CF-Justice Center-CS 960530 (2)DEVELOPMENT REVIEW COMMITTEE
ENGINEERING COMMENTS
ITEM: Coppell Town Center Addition, Preliminar,] Plat and Replat
(drawing submitted is labelled as a Final PlaO, to create a single lot
that will allow the development of the Criminal Justice btdlding and
the future Fire Station tt3 as well as accommodate the existing Town
Center, located on south side of Parkway Blvd., approximately
295.50 feet from Denton Tap Road, at the request of Pacheco Koch
Consulting Engineers, Inc.
DRC DATE: May $0, 1996 and June 6, 1996
CONTACT: M'tke Martin, E.I.T., Assistant City Engineer ($04-$679)
COMMENT STATUS: ~'PRELIMINAR Y ~ ,v~4qI~E,D
1. On site plan, relocate sidewalk away from back of curb on Town Center and Parkway
Blvd.
2. Show all fire lanes on plat.
3~ Provide a total of 25' for utility easement on the east side of Town Center Blvd.