additions and deletions for the job.
Eliminated items: A – 1
#10 $3,580.80
#17 $3,250.02
Used/Eliminated items:
#8 $16,576.32
#20 $12,220.00
Change order items:
#15 77 LF Add: $3,453.45
#16 16 LF Add: $ 827.52
#9 1880 SF Add: $49,707.20
A – 2
#28 and #28A 32 LF Add: $13866.56 (split between the 2 line items)
Steve has also estimated 7 days required to do the additions even subtracting what we didn’t do.