MA1006-CN110804CITY OF COPPELL . CHANGE OR EXTRA WORK ORDER PROJECT: NIA 10-06 Belt Line & Denton Tap Brick Paver Replacement CONTRACTOR: Jim Bowman Construction Company, L.P. OWNER: City of Coppell CHANGE ORDER NO.: 1 DATE: 7/20/11 Item Description Quantity Unit Unit Price Total ADD: 11 12" RC Pavement 23 SY $60.80 $1,398.40 w/ Curb 16 Sod 1385 SF $0.75 $1,038.75 SUBTRACT 15 4" RC Sidewalk 119.9 SF $4.00 ($479.60) Total Revision to Contract Amount $19957.55 Original contract amount $3529430.70 Net increase in contract amount $1,957.55 Revised contract amount $354,388.25 Cumulative increase in TOTAL change order amount (Percentage) <%1 Net increase in contract time of completion 0 Revised Contract time of completion 42 The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full accord and satisfaction of all past and future liability originating under any clause in the Contract by reason of this revision to the Contract. z Accepted by City Date