Can't we get Mike Glenn to hand-deliver the revised drawings and review the
revisions with Mike Martin on Monday so that we can obtain a grading permit
sooner? We are burning around $550 per day in interest carry and anything
we can do to initiate this project and save that money would be appreciated
(Rick Stacy at Stacy Furniture is the only one in the Metroplex that's
allowed to burn that kind of dough!).
..... Original Message .....
From: Williams, James
Sent: Thursday, February 22, 2001 1:39 PM
To: 'cmglenn@glennengineering.com'; 'tomm@alliancearch.com'
Cc: 'kwoltman@hill-wilkinson.com'; Ozymy, Scott; Mountford, Walt;
Newton, Murray; 'mmartin@ci.coppell.tx.us'; 'kgriffen@ci.coppell.tx.us';
'g jo nes@ci.coppell.tx.us'
Subject: Coppell Grading Permit
I just spoke with Mike Martin at Coppell about releasing the grading
permit only. He will only do that after revised civil plans are submitted
that satisfactorily address the comments in his Feb. 20th letter. He
indicated it would take him 2 days to review and approve the comments
related to grading and about 2 weeks to review and approve the remaining
items, assuming they are all satisfactorily addressed. He did say he
would be willing to issue a grading permit if he is satisfied with the
revised plans.
From a timing standpoint; Mike Glenn completes the corrections by end of
the day on Friday, Feb. 23rd, and Mike Martin receives the plans by 12
Noon Monday, Feb. 26th and is satisfied with them, the earliest he would
issue a grading permit on Wednesday, Feb. 28th. The permit for the
remaining civl work should follow by Monday, March 12th at the latest.
Mike and Ken: We understand that the City Engineering Dept. has limited
staff for plan review and if there is anything we can do to help speed the
process along please let us know. We are available to meet with you and
review each item if you desire. Thanks.
Page 1 I
CC: '"kwoltman@hill-wilkinson.com'" <kwoltman@ hill-wil...
tMichael Martin - Coppell Grading Permit
Page 1 I
From:
To:
Date:
Subject:
"Williams, James" <WilliamsJ@koll.com>
'"cmglenn@glennengineering.com'" <cmglenn@glenneng...
Thu, Feb 22, 2001 1:38 PM
Coppell Grading Permit
I just spoke with Mike Martin at Coppell about releasing the grading permit
only. He will only do that after revised civil plans are submitted that
satisfactorily address the comments in his Feb. 20th letter. He indicated
it would take him 2 days to review and approve the comments related to
grading and about 2 weeks to review and approve the remaining items,
assuming they are all satisfactorily addressed. He did say he would be
willing to issue a grading permit if he is satisfied with the revised plans.
From a timing standpoint; Mike Glenn completes the corrections by end of
the day on Friday, Feb. 23rd, and Mike Martin receives the plans by 12 Noon
Monday, Feb. 26th and is satisfied with them, the earliest he would issue a
grading permit on Wednesday, Feb. 28th. The permit for the remaining civl
work should follow by Monday, March 12th at the latest.
Mike and Ken: We understand that the City Engineering Dept. has limited
staff for plan review and if there is anything we can do to help speed the
process along please let us know. We are available to meet with you and
review each item if you desire. Thanks.