RE: West Sandy Lake - Additional Gabion workKeith
Per our discussion earlier this week please note the attached memo
submarining our commitment to fund the repairs to the gabion walls at
Sandy Lake Road Bridge.
Please let me know how you would like to proceed and if you have any
questions.
Thank you
Chris
Chris Schmitt, P.E.
Principal
17304 Preston Road, Suite 1340
Dallas, Texas 75252
214.461.9867 Main
214.988.9913 Direct
903.421.1897 Mobile
214.461.9864 Fax
cschmitt@tnpinc.com <mailto:cschmitt@tnpinc.com>
From: Keith Marvin [mailto:KMarvin@coppelltx.gov]
Sent: Thursday, November 13, 2014 10:58 AM
To: Chris Schmitt
Cc: Kenneth Griffin
Subject: FW: West Sandy Lake - Additional Gabion work
Chris,
See below. Let me know how you want to proceed.
Keith
From: Robert Caudill [mailto:rcaudill@TiseoPaving.com]
Sent: Thursday, November 13, 2014 9:41 AM
To: Keith Marvin; cschmitt@tnpinc.com <mailto:cschmitt@tnpinc.com>
Cc: Robert Caudill; Lance Smith; roycecarter1@yahoo.com
<mailto:roycecarter1@yahoo.com>
Subject: West Sandy Lake - Additional Gabion work
Keith;
The cost for additional Gabions is listed below.
1. Gabion wall – 148CY @ $185.00/CY = $27,380.00
2. Gabion Mattress (12”) – 7CY @ $350.00/CY = $2,450.00
3. Turf Reinforcement Matting – 167.50SY @ $6.50/SY = $1,088.75
4. Excavation to Gabion Wall – 1LS @ $7,500.00 = $7,500.00
5. Gabion wall Removal – 258.83CY @ $25.00/CY = $6,470.75
6. Staking – 1LS @ $1,500.00/LS = $1,500.00
Total for Gabion
$46,389.50
This work will take 35 working days. We will need to have approval as
soon as possible to work this in our time frame, if not this additional
time needs to be added to our original contract time.