ST9902-CS130620 (6)
Halie Hernandez
From:Cheney, David <david.cheney@twcable.com>
Sent:Thursday, June 20, 2013 10:33 AM
To:Gwin, Phillip; Keith Marvin
Subject:RE: West Sandy Lake Road Construction
My bad Keith,
We also should be clear on Sandy Lake as well. Please let us know if you believe otherwise
thanks
From: Gwin, Phillip
Sent: Thursday, June 20, 2013 10:26 AM
To: Cheney, David
Subject: RE: West Sandy Lake Road Construction
This is Sandy Lake Rd., not Bethel Rd.
From: Cheney, David
Sent: Thursday, June 20, 2013 10:00 AM
To: Keith Marvin; Gwin, Phillip
Subject: RE: West Sandy Lake Road Construction
Keith, Phillip believes we did all TWC relocates last summer here, the one we worked with you closely on.
Are you believing TWC to still have conflicts or conflicts that still remain that were not addressed? Please let us know
Thanks Keith
From: Keith Marvin [mailto:KMarvin@coppelltx.gov]
Sent: Thursday, June 20, 2013 8:13 AM
To: Michael Cook <mikehcook@hotmail.com> (mikehcook@hotmail.com); Michael Wisniewski
<michael.wisniewski@tritextech.com> (michael.wisniewski@tritextech.com); Cheney, David; Gwin, Phillip; Steve Forsythe
(sforsythe@henkels.com); Box, Darin (DARIN) <darin.e.box@verizon.com> (darin.e.box@verizon.com); Don Roundtree
(don@tandem-consulting.net); Brewster, Richard (Richard.Brewster@oncor.com)
Cc: Rick Odell; Robert Caudill (rcaudill@TiseoPaving.com)
Subject: West Sandy Lake Road Construction
Gentlemen,
We have scheduled a pre-construction conference for the reconstruction of West Sandy Lake Road for Monday, June
th
24 at 10:00am at our new office at 265 Parkway Blvd. The limits of this project are Denton Tap to Coppell Road
th
North. We anticipate the contractor beginning work on or about July 8.
All of you are invited to attend this meeting. If you have contractors working on your relocations that you would like to
bring with you, or send in your place, please do so. My goal is to coordinate your remaining work with the
commencement of our work.
1
If you are unable to attend this meeting, please let me know the status of your relocations, and a firm date on when you
will be clear of the project.
Thanks for your help on this important project.
Keith
Keith Marvin, P.E.
City of Coppell
972-304-3681
This E-mail and any of its attachments may contain Time Warner Cable proprietary information, which is privileged, confidential, or subject to copyright belonging
to Time Warner Cable. This E-mail is intended solely for the use of the individual or entity to which it is addressed. If you are not the intended recipient of this E-
mail, you are hereby notified that any dissemination, distribution, copying, or action taken in relation to the contents of and attachments to this E-mail is strictly
prohibited and may be unlawful. If you have received this E-mail in error, please notify the sender immediately and permanently delete the original and any copy of
this E-mail and any printout.
2