REPORT OF CONCRETE MIX INSPECTION
Report Date:
C I ient:
Project:
Contractor:
Concrete Supplier and Plant:
Location of Placement:
MATERIALS
July 16, 1996 Date Concrete Placed: Jtmrl3, 1996
City of Coppell
Village Parkway Pump Station Addition
North Texas Municipal Construction Co., Inc.
DFW Redimix, Inc.
Piers
~ce/ B.~h w~. INSPECTION DATA
Descriptitm (Lbs./C'~. Yd)
Standard 6"x12"
Area 28.27 Square Inches
COncrete Report No.: 4
Mix Number:
Cement:
Fly Ash:
Coarse Aggregate:
Intermediate Aggregate:
Fine Aggregate:
Admixtures:
1
2
Added Water:
15Gallons
Time Sample Batched: 11:25 am
Time Sampled: 12:45 pm
Sample Location: Piers 4 and 5
Truck/Ticket No: 306/4628
Temperature:
Ambient Range: 94°F
Concrete Range: 92°F
Slump Range (inches): 4.5"
Weather Conditions: Sunny
Time Started: 12:30 pm
Time Completed: 1:15 pm
Sample Air Content (%): N/A
Total Cubic Yards Placed: 15 C.Y.
Required Strength (Lbs./sq.in.): 4,000 psi
Specimen Measured Age Date Total Load Comptessive Strength
Number Slump (in.) (Days) Tested (Lbs.) (Lbs./Sq. ln.)
VPP 13 4.5" 7 06/20/96 85,960 3,040
VPP 14 4.5" 7 06/20/96 96,460 3,410
VPP 15 4.5" 28 07/11/96 116,460 4,120
VPP 16 4.5" 28 07/11/96 117,280 4,150
Test Methods Utilized Fracture l~gular
ASTM C-31,C-39,C-143 (Unless Noted Otherwise) Cylinders Made By: Cedy
Remarks and/or Distribution:
Remarks
Co:
Mr. Larry Davis - City of Coppell
Mr. Mike Diagre - North Texas Municipal Construction Co.
Mr. Gary Hendricks - Shimek, Jacobs and Finklea
.....