RE: Sandy Lake Revised Bridge Pier PlanHere you go.
One thing Delvin asked is that we make certain the contractor double
checks all of his staked piers as most of the piers have shifted
slightly to account for the movement on the ends.
I’ll follow up with additional sheets as soon as I get them. Thanks.
Casey McBroom, P.E.
Project Engineer
17304 Preston Road, Suite 1340
Dallas, Texas 75252
214.461.9867 Phone
972.900.5733 Mobile
214.461.9864 Fax
cmcbroom@tnpinc.com <mailto:cmcbroom@tnpinc.com>
From: Keith Marvin [mailto:KMarvin@coppelltx.gov]
Sent: Wednesday, August 07, 2013 1:52 PM
To: Casey McBroom
Subject: RE: Sandy Lake Revised Bridge Pier Plan
Just send me a PDF of it.
Keith Marvin, P.E.
City of Coppell
972-304-3681
From: Casey McBroom [mailto:CMcBroom@TNPINC.com]
Sent: Wednesday, August 07, 2013 8:56 AM
To: Keith Marvin
Subject: Sandy Lake Revised Bridge Pier Plan
Keith
Delvin has sent me his revised sheet. The rest will follow soon I
believe. I’m double checking one thing, but once that’s cleared how
would you like us to release this? I can send to you only, or CC anyone
you wish. We can also produce hard copies if needed.
Thanks.
Casey McBroom, P.E.