ST0502A-LR150121 (2)G1 • GEOTECHNICAL ENGINEERING E I • ENVIRONMENTAL CONSULTING E I • CONSTRUCTION MATERIALS TESTING GEE Consultants , Inc. 10046 Monroe Drive • Dallas, Texas 75229 • (214) 352-5433 • Fax (214) 352-6972 REPORT OF CONCRETE MIN. OBSERVATION Report Date: January 21, 2015 Date Concrete Placed: November 18, 2014 Standard 6"xl2" Cylinders Client: City of Coppell Cylinder Cross-sectional Area: 28.27 Square Inches Project: Freeport Pkwy from Ruby Rd. to Sandy Lake Rd. Concrete Report No.: 83 Contractor: CD Builders Inc. Project No.: 214-0144 Concrete Supplier and Plant: Argos #110 Location of Placement: Pavement North bound MATERIALS Source / SSD Batch Wts. OBSERVATION DATA Descriation (Lbs/CuYd) Mix Number: 1253 Time Sample Batched: 9:34 AM Cement: Time Sampled: 10:15 AM Fly Ash: Sample Location: STA. 2+40 7 Truck / Ticket No: 9020 /1527491 Coarse Aggregate: Temperature: FPP 330 Intermediate Aggregate: Ambient Range: 45 OF Fine Aggregate: Concrete Range: 58 OF Admixtures: Slump Range (inches): 2.1/4 1 Weather Conditions: Sunny 2 Time Started: 8:00 AM Added Water: 0 Time Completed: 6:00 PM Sample Air Content (%): 3.8 Total Cubic Yards Placed: 300 Fracture Regular Required Strength (Lbs./sa.in.): 3600 Specimen Number Measured Slump (in.) Age (Days) Date Tested Total Load (Lbs.) Compressive Strength (Lbs./Sq.In.) Remarks FPP 329 7 11/25/14 101,120 3,580 FPP 330 28 12/16/14 128,540+ 4,550+ FPP 331 2.25 28 12/16/14 129,460+ 4,580+ FPP 332 H Hold Test Methods Utilized Fracture Regular Cylinders Made By: CP ASTM C-31, C-39, C-143 (Unless Noted Otherwise) Remarks and/or Distribution:- None cc: Mr. Larry Davis - City of Coppell, Phone: 972-304-3684; via Fax: 972-304-3570 Mr. Michael Garza - City of Coppell, Phone: 972-304-3679; via E-mail: MGarza@coppelltx.gov Mr. Mitch Holmes - Teague, Nall & Perkins, Phone: 432-312-4205; via E-mail: mholmes@tnpinc.com Mr. Francisco Luyando - CD Builders, Inc., Phone: 787-688-8207; via E-mail: fluyando@cdbuilderspr.eom GEE Consultants, Inc TBPE Firm: F-3212 Reviewed by: I �' k" All letters and reports are for the exclusive use of the client to whom they are addressed and shall not be reproduced without the full approval of GEE Consultants Inc The use of our name must receive our prior written approval. Our tetters and reports apply only to the sample tested and/or observed and are not necessarily indicative of the quantities of apparently identical or similar products. G1 • GEOTECHNICAL ENGINEERING E • ENVIRONMENTAL CONSULTING E I • CONSTRUCTION MATERIALS TESTING GEE Consultants, Inc. 10046 Monroe Drive • Dallas, Texas 75229 • (214) 352-5433 • Fax (214) 352-6972 Report Date: January 21, 2015 Date Concrete Placed: November 18, 2014 Standard 6"x12" Cylinders Client: City of Coppell Cylinder Cross-sectional Area: 28.27 Square Inches Project: Freeport Pkwy from Ruby Rd. to Sandy Lake Rd. Concrete Report No.: 84 Contractor: CD Builders Inc. Project No.: 214-0144 Concrete Supplier and Plant: Argos #110 Location of Placement: Pavement North bound STA3+20 MATERIALS Source / SSD Batch Wts. OBSERVATION DATA Description (Lbs/CuYd) Mix Number: 1253 Time Sample Batched: 12:11 PM Cement: Time Sampled: 12:45 PM Fly Ash: Sample Location: Sta. 3+20 7 Truck / Ticket No: 5114 /1527763 Coarse Aggregate: Temperature: FPP 334 Intermediate Aggregate: Ambient Range: 56 OF Fine Aggregate: Concrete Range: 58 OF Admixtures: Slump Range (inches): 2.25 1 Weather Conditions: Clear 2 Time Started: 8:00 AM Added Water: 0 Time Completed: 6:00 PM Sample Air Content (%): 4.0 Total Cubic Yards Placed: 110 Fracture Regular Rennired Strentith (Lbs./sa.in.): 3600 Specimen Number Measured Slump (in.) Age (Days) Date 'Tested Total Load (Lbs.) Compressive Strength (Lbs./Sq.ln.) Remarks FPP 333 7 11/25/14 132,700 4,690 FPP 334 28 12/16/14 133,720+ 4,730+ FPP 335 2.25 28 12/16/14 137,060+ 4,850+ FPP 336 H Hold Test Methods Utilized Fracture Regular Cylinders Made By: CP ASTM C-31, C-39, C-143 (Unless Noted Otherwise) Remarks and/or Distribution:- None cc: Mr. Larry Davis - City of Coppell, Phone: 972-304-3684; via Fax: 972-304-3570 Mr. Michael Garza - City of Coppell, Phone: 972-304-3679; via E-mail: MGarza@coppelltx.gov Mr. Mitch Holmes - Teague, Nall & Perkins, Phone: 432-312-4205; via E-mail: mholmes@tnpinc.com Mr. Francisco Luyando - CD Builders, Inc., Phone: 787-688-8207; via E-mail: fluyando@cdbuilderspr.com e GEE Consultants, Inc.TBPE Firm: F-3212 Reviewed by: All letters and reports are for the exclusive use of the client to whom they are addressed and shall not be reproduced without the full approval of GEE Consultants, Inc. The use of our name must receive our prior written approval. Our letters and reports apply only to the sample tested and/or observed and are not necessarily indicative of the quantities of apparently identical or similar products. G1 • GEOTECHNICAL ENGINEERING E • ENVIRONMENTAL CONSULTING E I • CONSTRUCTION MATERIALS TESTING GEE Consultants, Inc. 10046 Monroe Drive • Dallas, Texas 75229 • (214) 352-5433 • Fax (214) 352-6972 Report Date: January 21, 2015 Date Concrete Placed: November 18, 2014 Standard 6"x12" Cylinders Client' City of Coppell. Cylinder Cross-sectional Area: 28.27 Square Inches Project: Freeport Pkwy from Ruby Rd. to Sandy Lake Rd. Concrete Report No.: 85 Contractor: CD Builders Inc. Project No.: 214-0144 Concrete Supplier and Plant: Argos #I 10 Location of Placement: Pavement North bound MATERIALS Source / SSD Batch Wts. OBSERVATION DATA Description (Lbs/CuYd) Mix Number: 1253 Time Sample Batched: 1:34 PM Cement: Time Sampled: 3:15 PM Fly Ash: Sample Location: Sta. 4+20 7 Truck / Ticket No: 5114 /1527763 Coarse Aggregate: Temperature: FPP 338 intermediate Aggregate: Ambient Range: 57 OF Fine Aggregate: Concrete Range: 62 OF Admixtures: Slump Range (inches): 2.5 1 Weather Conditions: Clear 2 Time Started: 8:00 AM Added Water: 0 Time Completed: 6:00 PM Sample Air Content N: 3.8 Fracture Regular Total Cubic Yards Placed: 200 (Unless Noted Otherwise) Do ....o4 Ctr nnth (i he /en in )- iFnn Specimen Number Measured Slump (in.) Age (Days) Date Tested Total Load (Lbs.) Compressive Strength (Lbs./Sq.In.) Remarks FPP 337 7 11/25/14 107,620 3,810 FPP 338 28 12/16/14 129,540+ 4,580+. FPP 339 2.5 28 12/16/14 129,700+ 4,590+ FPP 340 H Hold Test Methods Utilized Fracture Regular Cylinders Made By: CP ASTM C-31, C-39, C-143 (Unless Noted Otherwise) Remarks and/or Distribution:- None cc: Rick Odell <ROdell@coppelltx.gov> Mr. Michael Garza - City of Coppell, Phone: 972-304-3679; via E-mail: MGarza@coppelltx.gov Mr. Mitch Holmes - Teague, Nall & Perkins, Phone: 432-312-4205; via E-mail: mholmes@tnpinc.com Mr. Francisco Luyando- - CD Builders, Inc., Phone: 787-688-8207; via E-mail: fluyando@edbuilderspr.com GEE Consultants, Inc TBPE Firm: F-3212 Reviewed by ( c. All letters and reports are for the exclusive use of the client to whom they are addressed and shall not be reproduced without the full approval of GEE Consultants Inc.the use of our name must receive our prior written approval. Our letters and reports apply only to the sample tested and/or observed and are not necessarily indicative of the quantities of apparently identical or similar products. -INICAL ENGINEERING VIRONMENTAL CONSULTING • CONSTRUCTION MATERIALS TESTING GEE Consultants, Inc. 10046 Monroe Drive + Dallas, Texas 75229 • (214) 352-5433 ® Fax (214) 352-6972 Report Date: January 21, 2015 Date Concrete Placed: Client: City of Coppell Project: Freeport Pkwy from Ruby Rd. to Sandy Lake Rd. Contractor: CD Builders Inc. Concrete Supplier and Plant: Argos #110 Location of Placement: Slab Bridge Stagel(ION'of abudamentl) November 25, 2014 Standard 6"xt2" Cylinders Cylinder Cross-sectional Area: 28.27 Square Inches Concrete Report No.: 91 Project No.: 214-0144 MATERIALS Source / SSD Batch Wts. OBSERVATION DATA Description (Lbs/CuYd) Mix Number: Cement: Fly Ash: Coarse Aggregate: Intermediate Aggregate: Fine Aggregate: Admixtures: Added Water: 1251 Time Sample Batched: 9:57 AM Time Sampled: 10:30 AM Sample Location: 10`N of abudamentl Truck / Ticket No: 3041 /1532592 Temperature: Ambient Range: 56 OF Concrete Range: 62 OF Slump Range (inches): 4 Weather Conditions: Sunny Time Started: 8:30 AM Time Completed: 6:00 PM Sample Air Content (%): 3.8 Total Cubic Yards Placed: 20 Recntire.cl Strength (Lbs./sa.in.): 4000 Specimen Number Measured Slump (in.) Age (Days) Date Tested Total Load (Lbs.) Compressive Strength (Lbs./Sq.In.) Remarks FPP 361 7 12/2/14 118,340 4,190 FPP 362 28 12/23/14 127,340+ 4,500+ FPP 363 4 28 12/23/14 130,000+ 4,600+ FPP 364 H Hold Test Methods Utilized Fracture Regular Cylinders Made By: CP ASTM C-31, C-39, C-143 (Unless Noted Otherwise) Remarks and/or Distribution:- None cc: Rick Odell <ROdell@coppelltx.gov> Mr. Michael Garza - City of Coppell, Phone: 972-304-3679; via E-mail: MGarza@coppelltx.gov Mr. Mitch Holmes - Teague, Nall & Perkins, Phone: 432-312-4205; via E-mail: mholmes@tnpinc.com Mr. Francisco Luyando - CD Builders, Inc., Phone: 787-688-8207; via E-mail: fluyando@cdbuilderspr.com GEE Consultants, Inc TBPE Firm: F-3212 Reviewed All letters and reports are for the exclusive use of the client to whom they are addressed and shall not be reproduced without the full approval of GEE Consultants Inc The use of our name must receive our prior written approval. Our letters and reports apply only to the sample tested and/or observed and are not necessarily indicative of the quantities of apparently identical or similar products. G1 * GEOTECHNICAL ENGINEERING E I * ENVIRONMENTAL CONSULTING E I* CONSTRUCTION MATERIALS TESTING GEE Consultants, Inc. 10046 Monroe Drive Dallas, Texas 75229 0 (214) 352-5433 0 Fax (214) 352-6972 Report Date: January 21, 2015 Date Concrete Placed: November 25, 2014 Standard 6"x12" Cylinders Client: City of Coppell Cylinder Cross-sectional Area: 28.27 Square Inches Project: Freeport Pkwy from Ruby Rd. to Sandy Lake Rd. Concrete Report No.: 92 Contractor: CD Builders Inc. Project No.: 214-0144 Concrete Supplier and Plant: Argos #105 Location of Placement: Slab Bridge Stage I MATERIALS Source / SSD Batch Wts. OBSERVATION DATA Description (Lbs/CuYd) Mix Number: 1251 Time Sample Batched: 2:20 PM Cement: Time Sampled: 2:50 PM Fly Ash: Sample Location: Slab Bridge stage 1(30's of Coarse Aggregate: 12/2/14 abudament 4) Intermediate Aggregate: Truck I Ticket No: 4005 /1532906 Fine Aggregate: Temperature: 12/23/14 128,380+ Ambient Range: 65 OF Admixtures: Concrete Range: 66 OF I Slump Range (inches): 3.5 2 Weather Conditions: Sunny Added Water: 0 Time Started: 8:30 AM Time Completed: 6:00 PM Fracture Regular Sample Air Content (%): 3.6 (Unless Noted Otherwise) Total Cubic Yards Placed: 130 Rennired Strength (Lhs./so.in.): 4000 Specimen Number Measured Slump (in.) Age (Days) Date Tested Total Load (Lbs.) Compressive Strength (Lbs./Sq.1n.) Remarks FPP 365 7 12/2/14 122,120 4,320 FPP 366 28 12/23/14 128,380+ 4,540+ FPP 367 3.5 28 12/23/14 129,380+ 4,580+ FPP 368 H Hold Test Methods Utilized Fracture Regular Cylinders Made By: CP ASTM C-31, C-39, C-143 (Unless Noted Otherwise) Remarks and/or Distribution:- None cc: Rick Odell <ROdell@coppelltx.gov> Mr. Michael Garza - City of Coppell, Phone: 972-304-3679; via E-mail: MGarza@coppelltx.gov Mr, Mitch Holmes - Teague, Nall & Perkins, Phone: 432-312-4205; via E-mail: mholmes@tnpinc.com Mr. Francisco Luyando - CD Builders, Inc., Phone: 787-688-8207; via E-mail: fluyando@cdbuilderspr.com GEE Consultants, Inc. TBPE Firm: F-3212 Reviewed by: All letters and reports are for the exclusive use of the client to whom they are addressed and shall not be reproduced without the full approval of GEE Consultants, Inc, The use of our name must receive our prior written approval. Our letters and reports apply only to the sample tested and/or observed and are not necessarily indicative of the quantities of apparently identical or similar products, G1 * GEOTECHNICAL ENGINEERING ENVIRONMENTAL CONSULTING E I* CONSTRUCTION MATERIALS TESTING GEE Consultants, Inc. 10046 Monroe Drive • Dallas, Texas 75229 • (214) 352-5433 0 Fax (214) 352-6972 Report Date: January 21, 2015 Date Concrete Placed: November 26, 2014 Standard 6"xl2" Cylinders Client: City of Coppell Cylinder Cross-sectional Area: 28.27 Square Inches Project: Freeport Pkwy from Ruby Rd. to Sandy Lake Rd. Concrete Report No.: 93 Contractor: CID Builders Inc. Project No.: 214-0144 Concrete Supplier, and Plant: Argos #110 Location of Placement: Bike Trail MATERIALS Source / SSD Batch Wts. OBSERVATION DATA Description (Lbs/CuYd) Mix Number: 1049 Time Sample Batched: Cement: Time Sampled: Total Load (Lbs.) Sample Location: Fly Ash: Truck / Ticket No: Coarse Aggregate: Temperature: Intermediate Aggregate: Ambient Range: Fine Aggregate: Concrete Range Admixtures: Slump Range (inches): I Weather Conditions: 2 Time Started: Added Water: 0 Time Completed: 127,820+ Sample Air Content (%): FPP 372 Total Cubic Yards Placed: Hold Reauired Strength (Lbs./sq Specimen Number Measured Slump (in.) Age (Days) Date Tested Total Load (Lbs.) Compressive Strength (Lbs./Sq.1n.) FPP 369 7 12/3/14 93,320 3,300 FPP 370 28 12/24/14 114,640+ 4,060+ FPP 371 61/2 28 12/24/14 127,820+ 4,520+ FPP 372 Hold Hold Test Methods Utilized Fracture Regular ASTM C-31, C-39, 0-143 (Unless Noted Otherwise Remarks and/or Distribution:- None 11:26 AM 12:40 PM Bike Trail 200'N of Bridge 5120 /1533799 63 OF 65 OF 4 Sunny Clear 9:00 AM 3:00 PM 3.3 20 3600 Remarks cc: Rick Odell <ROdell@coppelltx.90v> Mr. Michael Garza - City of Coppell, Phone: 972-304-3679; via E-mail: MGarza@coppelltx.gov Mr. Mitch Holmes - Teague, Nall & Perkins, Phone: 432-312-4205; via E-mail: mholmes@tnpinc.com Mr. Francisco Luyando - CD Builders, Inc., Phone: 787-688-8207; via E-mail: fluyando@cdbuilderspr.com GEE Consultants, Inc. TBPE Firm: F-3212 Reviewed b � y �-L , . All letters and reports are for the exclusive use of the client to whom they are addressed and shall not be reproduced without me full approval of GEE Consultantspar enIncThe use of our name must receive our prior written approval. Our letters and reports apply only to the sample tested and/or observed and are not necessarily indicative of the quantities of aptly identical or similar products. LGEOTECHNICAL ENGINEERIN2 E I • ENVIRONMENTAL CONSULTING E I • CONSTRUCTION MATERIALS TESTING GEE Consultants, Inc. 10046 Monroe Drive • Dallas, Texas 75229 • (214) 352-5433 • Fax (214) 352-6972 Report Date: January 21, 2015 Date Concrete Placed: Client: City of Coppell Project: Freeport Pkwy from Ruby Rd. to Sandy Lake Rd. Contractor: CD Builders Inc. Concrete Supplier and Plant: Argos #105 Location of Placement: Bridge Stages December 1, 2014 Standard 6°x12° Cylinders Cylinder Cross-sectional Area: 28.27 Square Inches Concrete Report No.: 94 Project No.: 214-01.44 MATERIALS Source / SSD Batch Wts. OBSERVATION DATA Description (Lbs/CuYd) Mix Number: Cement: Fly Ash: Coarse Aggregate: Intermediate Aggregate: Fine Aggregate: Admixtures: 2 Added Water: 1083 Time Sample Batched: 1:20 PM Time Sampled: 2:10 PM Sample Location: Rail Post Bottom Footing Truck / Ticket No: 7098 /1534602 Temperature: Ambient Range: 44 OF Concrete Range: 59 OF Slump Range (inches): Weather Conditions: Fair Time Started: 1:00 PM 0 Time Completed: 4:15 PM Sample Air Content (%): 3.8 Total Cubic Yards Placed: 7+2=9 Rnn,,;rarl 4tranoth (l.hc /cn in ). 3600 Specimen Number Measured Slump (in.) Age (Days) Date "Tested Total Load (Lbs.) Compressive Strength (Lbs./Sq.In.) Remarks FPP 373 7 12/8/14 120,860+ 4,280+ FPP 374 28 12/29/14 128,880 4,560 FPP 375 28 12/29/14 121,440+ 4,300+ FPP 376 H Hold Test Methods Utilized Fracture Regular Cylinders Made By: CP ASTM C-31, C-39, C`-143 (Unless Noted Otherwise) Remarks and/or Distribution:- None cc: Rick Odell <ROdell@coppelltx.gov> Mr. Michael Garza - City of Coppell, Phone: 972-304-3679; via E-mail: MGarza@coppelltx.gov Mr. Mitch Holmes - Teague, Nall & Perkins, Phone: 432-312-4205; via E-mail: mholmes@tnpinc.com Mr. Francisco Luyando - CD Builders, Inc., Phone: 787-688-8207; via E-mail: fluyando@cdbuilderspr.com GEE Consultants, Inc TBPE Firm• F-3212 Reviewed All letters and reports are for the exclusive use of the client to whom they are addressed and shall not be reproduced without the full approval of GEE Consultants Inc The use o our name must receive our prior written approval. our letters and reports apply only to the sample tested and/or observed and are not necessarily indicative of the quantities of apparently identical or similar products. G • GEOTECHNICAL ENGINEERING G • ENVIRONMENTAL CONSULTING GEE Consultants, Inc. 1fJ• CONSTRUCTION MATERIALS TESTING 10046 Monroe Drive • Dallas, Texas 75229 • (214) 352-5433 • Fax (214) 352-6972 REPORT OF CONCRETE MIX OBSERVATION Report Date: January 21, 2015 Date Concrete Placed: December 02,2014 Standard 6"xl2" Cylinders Client: City of Coppell Cylinder Cross-sectional Area: 28.27 Square Inches Project: Freeport Pkwy from Ruby Rd. to Sandy Lake Rd. Concrete Report No.: 95 Contractor: CD Builders Inc. Project No.: 214-0144 Concrete Supplier and Plant: Argos #110 Location of Placement: Inlet top and wall STA+45;STA2+45;STA7+17.biketrail STAI9+00tol9+10 MATERIALS Source / SSD Batch Wts. OBSERVATION DATA Description (Lbs/CuYd) Mix Number: 1083 Cement: Fly Ash: Coarse Aggregate: Intermediate Aggregate: Fine Aggregate: Admixtures: Added Water: Time Sample Batched: Time Sampled: Sample Location: Truck / Ticket No: Temperature: Ambient Range: Concrete Range: Slump Range (inches): Weather Conditions: Time Started: Time Completed: Sample Air Content (%): Total Cubic Yards Placed: RPnidrPrl Strength (Lbs./so.m.) 12:45 AM 1:30 PM STa5+45;STA2+45;STA7+17; STA 19+00to 19+10 9024 /1535120 43 OF 58 OF 4 Sunny 10:00 AM 3:00 PM 4.8 10 3600 Specimen Number Measured Slump (in.) Age (Days) Date Tested Total Load (Lbs.) Compressive Strength (Lbs./Sq.In.) Remarks FPP 377 7 12/9/14 101,060 3,580 FPP 378 28 12/30/14 128,060+ 4,530+ FPP 379 4 28 12/30/14 132680+ 4,690+ FPP 380 Hold Hold Test Methods Utilized Fracture Regular ASTM C-31, C-39, C-143 (Unless Noted Otherwise) Remarks and/or Distribution:- None cc: Rick Odell <RCldell@coppelltx.gov> Mr. Michael Garza - City of Coppell, Phone: 972-304-3679; via E-mail: MGarza@coppelltx.gov Mr. Mitch Holmes - Teague, Nall & Perkins, Phone: 432-312-4205; via E-mail: mholmes@tnpinc.com Mr. Francisco Luyando - CD Builders, Inc., Phone: 787-688-8207; via E-mail: fluyando@cdbuilderspr.com GEE Consultants, Inc TBPE Firm: F-3212 Reviewed by: All letters and reports are for the exclusive use of the client to whom they are addressed and shall not be reproduced without the full approval of GEE Consultants Inc The use of our name must receive our prior written approved. Our letters and reports apply only to the sample tested and/or observed and are not necessarily indicative of the quantities of apparently identical or similar products. G1 * GEOTECHNICAL ENGINEERING E 1 9 ENVIRONMENTAL CONSULTING E I* CONSTRUCTION MATERIALS TESTING GEE Consultants, Inc. 10046 Monroe Drive • Dallas, Texas 75229 • (214) 352-5433 0 Fax (214) 352-6972 Report Date: January 21, 2015 Date Concrete Placed: Client: City of Coppell Project: Freeport Pkwy from Ruby Rd. to Sandy Lake Rd. Contractor: CD Builders Inc. Concrete Supplier and Plant: Argos 4 105 Location of Placement: Curve inlet December 3, 2014 Standard 6"xI2" Cylinders Cylinder Cross-sectional Area: 28.27 Square Inches Concrete Report No.: 96 Project No.: 214-0144 MATERIALS Source / SSD Batch Wts. OBSERVATION DATA Description (Lbs/CuYd) Mix Number: Cement: Fly Ash: Coarse Aggregate: Intermediate Aggregate: Fine Aggregate: Admixtures: Added Water: 1083 Time Sample Batched: 9:35AM Time Sampled: 9:50AM Sample Location: STA2+45;STA5+45;STA7+17 Truck / Ticket No: 7098 /1535834 Temperature: Ambient Range: 53 OF Concrete Range: 62°F Slump Range (inches): 43/4 Weather Conditions: Cloudy Time Started: 7:45 AM Time Completed: 3:30 PM Sample Air Content 5.2 Total Cubic Yards Placed: 10 Reauired Strenath (Lbs./sq.in.): 3600 Specimen Number Measured Slump (in.) Age (Days) Date Tested Total Load (Lbs.) Compressive Strength (Lbs./Sq.1n.) Remarks FPP 381 7 12/10/14 121,200 4,290 FPP 382 28 12/31/14 127,500+ 4,510+ FPP 383 43/4 28 12/31/14 128,260+ 4,540+ FPP 384 H Hold Test Methods Utilized Fracture Regular Cylinders Made By: CP ASTM C-31, C-39, C-143 (Unless Noted Otherwise) _ Remarks and/or Distribution:- None cc: Rick Odell <ROdell@coppelltx.gov> Mr. Michael Garza - City of Coppell, Phone: 972-304-3679; via E-mail: MGarza@coppelltx.gov Mr. Mitch Holmes - Teague, Nall & Perkins, Phone: 432-312-4205; via E-mail: mholmes@tnpinc-com Mr. Francisco Luyando - CD Builders, Inc., Phone: 787-688-8207; via E-mail: fluyando@cdbuilderspr.com GEE Consultants, Inc. TBPE Firm: F-3212 Reviewed by: 11 '*�' "' All letters and reports are for the exclusive use of the client to whom they are addressed and shall not be reproduced without the full approval of GEE Consultants, the The use of our name must receive our prior written approval. Our letters and reports apply only to the sample tested and/or observed and are not necessarily indicative of the quantities of apparently identical or similar products. • GEOTECHNICAL ENGINEERING VIRONMENTAL CONSULTING • CONSTRUCTION MATERIALS TESTING GEE Consultants, Inc. 10046 Monroe Drive • Dallas, Texas 75229 • (214) 352-5433 0 Fax (214) 352-6972 REPORT OF CONCRETE MIX. OBSERVATION Report Date: January 19, 2015 Date Concrete Placed: Client: City of Coppell Project: Freeport Pkwy from Ruby Rd. to Sandy Lake Rd. Contractor: CD Builders Inc. Concrete Supplier and Plant: Argos #110 Location of Placement: Pavement December 8, 2014 Standard 6"xl2" Cylinders Cylinder Cross-sectional Area: 28.27 Square Inches Concrete Report No.: 99 Project No.: 214-0144 MATERIALS Source / SSD Batch Wts. OBSERVATION DATA Description (Lbs/CuYd) Mix Number: 1273 Cement: Fly Ash: Coarse Aggregate: Intermediate Aggregate: Fine Aggregate: Admixtures: Added Water: Time Sample Batched: 9:45 AM Time Sampled: 10:30 AM Sample Location: Driveway 10 N. bound of Remarks median crossing Truck / Ticket No: 7098/ 1539036 Temperature: 121,160+ Ambient Range: 51 °F Concrete Range: 65 OF Slump Range (inches): 4.5 Weather Conditions: Cloudy Time Started: 9:00 AM Time Completed: 6:45 PM Sample Air Content (%}: 3.8 Total Cubic Yards Placed: 50 Required Strength (Lbs./sq.in.): 3600 Specimen Number Measured Slump (in.) Age (Days) Date Tested Total Load (Lbs.) Compressive Strength (Lbs./Sq.In.) Remarks FPP 393 7 12/15/14 121,160+ 4,290+ Bridge, Stage I FPP 394 28 1/5115 145,920+ 5,160+ Large Pilaster 4'S FPP 395 28 1/5/15 145,200+ 5,140+ FPP 396 H Hold Test Methods Utilized Fracture Regular Cylinders Made By: CP ASTM C-31, C-39, C-143 (Unless Noted Otherwise) Remarks and/or Distribution:- None cc: Mr. Larry Davis - City of Coppell, Phone: 972-304-3684; via Fax: 972-304-3570 Mr. Michael Garza - City of Coppell, Phone: 972-304-3679; via E-mail: MGarza@coppelltx.gov Mr. Mitch Holmes - Teague, Nall & Perkins, Phone: 432-312-4205; via E-mail: mholmes@tnpinc.com Mr. Francisco Luyando - CD Builders, Inc., Phone: 787-688-8207; via E-mail: fluyando@cdbuilderspr.com All letters and reports are for the exclusive use of the client to whom they are addressed and shall not be reproduced without the full approval of GEE Consultants, Inc. The use of'our name must receive our prior written approval. Our letters and reports apply only to the sample tested and/or observed and are not necessarily indicative of the quantities of apparently identical or similar products. INICAL ENGINEERING VIRONMENTAL CONSULTING * CONSTRUCTION MATERIALS TESTING GEE Consultants, Inc. 10046 Monroe Drive Dallas, Texas 75229 • (214) 352-5433 0 Fax (214) 352-6972 Report Date: January 19, 2015 Date Concrete Placed: December 8, 2014 Standard 6"x12" Cylinders Client: City of Coppell Project: Freeport Pkwy from Ruby Rd. to Sandy Cylinder Lake Rd. Cross-sectional Area: 28,27 Square inches Contractor: CD Builders Inc. Concrete Report No.: 100 Concrete Supplier and Plant: Argos #110 Project No.: 214-0144 Location of Placement: Pavement MATERIALS Source / SSD Batch Wts. Description (Lbs/CuYd) OBSERVATION DATA Mix Number: 1273 Time Sample Batched: 4:05 PM Cement: Time Sampled: 4:40 PM Fly Ash: Sample Location: Driveway 10 S. bound of Coarse Aggregate: median crossing, Inlet Sta. Intermediate Aggregate: 13+20 Fine Aggregate: Truck / Ticket No: 5094 /1539455 Admixtures: Temperature: I Ambient Range: 55 OF 2 Concrete Range: 65 OF Added Water: 0 Slump Range (inches): 4.25 Weather Conditions: Cloudy Time Started: 9:00 AM Time Completed: 6:45 PM Sample Air Content (%): 4.8 Total Cubic Yards Placed: 110 Re uired Strength (Lbs./sq.in.): 3600 Specimen Measured AgeDate Total Load Compressive Strength Number Slump (in.) Days)) "sT T Tested (Lbs.) (Lbs./Sq.1n.) Remarks FPP 397 7 12/15/14 —147,240 5,210 FPP398 425 28 115115 161,900+ 5,730+ FPP 399 . 28 115115 163,200+ 5,770+ FPP 400 H Hold Test Methods Utilized Fracture Regular ASTM C-31, C-39, C -143A (Unless Noted Otherwise) Cylinders Made By: CP � Remarks and/or Distribution:- None cc: Mr. Larry Davis - City of Coppell, Phone: 972-304-3684; via Fax: 972-304-3570 Mr. Michael Garza - City of Coppell, Phone: 972-304-3679; via E-mail: MGarza@coppelltx.gov Mr, Mitch Holmes - Teague, Nall & Perkins, Phone: 432-312-4205; via E-mail: mbolmes@tnpinc.com Mr. Francisco Luyando - CD Builders, Inc., Phone: 787-688-8207; via E-mail: fluyando@cdbuilderspr.com GEE Consultants, Inc. TBPE Firm: F-3212 Reviewed by: (��_ - All letters and reports are for the exclusive use of the client to whom they are addressed and shall not be reproduced without the full approval of GEE Consultants, Inc. The use of our name must receive out prior written approval. Our letters and reports apply only to the sample tested and/or observed and are not necessarily indicative of the quantities of apparently identical or similar products.