MA1009-CS131024 Halie Hernandez From:Steve Kenney <steve@jdkassoc.com> Sent:Thursday, October 24, 2013 2:27 PM To:Keith Marvin; asamaniego@coppelltx.gox Subject:Unit A2 Toe wall and rip rap Keith, We can get the toe wall and rip rap at the spill way do for: 1.Wall 50’L x 6’T x 1’W 2.Remove and replace Rip rap with existing and new 3.Rebuild small natural stone wall for access 4.Re grade and clean disturbed areas $14,000.00 ($3580.20) Total $10,419.80 The credit is for Unit A-1 Line 10 that we charged last pay period that was not supposed to be charged. This price is based on an answer today or first in the morning, because if we leave and come back we will need to include a pump and more man hours to complete the job. Thanks Steve Kenney JDK Associates, Inc. President 1