WA9302A-CS 960903SHIMEK, JACOBS & FINKLEA, L.L.P. Pago No. 1 of 2 CONSULTING ENGINEERS Phone: (214) 361-7900 FAX: (214) 361-0204 Subject: City of Coppell Village Parkway Pump Station Addition Construction Progress Meeting Memorandum To: Larry Davis, City of Coppell Mike Daigre, North Texas Municipal Construction Co. From: Gary Hendricks Date: September 3, 1996 In Attendance: 1. Larry Davis 4. Gary Hendricks 2. Mike Daigre 5. 3. Bill Bigham 6. Discussion Items: 1. Pump Performance Curves 2. Submittals a) O & M Manuals b) SCADA Modifications 3. Completed or working Field Changes a) Main Gate Entry Modifications b) Suction Header Tap c) Floor Drain Piping d) Control Panel at Disinfection Bldg. e) Valve at DWU injection vault f) Stone casting g) Disinfection Bldg. Slab & Floor (Panic Bar??) · SHIMEK, JACf'3S & FINKLEA, L.L.t VageNo. 2of2 · CONSULTING ENGINEERS Phone: (214) 361-7900 FAX: (214) 361-0204 Subject: City of Coppell Village Parkway Pump Station Addition Construction Progress Meeting Memorandum To: Larry Davis, City of Coppell Mike Daigre, North Texas Municipal Construction Co. From: Gary Hendricks Date: September 3, 1996 4. Pending Field Changes/Change Orders a) Pipe Insulation b) Existing Dormers -- Painting c) Overhead Door Lighting d) e) 5. Pump Pads and Base Plates -- Re: S, J & F letter dated July 19, 1996 6. Cone Valve Modifications/Orientation 7. Disinfection Building/Scrubber Operations 8. Pump Room Ventilation -- Sheet E7, Detail 4 9. Elevated Storage Tank Modifications 10. Schedule 11. 12. 13. 14.