FOR COMPLETION OF COPPELL JOB #9646
SOFTWARE
ALARM HISTORY - AUTO DIALER
ALARM SPAN
CHECK TRENDS
· GALLONS IN MGD ON VP SCREEN
· GALLONS ON EST 1 AND 2 SCREEN
· INSTALL SECURITY ON COMPUTER
· FINISH REPORTS
SOFTWARE INTERFACE PROBLEMS WILL BE COMPLETED WEEK OF 3-10
INSTALLATION
· B-PONY BOARD FOR PUMP 1 (WHEN RECEIVED)
· HOLES LEAKING AT DEFOREST
· TAGS FOR PUMPS 5 AND 6
· COMPLETED WEEK OF 3-10
O & M MANUALS
· COMPLETED WEEK OF 3-10
TRAINING
SCHEDULED FOR THE WEEK OF 3-10
MONDAY 8:00 A.M. TO 5:00 P.M.
TUESDAY 8:00 A.M. TO 5:00 P.M.
WEDNESDAY 8:00 A.M, TO 12:00 NOON
SEE ATTACHED FOR AGENDA
CHANGE ORDERS AND OTHER
· RECONNECTING THE SOLYD1NE CLIPPERNET FOR THE DALLAS
INFLUENT FLOW WILL BE THE WEEK OF 3-10
· PRESSURE POINTS AT COPPELL AND MOORE ROAD WILL BE
APPROXIMATELY TWO TO THREE WEEKS AFTER RECEIVING P.O, OR
CHANGE ORDER
· ADDING THE EXISTING PRESSURE POINTS AND THE RTU's AT SANDY
LAKE AND DEFOREST LIFT STATIONS WILL BE 1 TO 2 WEEKS AFTER
RECEIVING P.O. OR CHANGE ORDER