WA9302A-CN 971105 SHIMEK, JACOBS & FINKLEA, L.L.P. t,u ~ q"5'D 9__ ~
CONSULTING ENGINEERS
8333 Douglas Avenue, #820 Dallas, Texas 75225-5816 Fax (214) 361-0204 Phone (214) 361-7900
ROSS L. JACOBS, P.E.
RONALD V. CONWAY, P.E.
JOHN W. BIRKHOFF, P.E.
ton R. CARTnR, P.n. November 5, 1997
GARY C. HENDRICKS, P.E.
I. C. FINKLEA, P.E.
Mr. Michael G. Daigre
North Texas Municipal Construction Co., Inc.
5614 Dyer Street
Dallas, Texas 75206
Re: City of Coppell
Village Parkway Pump Station Addition
Change Order No. 6 (Revised)
Dear Mr. Daigre:
We are enclosing two (2) fully executed copies of Change Order No. 6 (Revised) to your contract with the
City of Coppell for the construction of the Village Parkway Pump Station Addition. These copies are for your
records.
~Sincerel~
Sincerely. ,~ars
Enclgsure
C/e(. Mr. Ken Griffin, P.E.
CITY OF COPPELL, TEXAS
VILLAGE PARKWAY PUMP STATION ADDITION
PROJECT NO. WA-9302
BID NO. Ql195-02
CHANGE ORDER NO. 6 (Revised).
A. INTENT OF CHANGE ORDER
The intent of this change order is to modify the provisions of the contract entered into by the City of Coppell,
Texas and North Texas Municipal Construction, Inc., 5614 Dyer Street, Dallas, Texas 75206, for construction
of the Village Parkway Pump Station Addition, dated January 9, 1996.
B. DESCRIPTION OF CHANGE
1. The City of Coppell hereby agrees to a request by North Texas Municipal Construction Co., of contract
time extension of 110 calendar days.
2. Pay Items Nos. 4, 5 and 6 are not required to complete this project and are eliminated by this Change
Order.
3. North Texas Municipal Construction Co., hereby agrees to a reduction in the total contract amount of
$2,275.
4. North Texas Municipal Construction Co., hereby agrees to a reduction in the SCADA Change Order
(Change Order No. 2), in the lump sum amount of $2,500 based on the agreed rate of $500 per day from
10/1/97 through final acceptance of the SCADA System on October 5, 1997.
C. EFFECT OF CHANGE ON CONTRACT AMOUNT
This change will have the following affect on the final contract amount:
Original Revised Change Revised
Item Contract Contract Order Contract
No. Description Units Quantity Quantity Unit Price Amount
4 Extra Class "A" Reinforced Concrete C.Y. 25 0 $350.00 ($8,750.00)
5 Extra Class "C" Concrete Backfill C.Y. 25 0 300.00 ($7,500.00)
6 Extra Crushed Stone C.Y. 25 0 35.00 ($875.00)
30 Contract Amount Adjustment L.S. 0 1 ($2,275.00) ($2,275.00)
31 SCADA System Contract Adjustment L.S. 0 I ($2,500.00) ($2,500.00)
~ Total Amount of Change ] ($21,900.00)
J:\CoppellX94156~pecs\CO-6.doc Page ] of 2
City of Coppell
Village Parkway Pump Station Add~s
Change Order No. 6
Original Contract Amount $933,000.00
Amount, Change Order No. 1 (5,000.00)
Amount, Change Order No. 2 152,739.00
Amount, Change Order No. 3 18,415.00
Amount, Change Order No. 4 2,991.00
Amount, Change Order No. 5 8,552.00
Amount, Change Order No. 6 (21,900.00)
Revised Contract Amount $1,088,797.00
D. EFFECT OF CHANGE ON CONTRACT TIME
The changes identified above will add 110 calendar days to the revised contract time.
Original Contract Time: 300 Calendar Days
Calendar Days, Change Order No. 1 0 Calendar Days
Calendar Days, Change Order No. 2 60 Calendar Days
Calendar Days, Change Order No. 3 0 Calendar Days
Calendar Days, Change Order No. 4 30 Calendar Days
Calendar Days, Change Order No. 5 30 Calendar Days
Calendar Days, Change Order No. 6 110 Calendar Days
Revised Contract Time 530 Calendar Days
By the signatures below of duly authorized agents, the City of Coppell, Texas and North Texas Municipal
Construction Company, Inc., do hereby agree to append this Change Order No. 6 to the original contract
between themselves, dated January 9, 1996.
City of Coppe!l, Texas North Texas Municipal Construction Company, Inc.
Contractor
Attest: Attest: ~ ~__~~
J:\Coppelr~94156\CO.-6.doc Page 2 of 2