ST9902-CS130419 (2)
Halie Hernandez
From:Casey McBroom <CMcBroom@TNPINC.com>
Sent:Friday, April 19, 2013 11:51 AM
To:Keith Marvin
Subject:RE: Sandy Lake Contractor questions
Great, thanks. I’ll incorporate these into the addendum in case there are others that can’t see them as well.
It’s looking like I should be in good shape to send you a draft later this afternoon.
Casey McBroom, P.E.
Project Engineer
17304 Preston Road, Suite 1340
Dallas, Texas 75252
214.461.9867 Phone
972.900.5733 Mobile
214.461.9864 Fax
cmcbroom@tnpinc.com
From: Keith Marvin [mailto:KMarvin@coppelltx.gov]
Sent: Friday, April 19, 2013 11:44 AM
To: Casey McBroom
Subject: RE: Sandy Lake Contractor questions
Casey,
Just in case you can’t see these, here are the questions on BidSync. Some have been answered, and some are
outstanding.
Question 1
Can you please give Engineer Estimate
(Submitted: Mar 29, 2013 3:59:06 PM CDT)
Answer
The estimate is $8,000,000
(Answered: Apr 1, 2013 11:27:38 AM CDT)
Question 2
Is Slipform Paving machine is required to place the concrete
(Submitted: Apr 1, 2013 1:24:06 PM CDT)
Answer
Yes, a slip form paving machine will be required to place the roadway paving.
(Answered: Apr 1, 2013 2:43:31
1
PM CDT)
Question 3
Can we submit a computer generated proposal that follow the same format as the original?
(Submitted: Apr 15, 2013 2:12:52
PM CDT)
Answer
No, please complete the bidform provided.
(Answered: Apr 16, 2013 8:23:10 AM CDT)
Question 4
Sheet 4 of Phase 2B - Typical Section for Cottonwood Drive refers to Cuty Standard 2110. This spec requires a lime treated
subgrade. Should the section for this street be cement treated?
(Submitted: Apr 16, 2013 2:01:29 PM CDT)
Question 5
Sheet 4 of Phase 2B - Typical Section for Cottonwood Drive refers to Cuty Standard 2110. This spec requires a lime treated
subgrade. Should the section for this street be cement treated?
(Submitted: Apr 16, 2013 2:01:35 PM CDT)
Question 6
NCTCOG section 103.4.2 requires Owners Protective Liability Insurace to be provided in addition to the General Liability. Is this
policy required?
(Submitted: Apr 16, 2013 2:04:13 PM CDT)
Answer
Yes, this is required.
(Answered: Apr 18, 2013 10:29:32 AM CDT)
Question 7
The notes regarding Temporary Paving in the plans for Phase 2A calls for 2" Type D on 6" Compacted Subgrade. 2B calls for 4"
Type D on 8" Flexbase. The specs calls for 2" Type B on 6" Flexbase. Which is correct?
(Submitted: Apr 16, 2013 3:15:15 PM CDT)
Keith Marvin, P.E.
City of Coppell
972-304-3681
From: Casey McBroom [mailto:CMcBroom@TNPINC.com]
Sent: Friday, April 19, 2013 9:06 AM
To: Jennifer Cook
Cc: Keith Marvin
Subject: Sandy Lake Contractor questions
Hi Jennifer
Were there any last minute contractor questions from yesterday?
Thanks.
Casey McBroom, P.E.
Project Engineer
17304 Preston Road, Suite 1340
2
Dallas, Texas 75252
214.461.9867 Phone
972.900.5733 Mobile
214.461.9864 Fax
cmcbroom@tnpinc.com
3