RE: Sandy Lake Sidewalk QuantityKeith, I understand your frustration and again apologize for the error. Additionally, I regret the position that this will put you in with council and the scrutiny that is inevitable when presenting a change order of this magnitude. When the time comes if you will allow me, I’d like to briefly present to council that this was not staff’s error, rather ours. I’d also like to share/reiterate the following details: • We calculated the sidewalk quantity in terms of SY, and typed SF on the bid form, effectively but inaccurately reducing the quantity bid by the SY/SF conversion factor of 9. • While we see it as significant, this change order does not appear to represent additional expense to the City for the quantity of sidewalk shown in the plans. We’ve compared the contractor’s sidewalk bid with their sidewalk bid on Phase 2A and found the unit price to be the same, so we are confident that they did not strategically inflate their unit price in anticipation of an impending change order to increase quantity, and profit. • We understand the change order made necessary, and sincerely regret the administrative inconvenience it has caused staff and council, particularly with your constraints of public bidding laws intended to assure competition. Please accept our apology and know that while errors happen, this kind of inaccuracy is unusual for us. If staff prefers to present this to the council, we’d like to at least be present in the chamber to field any questions. Please let me know if you’d like to discuss. Chris Chris Schmitt, P.E. Principal 17304 Preston Road, Suite 1340 Dallas, Texas 75252 214.461.9867 Main 903.421.1897 Mobile 214.461.9864 Fax cschmitt@tnpinc.com <mailto:cschmitt@tnpinc.com> -----Original Message----- From: Keith Marvin [mailto:KMarvin@coppelltx.gov] Sent: Monday, June 09, 2014 11:59 AM To: Chris Schmitt; Andrew Luce Cc: Rick Odell; Mike Jones; Kenneth Griffin Subject: RE: Sandy Lake Sidewalk Quantity Chris, This represents a $195,000 mistake. We're going to have to go to City Council for this change order and explain the discrepancy. Fortunately Tiseo's prices are fair and appropriate, and if the quantity had been correct in the bid tabulation we would have paid this amount anyway. I just hate to give the City Council a reason to question our competency. Keith -----Original Message----- From: Chris Schmitt [mailto:cschmitt@tnpinc.com <mailto:cschmitt@tnpinc.com> ] Sent: Monday, June 09, 2014 11:25 AM To: Keith Marvin; Andrew Luce Cc: Rick Odell Subject: RE: Sandy Lake Sidewalk Quantity Keith Yes ....we have discovered the problem. Dallas office was coordinating the final assembly of specs/quantities and took information that Andrew provided which was in SF and converted to SY but we did not modify the unit column on the spreadsheet. The resulting bid quantity is approximately 1/9 of what is should have been which reflects the conversion from SF to SY. For some reason we did not do this on Phase 2A but did on 2B. The correct SF quantities for the sidewalk should have been: For 5' sidewalk, Area=22,137.24 SF For 8' Concrete Path, Area=29,879.52 SF I realize that this represents a significant impact to these items and hope that TISEO is able to work with us to soften the blow. I did a quick review of the bid tab and noticed that TISEO bid the same unit price for these items on both 2A and 2B. It appears that only one contractor noticed the issue and attempted to inflate their unit price for 2B. Not that it was intentional but sure is interesting. Again I apologize for the error. We're happy to discuss at your convenience. Chris Chris Schmitt, P.E. Principal 17304 Preston Road, Suite 1340 Dallas, Texas 75252 214.461.9867 Main 903.421.1897 Mobile 214.461.9864 Fax cschmitt@tnpinc.com <mailto:cschmitt@tnpinc.com> -----Original Message----- From: Keith Marvin [mailto:KMarvin@coppelltx.gov <mailto:KMarvin@coppelltx.gov> ] Sent: Monday, June 09, 2014 11:03 AM To: Chris Schmitt; Andrew Luce Cc: Rick Odell Subject: RE: Sandy Lake Sidewalk Quantity Chris/Andrew Any update on the quantity issues? Keith -----Original Message----- From: Chris Schmitt [mailto:cschmitt@tnpinc.com <mailto:cschmitt@tnpinc.com> ] Sent: Friday, June 06, 2014 12:45 PM To: Rick Odell; Keith Marvin Cc: Andrew Luce Subject: RE: Sandy Lake Sidewalk Quantity Keith/Rick We are looking at this now and think that we've discovered the issue. I need to investigate a bit further and will report back ASAP. Thanks Chris Chris Schmitt, P.E. Principal 17304 Preston Road, Suite 1340 Dallas, Texas 75252 214.461.9867 Main 903.421.1897 Mobile 214.461.9864 Fax cschmitt@tnpinc.com <mailto:cschmitt@tnpinc.com> -----Original Message----- From: Rick Odell [mailto:ROdell@coppelltx.gov <mailto:ROdell@coppelltx.gov> ] Sent: Friday, June 06, 2014 10:27 AM To: Keith Marvin Cc: Chris Schmitt; Andrew Luce Subject: Re: Sandy Lake Sidewalk Quantity We will gave the same issue with the 8' trail also . Sent from my iPhone On Jun 5, 2014, at 11:50 AM, "Keith Marvin" <KMarvin@coppelltx.gov <mailto:KMarvin@coppelltx.gov> > wrote: > Chris, > > Can you verify the quantities for sidewalk on the Sandy Lake Road project? > > Thank you. > > Keith Marvin > City of Coppell