From:Kinsey, Matt <James.Kinsey@oncor.com>
Sent:Thursday, May 17, 2012 1:59 PM
To:Keith Marvin; Bryan Williams
Subject:RE: Sandy Lake Rd - Transmission Poles
Keith,
Thanks for the input. Please mail us a copy of that layout for our review. After we have had a chance to go over the drawing we will then
contact you about getting together to discuss everyone’s options.
Thanks again.
Matt Kinsey
ONCOR Electric Delivery Company
Transmission Engineering
115 W. 7th Street Suite 1105
Fort Worth, Texas 76102-7033
Phone:
(817) 215-6476 (Office)
(817) 999-2962 (Cell)
(817) 215-6274 (Fax)
Email:
mattkinsey@oncor.com
From: Keith Marvin [mailto:kmarvin@coppelltx.gov]
Sent: Wednesday, May 16, 2012 5:08 PM
To: Williams, Bryan; Kinsey, Matt
Subject: Fwd: Sandy Lake Rd - Transmission Poles
Matt/Bryan,
I took the transmission alignment that Matt sent me and had our consultant lay it out on our Sandy Lake Road
plans. See the attached PDF (attachment removed due to size). We have a few observations:
1. It appears a few of the pole locations may conflict with an existing 24" water line that belongs to the city.
2. There may be conflicts with some existing franchise utilities in the alignment as well.
3. It appears some of the poles fall outside the city owned right of way. In many of these cases they fall within a
platted utility easement. Does Oncor have the right to install transmission towers within this easement, or are you
asking the city to convey that right to you as part of this agreement?
4. Assuming we agree on locations for these poles, and we execute all necessary agreements, how do we preserve
these locations for your future use?
We look forward to discussing these issues, and any others needed to move forward with the removal of the existing
line.
Thanks,
Keith
Keith Marvin, P.E.
Project Engineer
1
(972) 304-3681
>>> "Chris B. Seely" <cseely@tnp-online.com> 5/16/2012 3:47 PM >>>
Keith:
Attached are exhibits showing the Oncor Transmission Pole and overhead transmission lines alignment per the color
exhibit we received on 4/18. I have noted the conflicts with the existing utilities. The transmission lines are over the
top of the 24” water line for approximately 1,800 feet from Cottonwood Drive to Oak Trail. It is also over the top of the
existing gas lines east of Oak Trail. I have not reviewed any solutions to these conflicts as of yet.
Chris
Chris Seely, P.E.
(TX)
Project Manager
TEAGUE NALL AND PERKINS, INC
.
17304 Preston Road Suite 1340
Dallas, Texas 75252
214.461.9867 phone
214.461.9864 fax
cseely@tnp-online.com
www.tnp-online.com
Confidentiality Notice: This email message, including any attachments, contains or may contain confidential
information intended only for the addressee. If you are not an intended recipient of this message, be advised
that any reading, dissemination, forwarding, printing, copying or other use of this message or its attachments is
strictly prohibited. If you have received this message in error, please notify the sender immediately by reply
message and delete this email message and any attachments from your system.
2