Grapevine Creek-CS140529
SUMMARY
Stormwater Technical Subcommittee Meeting
Thursday, May 29, 2014
9:30 a.m., Tejas Room
Welcome attendees were welcomed.
Discussion Items
1.2013 Recap
NCTCOG provided an overview of 2013 program highlights covering the last year an
the subcommittee met. Notably, the adoption process for the I-Plan took roughly 14 months
from submission to adoption by TCEQ Commissioners in December 2013.
2.First Annual Meeting
Because this was the first time the subcommittee had met since the adoption of the I-Plan,
those present reviewed the Stormwater Coordination implementation strategies for any
immediate concerns as well as strategies already being implemented. Because the Planning and
Development technical subcommittee did not have enough current m
Stormwater subcommittee also reviewed those implementation strat
Local Supplemental Environmental Projects have yet to be implemeial use to
every municipal MS4 is Arlingtons development of a unified stor
estimates the draft is 50% - 60% completed. Dallas continues to move ahead with tying
stormwater tax to impervious surfaces. Arlington mentioned the possibility of using total
suspended solids as a proxy for bacteria. Interagency communica
across the board. Mention was given to having an award given to green infrastructu
projects on alternating years with CLIDE.
3. Recommendations for Coordination Committee
The primary recommendations of the Stormwater subcommittee were for NCTCOG to move
ahead with the BMP Library (Implementation Strategy 8.0) and focus its efforts -
related programs. Identifying some BMPs for the library may be a matter of looking at an MS4s
annual report, either available online or by request.
Department of Environment and Development P.O. Box 5888 Arlington, Texas 76005-5888 817-695-9210