From:Harrison, Joe <Joe.Harrison@oncor.com>
Sent:Wednesday, May 22, 2013 2:31 PM
To:Keith Marvin
Cc:Lewis, Rick; Kinsey, Matt; dhallmark@chapmanconstruction.com; Little, Michael
Subject:FW: Coppell-Apollo Road 69 kV Line Schedule
Kevin,
We have had some emergencies on our system that has caused a delay in the above project. This is one on Sandy Lake
Rd.
We still plan on moving the existing line and poles in June. It looks like it will be about June 20th before we get started.
This project should only take about 5 working days.
Thanks
Joe Harrison
Construction Coordinator
214-724-8291 Cell
817-215-6702 Office
From: Kinsey, Matt
Sent: Tuesday, May 21, 2013 12:04 PM
To: Harrison, Joe
Cc: Lewis, Rick; Williams, Bryan
Subject: Coppell-Apollo Road 69 kV Line Schedule
Joe,
I got your voicemail concerning Sandy Road wreck-out. I understand that the storm damage has pushed everything back however, the city was
expecting us to be completed by June 15th so they could start on their road construction. Just give Keith Marvin a head's up on our schedule
being delayed due to emergency work so they can re-adjust their schedule as well.
Thanks
Matt
Matt Kinsey
Oncor Electric Delivery LLC
Transmission Engineering
115 W. 7th Street Suite 1105
Fort Worth, Texas 76102
Phone: Office 817-215-6476
Fax 817-215-6274
Cell 817-999-2962
mattkinsey@oncor.com
Confidentiality Notice: This email message, including any attachments, contains or may contain confidential
information intended only for the addressee. If you are not an intended recipient of this message, be advised that
any reading, dissemination, forwarding, printing, copying or other use of this message or its attachments is
strictly prohibited. If you have received this message in error, please notify the sender immediately by reply
message and delete this email message and any attachments from your system.
1