MA1006-CS110518 (7)GEOTECHNICAL
GROUP
May 18, 2011
Mr. George S. Marshall, P.E.
City of Coppell
255 Parkway Blvd.
Coppell, Texas 75019
Re: Belt Line & Denton Tap Brick Paver
Replacement C.I.P. Project MA 10-06
Coppell, Texas
Engineering Inspection & Testing Services
AGG Proposal No: P11 -0530C
e- . aA- 1.
® GEOTECHNIGAi_ ENGINEERING
ENVIRONI✓ENTAL CONSULTING
° CONSTRUCTION MATERIALS ENGINEERING AND TESTING
Phn: (972) 304-3562
Fax: (972) 304-3570
Alliance Geotechnical Group (AGG) is pleased to confirm our firm's interest in providing
materials inspection and testing services for the proposed Belt Line & Denton Tap Brick Paver
Replacement C.I.P Project MA 10-06 project noted above. A schedule of unit fees for this
project is attached.
After reviewing our fee schedule if you have any questions, please contact the undersigned at
(972) 444-8889. If acceptable, please sign below and fax back to our office as our Authorization
to Proceed. We look forward to the opportunity of working with you on this project.
Respectfully submitted,
ALLIANCE GEOTECHNICAL GROUP
Perryekara, S.E.T.
Sr. Project Manager
Approved by:
Signature
Date:
MEMBER 3228 Hilita\ Sricct a Dallas, Tcxas 75247
a
TA 972-444-88,S9 Fax: 972-444-8893 « ,, rn,r.Com kxb,..
SCHEDULE OF FEES
FOR
CONSTRUCTION MATERIALS ENGINEERING & TESTING
BELT LINE DENTON TAP BRICK PAVER REPLACEMENT COPPELL, TEXAS AGG PROPOSAL NO.: P11 -0530C
DESCRIPTION OF SERVICES
QUANTITY
UNIT FEE
UNIT
FEE
A. MASS GRADING, LIME AND WALL BACKFILL TESTING & INSPECTION
• Moisture/Density Relationship of Soils (ASTM D-698)
2
@
$150.00
each
$300.00
• Atterberg Limits
2
@
$50.00
each
$100.00
• Lime Series ( 5 point PI method)
• Concrete Cylinder Test - (4 cyis per 100 cyd) - Center Paving
@
$225.00
each
$0.00
• Cement Series ( as needed)
• Concrete Cylinder Test - (4 cyis per 100 cyd) - Paving
@
$375.00
each
$0.00
• Sulfate Test
• Concrete Core Depth Checks ( 2" dia core / 300 If)
@
$90.00
each
$0.00
• Paving Subgrade Density Test ( 1 per 300 If/ lift)
18
@
$13.00
each
$234.00
• Lime Gradation Test (1 per 300 If)
• Vehicle Charge
@
$13.00
each
$0.00
• Lime Depth Verification (1 per 300 If)
@
$13.00
each
$0.00
• Lime Subgrade In -Place Density Test (1 per 300 If)
@
$13.00
each
$0.00
• Sr. Engineering Tech to perform testing
26
@
$37.00
hour
$962.00
• Sr. Engineering Tech to perform proof roll observation
12
@
$37.00
hour
$444.00
• Project Manager
4
@
$75.00
hour
$300.00
• Geotechnical Project Manager( as needed)
@
$90.00
hour
$0.00
• Sr. Geotechnical Engineer ( as needed)
@
$110.00
hour
$0.00
• Vehicle Charge
10
@
$35.00
trip
$350.00
P11 -0530C
Sub -Total
$2,690.00
B. CONCRETE & REINFORCING TESTING & INSPECTION
• Concrete Inspection & Testing (regular time)
75
@
$37.00
hour
$2,775.00
• Concrete Cylinder Test - (4 cyis per 100 cyd) - stamped Paving
16
@
$14.00
each
$224.00
• Concrete Cylinder Test - (4 cyis per 100 cyd) - Center Paving
12
@
$14.00
each
$168.00
• Concrete Cylinder Test - (4 cyis per 100 cyd) - Paving
20
@
$14.00
each
$280.00
• Concrete Core Depth Checks ( 2" dia core / 300 If)
@
$40.00
each
$0.00
• Project Manager
2
@
$75.00
hour
$150.00
• Vehicle Charge
19
@
$35.00
trip
$665.00
Sub -Total
$4,262.00
ESTIMATED TOTAL
$6,952.00
P11 -0530C
SCHEDULE OF FEES
FOR
CONSTRUCTION MATERIALS ENGINEERING & TESTING
BELT LINE DENTON TAP BRICK PAVER REPLACEMENT COPPELL, TEXAS AGG PROPOSAL NO.: P11 -0530C
DESCRIPTION OF SERVICES QUANTITY UNIT FEE UNIT FEE
NOTES:
1. Overtime rates of 1.5 times the regular hourly rate will be charged for hours worked over eight (8) hours
per day Monday thru Friday or any time before 7:00 a.m. or after 5:00 p.m. Service performed on Saturdays
and Sundays will be billed at 1.5 times the regular hourly rate. Services performed on recognized holidays
will be billed at 2.0 times the regular hourly rate. ( WILL BE BILLED TO CONTRACTOR)
2. All laboratory test fees are F.O.B. our laboratory; additional charge for sample pickup may apply.
3. Any additional tests will be billed on a hourly rate and charged at the applicable rate, portal-to-portal.
4. Additional test not specified in this proposal will be quoted upon request.
5. This proposal does not include any technician stand-by, non -readiness charges, and/or trips or re -tests of the
previous failing tests.
6. The above unit rates are based on the following estimated schedule:
* Proctor pickup - 1 estimated site visit
* Subgrade proof rolling observation - 3 estimated site visits
• Subgrade field density testing - 6 estimated site visits
* Bomanite stamped concrete - 4 estimated concrete placement
* Center detail concrete paving - 3 estimated concrete placements
* Standard concrete paving - 5 estimated concrete placements
Concrete test cylinder pickup - 7 estimated site visits
P11 -0530C