From:Don Roundtree <don@tandem-consulting.net>
Sent:Friday, April 05, 2013 8:43 AM
To:Keith Marvin
Cc:Kyle Capps; Russell Saye
Subject:Re: West Sandy Lake Road
Keith, thanks for the update. We were just discussing this relocation and planning on starting work shortly. I
plan to visit the project with our contractor next week and will give you an update. We do not anticipate that
Coppell ISD relocation will hold your work up.
Don Roundtree, CSI, CCCA
Tandem Consulting, LLC
903-439-7217
www.tandem-consulting.net
From:
Keith Marvin <KMarvin@coppelltx.gov>
To:
"Michael Wisniewski <michael.wisniewski@tritextech.com> (michael.wisniewski@tritextech.com)"
<michael.wisniewski@tritextech.com>; "David Cheney <david.cheney@twcable.com> (david.cheney@twcable.com)"
<david.cheney@twcable.com>; "Phillip Gwin (phillip.gwin@twcable.com)" <phillip.gwin@twcable.com>; "Michael Cook
<mikehcook@hotmail.com> (mikehcook@hotmail.com)" <mikehcook@hotmail.com>; "Don Roundtree (don@tandem-
consulting.net)" <don@tandem-consulting.net>; "Kyle Capps (kcapps@capco-inc.com)" <kcapps@capco-inc.com>; "Cliff
Stephens (cstephens@henkels.com)" <cstephens@henkels.com>; "Brewster, Richard (Richard.Brewster@oncor.com)"
<Richard.Brewster@oncor.com>
Sent:
Friday, April 5, 2013 8:37 AM
Subject:
West Sandy Lake Road
Gentlemen,
I wanted to touch base and give you a status report on West Sandy Lake Road. We are currently advertising for
th
bids for the widening of Sandy Lake from Denton Tap to North Coppell Road. We open bids on April 25, and
st
construction is anticipated to begin on or about June 1 of this year.
I still see a lot of utility work that needs to take place in order for this project to be clear for us to begin. Please
respond to this email and let me know the status of your work on this project.
Thank you.
Keith Marvin, P.E.
City of Coppell
972-304-3681