RE: Change Order #3Keith Agree that this time seems excessive for sidewalk. Albeit this is a substantial change but it does not make sense that it would take 2.5 months to construct sidewalk? Also, received your message yesterday regarding Verizon conflict. Please forward along and additional information as soon as you can and we will look into it ASAP. Chris Chris Schmitt, P.E. Principal 17304 Preston Road, Suite 1340 Dallas, Texas 75252 214.461.9867 Main 903.421.1897 Mobile 214.461.9864 Fax cschmitt@tnpinc.com <mailto:cschmitt@tnpinc.com> -----Original Message----- From: Keith Marvin [mailto:KMarvin@coppelltx.gov] Sent: Tuesday, June 24, 2014 7:44 AM To: 'Robert Caudill' Cc: Rick Odell; Lance Smith; Walter Mitchell; Chris Schmitt Subject: RE: Change Order #3 Robert, This seems like an excessive amount of time for the scope of work included in this change order, most of which was shown in the plans, just not correctly shown in the bid tabulation. Please provide additional detail for this request, or revise it to reflect the time needed for this scope of work. Keith -----Original Message----- From: Robert Caudill [mailto:rcaudill@TiseoPaving.com <mailto:rcaudill@TiseoPaving.com> ] Sent: Monday, June 23, 2014 4:59 PM To: Keith Marvin Cc: Rick Odell; Lance Smith; Walter Mitchell Subject: RE: Change Order #3 Keith; In communicating with Tiseo subs an additional time required is an additional 75 calendar days. This work is time and labor consuming and we will need this time. -----Original Message----- From: Keith Marvin [mailto:KMarvin@coppelltx.gov <mailto:KMarvin@coppelltx.gov> ] Sent: Monday, June 23, 2014 10:18 AM To: Robert Caudill Cc: Rick Odell; Lance Smith; Walter Mitchell Subject: Re: Change Order #3 Are you asking for additional time? If so, how much are you asking for? Keith Marvin City of Coppell > On Jun 23, 2014, at 10:17 AM, "Robert Caudill" <rcaudill@TiseoPaving.com <mailto:rcaudill@TiseoPaving.com> > wrote: > > Keith; > > What about additional time? > > -----Original Message----- > From: Keith Marvin [mailto:KMarvin@coppelltx.gov <mailto:KMarvin@coppelltx.gov> ] > Sent: Thursday, June 19, 2014 6:11 AM > To: Robert Caudill > Cc: Rick Odell > Subject: Change Order #3 > > Robert, > > I'm sure by now you have heard of the quantity bust on the sidewalk and trail on phase 2A of Sandy Lake Road. The engineer apparently converted these quantities into square yards and left the unit as square feet. We will need to do a change order to allocate the rest of the money for this work. > > While we are doing this change, I want to catch all the quantity overruns we've had and fund them as well. See the attached proposed change order #3 and let me know if there is anything I'm missing. > > This will go to City Council for approval on July 8th. > > Thanks. > > Keith > > -----Original Message----- > From: Robert Caudill [mailto:rcaudill@TiseoPaving.com <mailto:rcaudill@TiseoPaving.com> ] > Sent: Wednesday, June 18, 2014 8:43 AM > To: Keith Marvin > Subject: FW: > > Keith; > > Attached is a signed change order #2, original will be hand delivered tomorrow. > > -----Original Message----- > From: scanner@tiseopaving.com <mailto:scanner@tiseopaving.com> [mailto:scanner@tiseopaving.com <mailto:scanner@tiseopaving.com> ] > Sent: Tuesday, June 18, 2013 9:03 AM > To: Robert Caudill > Subject: > > ------------------- > 2H0-25 > [00:c0:ee:1e:e8:84] > -------------------