Creekview II L2-CS 930902 (2)Creekview Estates Limited Partnership September 2, 1993
8333 Douglas Avenue, Suite 1510
Dallas, Texas 75225-5811
RE: Creekview Estates II
Development Fee Assessment
Dear Sir:
Enclosed is a copy of the City of Coppell Development Fee Assessment list, along with a copy of the
development fee calculations for Lot 1, Block A and Lots 1 and 3, Block B of Creekview Estates II.
Please provide a check made payable to the City of Coppell in the amount of $3,300.00 and forward
it to Mr. Alan Johnson, Acting Finance Director, along with a copy of the fee assessment list. The
remaining monies due are payable at the time of building permit or the issuance of meters.
Please provide a copy of your paid receipt to our offices. Copies of your receipts will help us verify
payment of the required fees and assure a successful beginning of this project.
Please note that Section 1.06 of Ordinance 91533.1 (Impact Fees) states "No final plat shall be approved
unless the applicant has paid the impact fee imposed by and calculated hereunder". In this case, the
impact fee due for all four lots must be paid before the plat can be released to be filed at the county.
This includes the amount due by both Greg Gemoules and Creekview Estates Limited Partnership.
If you should have any questions, please do not hesitate to contact me.
Sincerely,
Kenneth M. Griffin, P.E.,
City Engineer
cc: Steve Goram, Director of Public Works
Alan Johnson, Acting Finance Director
Greg Jones, Building Official
Doug Stevens, Engineering Technician
Peter G. Smith, City Attorney dewlmt/crkview, fe¢
CITY OF COPPELL
DEVELOPMENT FEES
Date: August 24, 1993
Project: Creekview Estates H Lot 1, Block A & Lots 1 & 3, Block B
AMOUNT DUE
PRIOR TO
TOTAL COUNCIL
ASSESSMENT APPROVAL
Water Impact Fee $ 1,950.00 $ 1,950.00
(100% due prior to Council Approval)
Water Tap Inspection Fee $ 300.00 -0-
(100%due at Issuance of Building Permi0
Wastewater Impact Fee $1350.00 $ 1,350.00
(100% due prior to Council Approval)
Utility Final Inspection Fee $ 150.00 -O-
(100%due at Issuance of Building Permi0
Water Meter Fee (Lots) $ 66.75 -O-
(100%duc at Issuance of Building Permi0
Water Meter Fee (Irrigation) * -0-
(100%due at Issuance of Water Meters)
Water Meter Deposit $ 105.00 -0-
(100%due at Issuance of Building Permi0
Irrigation Meter Deposit * -O-
(100%due at Issuance of Water Meters)
TOTAL $ 3,921.75 $ 3,300.00
TOTAL AMOUNT DUE PRIOR TO $ 3,300.00
COUNCIL APPROVAL
* Irrigation Fees to be determined
at the time of development
COPpRnn PUBLIC WORKS
TO: Mike Martin, Graduate Engineer
I"_
The following fees should be assessed on the above referenced
project.
~* - %" x ~" Domestic Meter/s = 3 ESU's
1 - %" x ~" Irrigation Meter/s = 1 ESU's
Total ESU's ~ $650.00 ea =
100% due prior to Council approval of final plat.
Wastewater Impact (City)
.2*~ - %" x ~" Residential meters = 3 ESU's
Total ~'-- ESU's @ $450.00 ea
100% due prior to Council approval of the final plat.
Water Tap Inspection Fee
_~*S Connections ~ $100.00 each = $ ISO.O'3 ~"' ~
100% due prior to issuance of building permit. (Or in the case of
the irrigation meter-prior to issuance of meter).
100% due prior to issuance of building permit.
Utility Final Inspection Fee
,,?4.. lots
100% due prior issuance of b~ilding permit.
Development Fees
Page 2 ~_~_
Water Meter Fee (Lots)
m~. _ ~,, x ~" Domestic Meters ~ $22.25 ea = $66_,5
100% due prior to issuance of building permit.
Water Heter Fee (Irrigation)
- %" X ~" Irrigation Meters @ $22.25 ea = $22.25
- -I ........ I~igatio~r'-M~er ~ ,~" ,40 --ea
Total = ~
100% due prior to issuance of water meters.
Water Heter Deposit Commercial
Residential - ~ meters @ $35.00 ea = Si~.~
100% due prior to issuance of building permit.
Irrigation HeterDeposit
1 - ~" meters @ $35.00 ea = $
Total = $ .~
100% due prior to issuance of water meters.
CREEKVII .HLP