ST9902-CS130405 (9)
Halie Hernandez
From:Casey McBroom <CMcBroom@TNPINC.com>
Sent:Friday, April 05, 2013 11:55 AM
To:Keith Marvin
Subject:RE: West Sandy Lake Road
Attachments:[Untitled]_0405201316522800.pdf
A possible conflict I see would be the section highlighted in the attached PDF. I’m concerned they may not be low
enough through here to be safely beneath the barrier free ramps, and then out of the way of the wall footing. They
really need to be down in the 496 range when they pass underneath the wall.
Everything else appears to be OK upon quick inspection.
Casey McBroom, P.E.
Project Engineer
17304 Preston Road, Suite 1340
Dallas, Texas 75252
214.461.9867 Phone
972.900.5733 Mobile
214.461.9864 Fax
cmcbroom@tnpinc.com
From: Keith Marvin [mailto:KMarvin@coppelltx.gov]
Sent: Friday, April 05, 2013 9:55 AM
To: Casey McBroom
Subject: FW: West Sandy Lake Road
Casey,
Can you look at the attached Atmos permit and provide feedback on their relocations?
Thanks.
Keith Marvin, P.E.
City of Coppell
972-304-3681
From: Michael Wisniewski [mailto:Michael.Wisniewski@tritextech.com]
Sent: Friday, April 05, 2013 9:18 AM
To: Keith Marvin
Subject: RE: West Sandy Lake Road
1
Keith,
Attached is an updated drawing for the Atmos Permit. We have incorporated the new walls and the additional drainage
in the area. Please review the attached drawing and let me know if the city approves. Once we have an approve on the
drawings I will send the contractor up to sign for the permits and update the start and completion dates.
Thanks,
Michael Wisniewski
TriTex Technologies, Inc.
5339 Alpha Road, Suite 215
Dallas, Tx 75420
Office: (972) 233.2536
Fax: (972) 233.5160
From: Keith Marvin [mailto:KMarvin@coppelltx.gov]
Sent: Friday, April 05, 2013 8:37 AM
To: Michael Wisniewski; David Cheney <david.cheney@twcable.com> (david.cheney@twcable.com); Phillip Gwin
(phillip.gwin@twcable.com); Michael Cook <mikehcook@hotmail.com> (mikehcook@hotmail.com); Don Roundtree
(don@tandem-consulting.net); Kyle Capps (kcapps@capco-inc.com); Cliff Stephens (cstephens@henkels.com); Brewster,
Richard (Richard.Brewster@oncor.com)
Subject: West Sandy Lake Road
Gentlemen,
I wanted to touch base and give you a status report on West Sandy Lake Road. We are currently advertising for bids for
th
the widening of Sandy Lake from Denton Tap to North Coppell Road. We open bids on April 25, and construction is
st
anticipated to begin on or about June 1 of this year.
I still see a lot of utility work that needs to take place in order for this project to be clear for us to begin. Please respond
to this email and let me know the status of your work on this project.
Thank you.
Keith Marvin, P.E.
City of Coppell
972-304-3681
2