ST9902-CS130813 (2)
Halie Hernandez
From:Robert Caudill <rcaudill@TiseoPaving.com>
Sent:Tuesday, August 13, 2013 12:02 PM
To:Keith Marvin
Cc:Lance Smith; Rick Odell
Subject:Re: West Sandy Lake Road
I will agree on the price for the 8" PVC on 2A, but need the prices as stated.
Sent from my iPhone
On Aug 13, 2013, at 10:49 AM, "Keith Marvin" <KMarvin@coppelltx.gov> wrote:
Robert,
We have a pay item in the contract for 8” water line and 8” gate valves. This seems like a simple matter
of over running plan quantities.
Keith Marvin, P.E.
City of Coppell
972-304-3681
From: Robert Caudill [mailto:rcaudill@TiseoPaving.com]
Sent: Tuesday, August 13, 2013 6:38 AM
To: Keith Marvin
Cc: Rick Odell; Robert Caudill; Lance Smith
Subject: West Sandy Lake Road
Keith;
Below are the prices for extra work.
1.Water Line Relocation
A.8” PVC Water Line – 40LF @ $116.50/LF = $4,660.00
B.Fittings & Blocking – 1LS @ $1,725.00/LS = $1,725.00
C.8” FLG Gate Valve at 13’ Depth – 1EA @ $2,530.00/EA = $2,530.00
Total for Water Line Relocation $8,915.00
Robert Caudill
Vice President
Tiseo Paving Company
(972) 289-0723