MA1006-CS110713 (3)
Michelle Matunas
From:Adrian Bowman <adrian@bowmanconstruction.com>
Sent:Wednesday, July 13, 2011 7:53 AM
To:George Marshall
Subject:RE: MA10-06 Belt Line/ D Tap
We can look at it and measure it this morning, but the vast majority was behind the ramps. The previous ramps were
much larger than the current ones. We imported about 60CY of fill dirt to fill in behind those ramps as well.
-Adrian
From: George Marshall \[mailto:gmarshall@coppelltx.gov\]
Sent: Monday, July 11, 2011 1:36 PM
To: adrian@bowmanconstruction.com
Subject: MA10-06 Belt Line/ D Tap
Adrian,
I was looking over your pay application and most of it looked ok but why and where did we come up with 2.3 times the
original quantity of sod? I don't like to see such a quantity overrun without knowing about it in the field. Please look
into it and get back with me.
Thank You, George
George Marshall, PE
City of Coppell
Engineering
972-304-3562
1