Loading...
CF-TownC CHC-SY 850628 HII. TOI E & ABBOCIA ,'EB, INC. 8577 MANDERVIL.i.E"RQ DALLAS. TEXAS 75~31 2'L4/361-cJ~11 June 28, 1985 Howard U. FreemanConstruction'Co. 1428 E. Grauwyler Irving, TX 75060 Attn: Jack Washcitz-~' Re: Coppell Town Center Dear Mr. Washcitz: At the request of Freeman Construction, Shilstone and Associates, Inc. has undertaken an evaluation of pier conditions at the above referenced project. The superintendent on the project had noted that some of the piers had very soft concrete. CONCLUSIONS The soft concrete was caused by the intrusion of water into the plastic concrete. This water either washed the cement out of the concrete matrix or greatly increased the water cement ratio and so reduced the concrete strength. Indications are that the "seal" between the removable casing and the concrete was destroyed at some point. This allowed water standing in the pier hole to mix in with subsequent layers of concrete and destroy the concrete's strength. Observers from/ your office .......... .J_III._.L. ',~.,~ _ I~,, state that there was always concrete in the casing during placement and so the seal was not lost by that method. The other alternative is that the concrete hung up in the casing while the casing was being withdrawn and allowed water to intrude without the knowledge of the observers. The second alternative is unlikely but is the only explanation which fits all the facts and observations. The quality of the piers varies greatly. Most of the piers have a layer of soft concrete starting at the top and ranging down for 18 to 60 inches. Some of the piers exhibit iow strengths and multiple discontinuities for up to 14 feet. Most of the piers appear to be continuous once they get below the water table at about 14 feet. Concrete strengths in the piers range from 4600 psi to nil. The piers were originally cast with a diameter 4 inches greater than that specified. Ultrasonic testing identified a reduction in cross section of the piers ranging from 5 to 30 percent. Considering the cross section reduction and the increased pier casting size, the effective cross section of the piers ranges from one half of an inch too small in diameter to three, and one half inches too large. It is the responsibility of the Engineer to determine the acceptability of the piers as they are in place. Two possible deficiencies appear to exist in the piers: 1) There are multiple lenses or honeycomb in the piers to the depth of the water table. This condition is evide~t'i~ only a few piers. 2) The top of the pier may be too soft to support the load to be placed on it. This condition may exist in many of the piers. In case number one, it may be necessary to provide alternate means of support for the piers in question. In case number 2 it is only necessary to remove the soft top concrete until solid concrete is found and then cap the piers to bring the concrete up to the design height. If new piers are to be placed, we feel that ACI 336- "Specification for End Bearing Drilled Piers" should be followed (copy enclosed). It is not referenced in the contract specifications but is a good guide to follow. Paragraph 2.3.4.7 states, "Where casing is removed, provide specially designed concrete with a minimum slump of 5 in. and with a retarder to prevent arching of the concrete..." Also, when the bottom of the casing reaches the bottom of the water table, casing lifts should be confined to small increments such as two or three feet to reduce the possiblity of a sudden outflow of material to fill a large void. PROCEDURE The softness of the concrete in the piers could have been caused by one of two types of conditions: 1) Improper batching, mixing or delivery of the concrete or 2) Improper placement or intrusion of water into the concrete after placement. A review of the Ready Mix suppliers mix design and batching operations indicated that the problem was more likely in the second area. Petrographic analysis of the concrete showed the pressence of fly ash, which was not permitted in the specifications, but fly ash should not have caused the problem by itself. An ultrasonic evaluation of the piers was conducted by Richard Muenow of Richard Muenow and Associates, Inc. (see attached report). The pulse echo method of ultrasonic analysis used is recognized by both the National Bureau of Standards and the Nuclear Regulatory Commission as a valid method of evaluating the condition of in-place concrete. Pulse echo procedures showed that almost all piers had soft tops ranging in size from 18 inches to six feet. Most of the piers showed a reduction of cross section of five to thirty percent at a depth of about twelve feet. This depth corresponds to the depth of the water table at the site. Ail of the piers showed good quality concrete (over 3000 psi) below the cross section reduction. Some of the piers exhibited multiple lenses, indicating changes in the consistency of the concrete and probable honeycomb or washout of the cement. Piers 14, 16, 33, 68 and 69 all exhibited multiple lenses. Piers 69, 16 and 14 were dug out so they could be observed. Each of the piers was extremely soft to a depth of seven to nine feet, the limit that the back-hoe could excavate. Pier 16 was cored to a depth of 16 feet. The concrete in the top two and one half feet had a compressive strength of 1606 psi. The concrete to a depth of'12 feet either had no cement in it or was so weak that the coring operation washed out the cement and left only sand and stone. The remaining concrete to a depth of 16 feet had a compressive strength of 2464 psi. -2- Piers t3, 46, 54, 70 and 77 all showed a reduction in cross section of 30 percent at a depth of 9 to 14 feet. These piers were excavated and showed variable conditions. Piers 13 and 54 were too soft to attach the core drilling apparatus and remained so for the entire excavated depth. Piers 46, 70 and 77 were cored and showed strengths at the one foot level were 3091, 1370 and 4479 psi respectively. At the three foot level those strengths were 4853, 1935 and 4111 psi. Pier 78 showed a reduction of cross section of 5 percent and had core strengths of 4831 and 4762 psi at the one and three foot levels. Pier 63 had a cross section reduction of 10 percent at the nine to 11 foot level and a strength of 3620 psi at that level. Pier 83 showed a 20 percent reduction and a strength of 3686 psi. ANALYSIS Two questionable conditions appear to exist in some of the piers, reduced cross sectional area and softness to a variable depth. One condition does not necessarily imply the other but the greater the cross sectional reduction, the greater the propensity to develop a soft top. Any softness probably does not extend much below the water table, The cause of the problems are still in question. The immediate cause of the problem is the presence of too much water in the concrete. This results in low strength concrete. Observers report that the concrete had a reasonable slump (indicative of normal water content) when it was being placed in the pier hole and that the hole itself was free from waterinside the casing. To understand how water can intrude into the concrete it is necessary to understand the drilling and placement processes~ When a pier is being placed in ground that has water im the drilling depth, a casing (steel pipe) is placed into the hole so that an area can be created that water cannot enter. Concrete is then placed into the casing and the casing is gradually removed. As the casing is removed, it should always contain concrete and be in contact with the concrete below its lower edge. This prevents water from flowing ~ between the concrete previously placed and new concrete being entered. If the seal is broken, water will intrude and mix with the new concrete. This weakens the concrete. Gradually the water will migrate to the top of the pier, weakening concrete as it goes. According to observers from both your office and the testing lab, the pier hole was dry at the time of placement. At no point in the laboratory reports was there an indication that the seal was broken. The superintentent on the project is experienced in the placement of piers by this method and reports he was always placing fresh concrete on top of previous concrete and not water. This condition is hard to confirm when the top of the casing gets above an immediately accessable position. When the bottom of the casing reached'the level of the water table, the top of the casing would be at about eight feet. It would have been impractical and unsafe to have a person riding the concrete -3- cket to observe the level of the co~crete in the casing. The only way to identify that concrete was still in the casing would have been been the sound of the concrete hitting bottom. Often this method is sufficient for an experienced contractor. During the drilling operation before the casing was placed into the hole, the water table may have washed large quantities of sand and gravel from the sides ~ the hole into the bottom of the hole (see Figure 1). As the casing was being raised, it would have reached a larger than normal volume of the hole to be filled. Given the depth of the water table and the height of the top of the casing, it is conceivable that the casing lost its seal without placement personnel recognizing the problem. The superintendent does not believe this occurred. One explanation which fits the evidence at hand is that the concrete might have gotten hung up in the casing as it was lifted. This would result in a broken seal while there was still concrete in the casing. This condition usually occurs only in smaller diameter casings but is conceivable in this case. The piers showing the most problem are mostly the smaller 16 and 20 inch piers. One laboratory report shows concrete being placed at a three inch slump. If iow slump concrete were placed in the casing at the end of one truck and the casing was left in place for some time and then lifted, the above condition could occur. The broken seal would not be visible to placement personnel. Enclosed is a copy of Richard Muenow's report. Because of the poor quality of Xerox reproduction of the photographs, original photos are being sent to us and will be copied to you. A summary of the pier tests in numerical order is also included.Should you have any questions, please call us. Yours truly, SHIL~TONE & ASSOCIATES, INC. ~__ames M. Shilstone, Jr. Vice President enc. -4- COPPELL TOk'N CENTER PIER klASHOUT EXAI~PLE 8' CASING. CLAY CLAY CDPPELL'~'~WN CENTER PIER TEST RESULTS Pier Date Depth Diam Seam % $~C. El(. Oi. Off Top Bott. I 5/15 24-4 20 VS 90 22.77 2.77 2 5/15 18-5 24 12-16 90 26.56 2.56 5 5/15 18-11 24 12-14 80 25.04 1,04 4 5/15 20-8 24 9-11 90 26.56 2.56 5 5/15 24-11 20 9-12 80 21.47 1.47 6 5/15 24-0 24 VS 95 27.29 5.29 7 5/14 27-9 24 9-12 90 26.56 2.56 8 5/14 29-5 24 VS 90 26.56 2.56 9 5/16 27-11 20 11-12 90 22.77 2.77 10 5/16 29-6 20 11-15 80 21.47 1.47 11 5/15 24-0 24 VS 11-15 85 25.81 1.81 12 5/16 20-0 20 11-12 90 22.77 2.77 15 5/14 28-10 24 9-15 70 25.45 -0.57 I 1! 5/15 24-0 20 Numerous 15 5/16 23-5 50 Not t~ken 16 5/16 28-0 24 Numerous 1606 2464 17 5/16 22-10 50 11-12 90 52.26 2.26 18 5/16 20-2 50 VS 11-12 90 52.26 2.26 19 5/16 22-1 20 VS 9-10 90 22.77 2.77 20 5/17 22-1 20 11-12 95 25.59 5.59 21 5/16 2'0-3 20 VS 9-11 95 23.39 J.39 22 5/16 24-11 20 VS 9-10 95 23.59 3.59 23 5/16 24-6 36 11-12 90 37.95 1.95 24 5/17 2&-9 56 9-12 80 55.78 -0.22 25 5/15 25-2 20 11-15 90 22.77 2.77 26 5/15 24-6 20 11-14 90 22.77 2.77 27 not on plan 28 5/15 22-B 24 11-12 95 27.29 3.29 29 5123 26-3 36 9-11 95 38.99 2,99 30 5/16 23-6 Solid 95 3.90 3,90 51 5/17 24-2 56 10-15 80 55.78 -0.22 52 5/17 25-6 20 11-1J 80 21.47 1.47 55 5/17 19-6 20 Numerous 34 5/17 23-6 20 US 10-11 95 23.39 3.39 55 5/28 23-10 20 I0-13 90 22.77 2.77 56 not on plan 57 5/15 27-9 20 9-12 80 21.47 1.47 58 5125 25-5 36 11-14 80 35.78 -0.22 39 5/17 27-0 56 VS 11-12 95 38.99 2.99 40 5116 22-5 20 US 9-11 90 22.77 2,77 41 5/17 22-0 20 US 9-10 95 23.39 5.39 42 5/17 21-9 20 9-12 BO 21.47 1.47 45 5/17 24-4 20 VS 9-10 95 23.39 3.39 44 5/23 26-4 36 VS 11-15 90 37.95 1.95 45 5/24 25-4 36 1-11 90 37.95 1.95 46 5/24 22-~ 20 12 70 20,08 0,08 ~091 4853 47 5/23 25-5 20 NA 48 not on plan 49 5/23 24-3 20 VS 9-11 90 22.77 2.77 50 5/25 28-3 50 9-12 90 52.26 2.26 51 5/24 27-0 56 VS 11-12 95 38.99 2.99 52 5/17 24-6 30 VS 9-12 80 30.41 0.41 53 5/17 22-4 20 US 8-10 90 22.77 2.77 C 0 P P E LI,/,-T,,O W N CENTER PIER TEST RESULTS Pier Date Depth Diam Seam % Sec. Elf. Di. Off Top Bott. 54 5/24 28-2 16 11-14 70 16.73 0,73 55 5/24 26-5 16 V8 10-11 95 19.49 3.49 55 5/28 23-1 24 VS 9-i1 BO 25.04 1.04 57 5/24 27-4 24 VS 9-11 90 26,58 2.56 58 5/23 30-5 24 VS 9-13 90 26.56 2,56 59 5/23 27-0 24 ¥S 10-I1 90 26.56 2.56 60 5/17 23-9 24 VS 9-11 80 25.04 1,04 61 5/23 22-5 16 VS 9-10 90 18.97 2.97 62 5/17 22-4 24 VS 11-12 90 26,56 2,56 63 5/23 24-10 24 V$ 9-11 90 26.56 2.56 3620 64 5/23 24-3 24 VS 9-11 90 26.56 2,56 65 5/23 25-5 20 VS 9-12 80 21.47 1.47 66 5/14 24-0 16 VS 9-11 90 18,97 2.97 67 5t14 26-10 16 9-11 85 18.44 2.44 68 5/14 26-4 16 VBAO TT~ V~y' ~ 69 5/14 25-0 16 Numerous 70 5/28 23-2 16 11-12 70 16.73 0.73 1370 1935 71 5/25 24-0 24 11-12 90 26.56 2.56 72 5/28 22-2 16 9-11 95 19.49 3.49 73 5/28 24-11 24 11-12 95 27.29 3.29 74 5/14 27-7 20 VSL 90 '22.77 2,77 75 5/14 27-0 20 9-14 BO 21.47 1.47 76 5/14 26-6 20 VS 9-11 90 22,77 2.77 77 5/14 26-0 20 9-14 70 20,08 O.OB 4479 4111 78 5/14 27-10 20 VS 95 23.39 3.39 4831 4762 79 not on plan BO 5/16 23-0 16 10-12 SO 17.89 1.89 81 5116 22-9 16 11-12 BO 17.8~ 1.89 82 5/16 25-10 16 9-11 90 18.97 2.97 83 5/16 24-3 16 9-12 80 17.89 1.89 3686 MANUAL OF CONCRETE PRACTICE SPECIFICATION CHECKLIST (cont.) Section/Parl/Article of ACI 336.1 Notes to the Designer/Specifier 2.3.1.2b Inspection and testing Specify inspection and testing procedures to be followed (it is recognized that procedures vary in different parts of country depending on pre- vailing geology and experience). Show bells on drawings. 2.3.1.2c Bells Specif.,,. limiting amount of loose material or water 2.3.1.5 Loose material permitted in hole at time of concrete placement. Specify any other acceptability requirements. 2.3.1.6 Disposal of excavated material Specify where. 2.3.2.1 Void space Specify whether grouting is required of any an- nular void space outside of permanent casing. 2.3.2.2 Removal of casing Specify removable or permanent Casing. 2.3.4.1 Dewatering Specify specific dewatering criteria. 2.3.4.2 Approval to place concrete Emphasize. 2.3.4.4 Free fall Specify any special concrete placement proced- ures required. 2.3.4.9 Tremie concrete Specify specific tremie procedures, such as: Mini- mum 7 to 9 in. slump, maximum 5~ in. aggregate, continuous tremie pipe, minimum pipe embed- ment in concrete at all times, continuous concrete placement, and static water ]eve] in hole prior to concrete placement. Specify coring or other special requirements of tremie concrete placement. 2.3.4.10 Concrete tests Specify requirements for making test cylinders and for testing. SECTION 1 ....GENERAL REQUIREMENTS 1.1--Scope 1.2.2 Allowable service load bearing pressure-- The vertical pressure per unit area that may be lA.l--This standard specification covers re/luire- applied to the bearing stratum at the level of the ments for end bearing drilled pier construction, pier bottom. Allowable service load bearing pres- 1.1.2--The provisions of this standard specifica- sure is normally selected by the Gcotechnical En- tion shall govern unless otherwise specified in the gineer on the basis of samples, tests, and applied contract documents. In case of conflicting require- soil mechanics, ~vith due regard for the character merits, the contract documents shall govern, of the loads to be applied and the settlements that -- can be tolerated. 1.2--Definitions 1.2.3 Architect-Engineer--The authority, such as The following definitions cover the meanings of the architect, the engineer, the architectural firm, certain words and terms as used in this standard the engineering firm, the contracting officer, or specification, other agent of the owner issuing project specifica- 1.2.1wAcceptable or accepted--Acceptable or ac- tions and drawings, and/or authorized by the - cepted by the Architect-Engineer or Geotechnical owner to administer work under the project doeu- , END BEARING DRILLED PIERS · - ~ 336.1-5 ' 1.2~4 Bearing stratum--The formations or layers 1.2.19 Specified--Defined in-the contract docu- of soil or rock that support the pier and the loads merits. imposed on it. 1.2.5 Bell--An enlargement at the bottom of the 1.2.20 Submitted--Submitted to the Architect- shaft for the purpose of spreading the load over Engineer for review. a larger area. - 1.2.6 Casing--Protective steel casing usually of 1.3---Notation cylindrical shape, lowered into the excavated hole The following abbreviations are defined for to protect workmen and inspectors entering the use in this standard specification. shaft from collapse or cave-in of the sidewalls 1.3.1--ACI: American Concrete Institute and for the purpose of excluding soft and water from the excavation. P.O. Box 19150 Detroit, Mich. 46219 1.2.7 Contract documents--Consist of the agree- 1.3.2--ASTM: American Society for Testing ment, conditions of the contract, contract specifica- tions, contract drawings, and all addenda thereto and Materials issued prior to the signing of the contract. 1916 Race Street Philadelphia, Pa. 19103 1.2.8 Contract drawings--Drawings which ac- company contract specifications and complete the 1.3.3--AWS: American Welding Society descriptive information for drilled pier construc- 2501 N.W. 7th Street tion work required or referred to in the contract Miami, Fla. 33125 specifications. 1.2.9 Contractor--The organization contracted 1.4--Reference standards with to carry out the work shown on the contract 1.4.l--The standards referred to in this Standard drawings and specifications. Specification ACI 336.1 are listed in Articles 1.4.2 1.2.10 Contract specifications--The specifications through 1.4.4 of this Section. with their complete which employ ACI 336.1 by reference and which designation and title including the year of adop- serve as the instrument for making the mandatory tion or revision and are declared to be a part of and optional selections available under the speci- this Standard Specification ACI 336.1 the same fication, as if fully set forth herein, unless otherwise indi- 1.2.11 End bearing drilled pier--Cast-in-place cared in the contract documents. foundation element with or without enlarged 1.4.2 ASTM standards bearing area extending downward through weaker soils or water to a rock or soil stratum capable of A 36-75 Standard Specification for Structural 'supporting the loads imposed on or within it. A Steel shaft diameter of 2¥~ ft (0.76 m) is the lower A 82-76 Standard Specification for ColdDraw_n limit for piers covered by these specifications. Steel Wire for Concrete Reinforce- 1.2.12 Geotech~icaI Engineer--The specialized ment engineer retained by the owner reporting to the A 252-75 Standard Specification for Welded Architect-Engineer and with responsibilities as defined herein, and Seamless Steel Pipe Piles 1.2.13 Testing Zaborator.v~The testing agency A444-75 Standard Specification for Steel retained by the owner to perform required tests Sheet, Zinc Coated (Galvanized) on the contract construction materials to verify by the Hot Dip Process for Culverts conformance with specifications, and Underdrains 1.2.14 Owner~Party that pays for approved A615-76a Standard Specification for Deformed work performed in accordance with drawings and and Plain Billet-Steel Bars for contract specifications and receives the completed Concrete Reinforcement work. A 616-76 Standard Specification for Rail-Steel 1.2.15 Permitted--Permitted by the Architect- Deformed and Plain Bars for Con- Engineer. crete Reinforcement 1.2.16 Qualified~Qualified by training and by A 617-76 Standard Specification for Axle-Steel experience on comparable projects. Deformed and Plain Bars for Con- 1.2.17 Required~Required by the contract docu- crete Reinforcement ments. A 706-76 Standard Specification for Low-Alloy 1.2.18 Shaft--Drilled pier above bearing surface Steel Deformed Bars for Concrete' exclusive of bell, if any. t, 336.1-6 ' MANUAL OF CONCRETE PRACTICE ~ C 39-72 Standard SpecifiCation for Compres- 1.5.2 Subsurface data--A subsurface investiga- sive Strength of Cylindrical Con- tion has been made by Logs of crete Specimens borings and test data are available for Contractor's E329-72 Standard Recommended Practice for information and for his interpretation as to soil Inspection and Testing Agencies for and water conditions that may be encountered at Concrete, Steel and Bituminous Ma- the site. Logs and test data are not represented as terials as Used in Construction complete description of the site soil and water in- 1.4.3 ACI standards formation bus only display what was found in 301-72 Specifications for Structural Concrete borings at the indicated locations. Contractor has (Revised for Buildings the right to obtain additional information, if neces- 1975) sary in his judgment. 318-77 Building Code Requirements for Re- 1.5.3 Existing underground utilities--Locate all inforced Concrete existing underground utilities and construction in 322-71 Building Code Requirements for the field by a qualified surveyor so as to deter- Structural Plain Concrete mine any conflicts with the work. Should conflicts 1.4.4 AWS standards be determined, do not proceed with the work un- 01.1 Structural Welding Code til the Architect-Engineer specifies method(s) to 012.1 Reinforcing Steel Welding Code eliminate the conflict. 1.5.4 Pre-job con~erence--The contract docu- 1.=. -Project conditions meats will specify if a pre-job conference is re- 1.5.1 E~camination o~ site--Visit (prior to sub- quired among the Architect-Engineer, the Con- mitring bid) to determine exis, ting surface condi- tractor(s), and the Geotechnical Engineer to tions, review special requirements for the work. SECTION 2--MATERIALS AND CONSTRUCTION PART 2.1gGENERAL f. Notification to Architect-Engineer to permit 2.1,1 Description--This section covers require- in-place inspection of reinforcing steel prior to ments for materials and construction for end bear- placing concrete lng drilled piers, and includes the following: g. Testing loboratory reports for concrete tests during construction 2.1.1.1 Excavation and casing, dewatering, gas testing and probing, h. Reports of actual location, alignment, eleva- 2.1.1.2 Reinforcing steel. - tions, and dimensions of drilled piers 2.1.1.3 Concrete. i. Reports of materials quantities, if specified 2.1.2 Submittals 2.1.3 Quality assurance 2.1.2.1 Geotechnical Engineer--Will submit 2.1.3.1 Geotechnica! Engi~eer--Will provide test reports to Architect-Engineer and to Con'trac- inspection of all phases of drilled pier construc- tor concerning allowable service load bearing tion, and request additional soil or rock testing pressures, elevations, dimensions, and alignment, if needed. 2.1.2.2 Contractor~Submit the following: 2.1.3.2 Contractor a. Reinforcing steel shop drawings a. Provide the services of a qualified surveyor b. Certified mill test reports for reinforcing for performing all surveys and layouts and to Steel determine vertical and horizontal alignments. b. Protect reinforcing steel from contamination. c. Evidence that proposed materials and mix designs conform to all requirements of "Specifi- 2.1.3.3 Testing laboratory~Will provide ser- cations for Structural Concrete for Buildings (ACI vices conforming to the requirements of ASTM 301-72) (Revised 1975)," except as modified by E 329, for sampling, testing, inspection, and re-. these specifications porting with respect to casing, reinforcing, and concrete. d. Detailed procedures for casing removal, if any 2.1.4 Constructiott tolerances e. Detailed procedures for tremie concrete, if 2.1.4.1 Bottom elevation of drilled piers as any shown are estimated from so/] boring data. Geo~ END BEARING DRILLED PIERS 336. i'~7 technical Engineer will determine actual final drawings call for an allowable service load bear- bearing level during excavation, ing pressure, extend excavation to suitable ma- - 2.1.4.2 Maximum permissible variation of lo- terial. cation--1/24th of shaft diameter or 3 in., which-_ 2.3.1.2 Determine suitability of supporting ma- ever is less. - terial for drilled piers, as follows: 2.1.4.3 Concrete shafts out of plumb--Not a. Explore bearing stratum to depth equal to more titan 1.5 percent of the length nor exceeding the diameter of the bearing area below the bot- t2.5 percent of shaft diameter or 15 in., whichever tom of the drilled pier with probe hole when dj- is less. rected by the Geotechnical Engineer. 2.1.4.4 If tile tolerances of Articles 2.1.4.2 and b. Inspection and testing at the bottom of each 2.1.4.3 are exceeded, furnish and pay for correc- pier will be by the Geoteehnieal Engineer. rive design and construction that may be required. c. Excavate for drilled pier bells (if required) 2.1.4.5 Concrete cut-off elevation tolerance-- immediately upon confirmation of the allowable Plus 1 in. to minus 3 in. service load bearing value by the Geotechnical 2.1.5 Delivery. handling, and storage of perma- Engineer. nentcasing d. If test results indicate the stratum is not 2.1.5.1 Deliver casing to site in undamaged capable of providing the required service load condition, bearing pressure, notify the Arehitect-Engineei' 2.1.5.2 Handle and protect casing to maintain for a determination of adjustments to be made. round within ±2 percent. These may include, but not be limited to. advanc- ing the shaft length as directed by the Geotechni- cal Engineer and repeating the above steps, or PART 2.2~MATERIALS enlarging the bell diameter as determined by the 2.2.1 Stee[casing Architect-Engineer for the appropriate bearing 2.2.1.1 ASTM A 252, Grade 2, or ASTM A 36, pressure as determined by the Geotechnical Eh- or ASTM A 444 corrugated steel, as specified, or gineer. as shown on the contract drawings. 2.3.1.3 Provide gas testing equipment, protec- 2.2.1.2 Furnish 100 percent penetration welds tire cage, or temporary casing of proper diameter, for vertical joints in noncorrugated permanent length, and thickness and other safety equipment casings, called for by law for inspection and testing of 2.2.1.3 For permanent casing requiring hard- drilled piers and to protect workmen during hand ened steel teeth for seating into rock, face weld belling or other operations necessitating entry into teeth with AWS electrodes, shaft. 2.2.2 Reinforcing steel~ASTM A 615, A 616, 2.3.1.4 Check each drilled pier for toxic and A 617 or A 706, as specified, or as shown on the explosive gases prior'to personnel entering. If gas contract drawings, is found, ventilate with forced air until safe for 2.2.3 Concrete--Concrete work shall conform to entry. all requirements of "Specifications for Structural 2.3.1.5 Remove from bottom of drilled piers, Concrete for Buildings (ACI 301-72) (Revised loose material or free water in quantities sufficient 1975)," except the following: to cause settlement or affect concrete strength as Sections 3.83, 3.84, Chapter 9 determined bx- the Geotechnical Engineer. Exca- and 3.85 Chapter 10 rate pier bottoms to a level plane. If bottoms are Chapter4 Chapter 11 sloping rock. excavate to a level plane or step Section 5.4 Chapter 12 with maximum step height less than one-quarter Sections 6.2, 6.3, Chapter 13 the width or diameter of the bearing area. 6.4 and 6.5 Chapter 14 2.3.1.6 Remove excavated material from site or Section 7.4 Chapter 15 as otherwise directed by the Architect-Eneineer. 2.2.4 Sand-cement 9rout~As specified for filling annular void outside permanent casing. 2.3.2 Steel casin.q 2.3.2.1 Provide steel casinff for shaft excava- PART 2.3~CONSTRUCTION tion where required. Provide casin~- of sufficient strength to withstand handlin~ stresses, concrete 2.3. l Excavation. soil testing, and inspection pressure, and surroundin~ earth and/or fluid 2.3.1.1 Excavate drilled piers to dimensions and pressures. Make diameter of excavation in rela- ~6.1-8 ' MANUAL OF CONCRETE PRACTICE permanent casing with minimum outside diameter gineer has verified allowable service load bearing equal to nominal outside diameter of shaft, capacity. Do not leave uncased or belled excava- 2.3.2.2 Casing may be removed at option of lions open overnight. Contractor unless otherwise specified. If casing is 2.3.4.4 Free fall concrete may be used pro- removed during or after concreting, follow special vided it is directed through a hopper, or equiva- requirements specified in Article 2.3.4. lent. such that fall is vertical down center of shaft 2.3.3 Reinforci)~.o steer without hitting sides or reinforcing. Vibrate top 2.3.3.1 Place reinforcement for drilled piers in 5 fl of concrete, but only after casing has been accordance with the contract documents, pulled or when casing is permanent. 2.3.3.2 Use reinforcement at time of placement 2.3.4.5 Place concrete in pier in one continuous which is free of mud. oil. or other coatings that operation. If a construction joint is unavoidable, adversely affec! bon(~ level, roughen, and clean surface prior to recom- 2.3.3.3 Reinforcement with rust, scale, or a mencement of concrete placement. Provide rein- combination of both may be used provided the forcing dowels or a shear key when required by minimum dimensions, including height of defor- the Architect-Engineer. mations and weight of wire brushed specimens. 2.3.4.6 If casing is withdrawn, the Geoteehnica] are not less than required by applicable ASTM Engineer wilt provide inspection during the re- specifications. Architect-Engineer will determine moral of easing and placing of concrete. With- acceptability of such reinforcement. draw casing only as shaft is filled with concrete. 2.3.3.4 Use metal reinforcement without kinks Maintain adequate head of concrete to balance out- or nonspecified bends. Straighten or repair bars in side soil and water pressure above the bottom of a manner that will not damage the bars or adja- the casing at all times during withdrawal. Specific cent construction, procedures that the Contractor will follow to ac- 2.3.3.5 Place bars as shown on contract draw- complish this objective shall be submitted for ings with cover of not less than 3 in. where ex- approval. posed to soil. 2.3.3.6 Make splices in reinforcement as shown 2.3.4.7 Where casing is removed, provide spe- on contract drawings unless otherwise accepted, cially designed concrete wi,th a minimum slumr~ 2.3.3.7 Provide clear distance between bars of of 5 in. and with a retarder to prevent arching not less than one and one-half times the bar di- ~f"concrete (during casing pulling) or setting of ameter, nor one and one-half times the maximum concrete until after casing is pulled. Cheek con- crete level prior to, during and after pulling cas- aggregate size. lng. Avoid vibrating concrete if casing is pulled. 2.3.4 Co~crete Pull casing before slump decreases below 5 in. as 2.3.4.1 Dewater drilled pier excavation prior to determined by testing. placing concrete. Perform pumping in a manner that will not create ground loss problems that 2.3.4.8 When casing is left in place, fill void might adversely affect this and existing adjacent space between casing and shaft excavation with structures as determined by the Geotechnical Eh- concrete or fluid grout by means of grout pipe and gineer. If during pumping excessive water inflow pump pressure as required. is noted, use alternative means to reduce inflow' 2.3.4.9 For placing concrete under water, such as extending casing, outside deep w. etls, or where permitted, use tremie pipe or concrete grouting, or other acceptable means. If water pumping with special procedures as specified or seepage still is considered by the Geotechnical Eh- accepted. gineer to be excessive for safe removal, follow 2.3.4.10 Co~crete tests~Take one set of four procedure specified in Article 2.3.4.9. cylinders per drilled pier but not more than one 2.3.4.20biain permission of Arehiteet-Engi- set per truck, or less than required by ACI 318-77. neet prior to placing concrete. Test one sample at 7 days and two at 28 days; 2.3.4.3 Place concrete immediately after eom- keep one sample in reserve for testing in the event pletion .of excavation and after Geotechnical En- o.f a low break. MATERIALS ANO NON(~$TRUCllV~ T~STING ~40 HUNT~.IFF. DR. CHARLOTTE. NORTH CAROUNA Z8211 (704) 377.4041 · (704~ 542,2223 PULSE ECHO NO~TDESTRUCTIVE EVALUATION OF PILES AT COPPELL TOWN CENTER COPPELL. TEXAS AND NO~q~ST~t,.~I'rVI~ CO4AJ~OT'TL NO~TJq CAJqO(.#~ 28211 377,40~1 · [70~ ~d2-2223 PULSE-ECHO NONDESTRUCTIVE EVALUATION OF PILE AT COPPELL TOWN CENTER BUILDING - COPPELL, TEXAS BY RICHARD A. MUENOW P.E. On June 7, 1985 a series of pulse-echo nondestructive tests (NDT) were conducted at the Coppell Town Center, Coppell, Texas. The purpose of our investigation was to determine the insitu condition of concrete used in approximately 79 pile. It was reported, that due to ground water flows, some cement matrix wash out may have occurred. This pro- ject was authorized by Jim Shilstone of Shilstone and Associates, Inc. of Dallas, Texas. All testing and data reduction was conducted by Richard Muenow of Muenow and Associates, Inc., of Charlotte, North Carolina. TEST TECHNIQUE The'theory of pulse-echo nondestructive testing for the evaluation of concrete and concrete structures is based upon Shell's Laws of Reflection and Refraction. This law states that as mechanical energy (sound waves) pass through a medium, a portion of the energy will be reflected as changes in density are encountered. These changes in density can be the opposite side of the structural member or internal discontinuities such as cracks, voids, honeycomb or'lack of consolidation associated with the reinforcement steel system. The pulse-echo NDT system not only identifies these internal ' discontinuities as to nature and characteristics, but will also delineate aerial extent and depth ~-lthin members. A measure of pulse velocity is also recorded which is a measure of the speed with which a sound wave propagates through a medium. This value of pulse velocity is then correlated to the ~niformity of concrete~ "E" values and the in situ compressive strengths. See enclosure for test procedure and general illustration of test method. TEST LOGISTICS Prior to our arrival on site most of pile tops had been cleaned off and concrete exposed. Testing consisted of introducing a stress wave in- to the pile by means of a spring loaded hammer. Immediately adjacent to the hammer position is a piezoelectric transducer which receives reflected energy from within a pile. Personnel from Howard Freeman Construction Co., the contractor, assisted in locating and identifying pile for our test records. Jay Shilstone operated the spring h-mmer and piezoelectric hammer. TEST DATA The attached tabulation reflects our test data interpretation; data includes, pile identification, depth of pile, depth to initial internal discontinuity and approximate remaining cross sectional area. Common characteristics to all pile are: 1) Top 6 to 18 inches of each pile appear to contain low density concrete. 2) Concrete below the 9 to 12 foot elevation is well consolidated and appears to transmit energy at a rate of 6.4 microseconds per inch. Propagation times such as these normally indicate strengths in the range excess of 3000 to 3500 PSI. 3) Concrete from the surface to between the 9 and 12 foot elevation appears to be of slightly low density, re- flecting transmission times of 6.8 to 7.6 microseconds per inch. Propagation times such as these normally in- dicate strengths in the range of 2500 PSI. 4) Reduction in cross sectional area, where indicated, appears to be circumferentially equal. 5) Test data comments indicating "slight seam'' at a particular depth means that an internal reflector was identified, but no reduction in cross section could be calculated. PIER NO. DEPTH COMMENTS 50 28' 0" 9-12 feet seam 90% X section 45 25' 3" 1-11 feet seam 90% X section 47 25' 5" Not Available 46 22' 3" 12 foot seam 70% X section 37 27' 9" 9-12 feet seam 80% X section 70 23' 2" 11-12 feet seam 70% X section 35 23' 0" 10-13 feet seam 90% X section 71- 24~ 0" 11-12 feet seam- 90% X section 28 22~ 8" 12 feet seam 95% X section 25 23~ 2" 12 feet seam 95% X section 26 24' 6" 11-13 feet seam 90% X section 14 24' 0" 11-I4 feet seam 90% X section 15 23' 3" Numerous Lenses 82 23' 10" 9-11 feet seam 90% X section 83 24' ~' 9-12 feet seam 80% X section PIER NO. DEPTH CO~KENTS 81 22t 9" 11-12 feet seam 80%-90% X section 5 24' 11" 9-12 feet seam 80% X section 80 23' 0" 10-12 feet seam 80%-90% X section 4 20' 8" 9-11 feet 90%-95% X section 3 18' 0" 12-14 feet 80%-90% X section 2 18' 3" 12-16 feet 90% X section 1 . VS seam 90%-95% X section 21 20' 3" VS seam 9-11 feet 95% X section 20 22' 1" VS_seam 11-12 feet 95% X section IA 23' 6" 11-13 seam 80%-90% x section 73 24' 0" VS seam 11-12 feet 95% X section 34 23' 6" VS seam 10-11 feet 95% X section 33 Numerous Lenes TT. PIER NO. DEPTH COI~NTS 22' 3" VS seam 9-11 feet 90% X section 72 22' 2" VS seam 9-11 feet 95% X section 43 24' 4" VS seam 9-10 feet 95% X section 42 21' 9" 9-I2 feet seam 80%-90% X section 41 22' 0" VS seam 9-10 feet 95% X section 69 25' 0" Numerous Lenses 67 26' 10" 9-11 feet seam 85% X section 66 24' 0" VS seam 9-11 feet 90% X section 23 24' 6" 11-12 feet seam 90% X section 17 22' 10" 11-12 feet seam 90% X section 12 23' 8" 11-12 feet seam 90% X section 9 27' 11" 11-12 feet seam 90% X section 10 29' 6" 11-13 feet seam 80%-90% X section PIER NO. DEPTH COMMENTS 39 27' 0" VS seam 11-12 feet 95% X section 44 26' 4" VS seam 11-13 feet 90%-95% X section 38 25' 5" 11-14 seam 80%-90% X section 51 27' 0" VSseam 11-12 feet 95% X section 55 26' 5" VS seam 10-11 feet 95% X section 54 28' 2" 11-14 feet seam 70%-80% X section 31 24' 2" 10-12 feet seam 80%-90% X section 22 24' 11" VS seam 9-10 feet 95% X section 74 27' 0" VSL seam 90%-95% 8 29' 5" VS seam 90%-95% 13 28' 10" 9-13 seam 70%-80% X section 75 27' 0" 9-14 feet 80%-90% X section 76 26' 6" 9-11 feet VS 90%-95% X section PIER NO. DEPTH COMPIENTS 77 26' 0" 9-14 seam 70X-90X X section 78 27' 10" VS seam 95~ X section 6 25' 5" VS seam 95Z X section '16 28' 0" Numerous Lenses 24 26' 9" 9-12 feet seam 80% X seciton 29 26' 3" 9-11VS seam 95% X section 30 23' 6" Solid 95Z X section 68 26' 4" VBAO Lenses TT 53 22' 4" VS seam 8-10 feet 90Z X section 52 24t 6" VS seam 9-12 feet 80%-90~ X section 60W VS seam 9-11 feet 80%-90Z X section 61W 22' 8" VS seam 9-10 feet 90Z X section 59 27' 0" VS seam 10-11 feet 90%-95Z X section PIER NO. DEPTH COHPIENTS 19 22' 1" VS seam 9-10 feet 90% X section 18 20' 2" VS seam 11-12 feet 90% X section* 11 23' 0" VS seam 11-13 feet 85%-90% X section 7 27' 9" 9-12 feet seam 90% X section 49 24' 3" VS seam 9-11 feet 90% X section 56W 23' 1" VS seam 9-11 feet 80%-90% X section 57W 27' 4" VS seam 9-11 feet 90% X section 65W 25' 5" VS seam 9-12 feet 80%-90% X section 64W 24' 3" VS seam 9-11 feet 90% X section 63W 24' 10" VS seam 9-11 feet 90% X section PIER NO. DEPTH COUNTS 58W 30~ 5" VS seam 9-13 feet 90Z X section 62W 22t 4" VS seam 11-12 feet 90~ X section 59~ 27t 0" VS seam 11-12 feet 90Z X section Coppell Town Center " MUENOW and ASSOCIATES, INC. Jo.- :' , . Materials and Nondestruct~'~Testin§ SHEET NO 3940 Huntcld! CHARLOTTE, NORTH CAROLINA 28211 CA~.cu~.^*rEO .v_l~spec~/nn nf ~i~LeS~____ (704) 377-4041 542-2223 C.ECK£O BV P__h.o__[to~ra_phic R~4~__rd SCALE .... · Coppell Town Centei ..' '~ MUENOW and ASSOCIATES, INC. JoB . . Materials an( Nondestrucv''~ ]estin:: s~rF, NO -C~PP-¢ ~-T~F~/,.~L____ oF -- 3940 Huntchll CHARLOTTE. NOR1H CAROLINA 282I] CALCULATED Bv~e~:n ~f ~1 ~S _J=B5 .... (704) 377-4041 5~2 · *i Coppeli Town Center · ' MUENOW and ASSOCIATES, INC. . Materials and Nondestructi~"~.sting 3940 Huntchft Drive CHARLOTTE. NORTH CAROLINA 2821] C^~CuL^,EDB*-~nS[;;tP.~On nf ~rles 5_-R~ __ (704) 3~ ~-404! 54!-2223 C.EC~,OB* ,_~_h_ot. gcjraphic R~.n.-~.~;d ___~ · ' '~. MUENOW an,5 ASSOCIATES, INC. ~o.---c,°ppell Town Center 3940 Huntclilf CHARLOTTE, N DRIH CAROLINA 28211 (704) 377-40~1 542-2223 c.~c~ro.~ ~hotoqraphic R~ SCALE · - Coppell Town Center .', MUENOW and ASSOCIATES, INC. Jo. " , , ~ Materials and NondestructiW"~cstin§ SHEET NO Co~.~.e~~L OF ,, 3940 Huntclifl Drive CHARLOTTE, NORTH CAROLINA 28211 CA~Cu.^,ED ,v_InsP~.~:JLl~:L~f_ 1~&~1 ~_~ 5-R~ __ (704) 377-404! 542-2223 C.ECKED Sv Ph_o_t_o_graphic R~c~q. rd SCALE -- -- .. ----C°ppell Town Center ',/ MUEhlOW and ASSOCIATES, INC. Jo. · , '," ~ Materials and Nondestructi/'"'esting SHEET .O _.COP~e.'v~-.Tt~;Ia;___ or __ 3940 Huntcl~H Dr~w CHARLO~E. NORTH CAROLINA 2821 l c,~cu~o e~nsp~~ ~es .~-RR _. (704) 377-4041 542-2223 C.EC~.* Photo~b~c R~d_. SCALE Ccppell Town Center ~.." MUtNOW and ASSOCIATES, INC. 3940 Huntchff Dr;~_ CHARLOTTE, NORTH CAROLINA 2821 ] (704) 377-4041 542-2223 CH£CKEDBY Photographic R~P__~_d. SCAI. £ --_ Coppell Town Center " MU'ENOW and ASSOCIATES, INC. ~o. .... . .L,... Materials and Non~-estruo'''''' Testing s.£[~ NO _~I;).D.P_f"~TP-.~S or, 3940 Huntclilt Dr, . CHARLO]-rE. NORTH CAROLINA 28211 . CALCULA'EO ov_.Irts~e~ nn~ ~i~ 5- fl 5 (704) 377-4041 542-2223 C.ECK~O ay_ Photogra_p..h__ic_R~c~3rd SCALE -- C