WA9302A-CS 960903SHIMEK, JACOBS & FINKLEA, L.L.P. Pago No. 1 of 2
CONSULTING ENGINEERS
Phone: (214) 361-7900
FAX: (214) 361-0204
Subject: City of Coppell
Village Parkway Pump Station Addition
Construction Progress Meeting
Memorandum To: Larry Davis, City of Coppell
Mike Daigre, North Texas Municipal Construction Co.
From: Gary Hendricks Date: September 3, 1996
In Attendance:
1. Larry Davis 4. Gary Hendricks
2. Mike Daigre 5.
3. Bill Bigham 6.
Discussion Items:
1. Pump Performance Curves
2. Submittals
a) O & M Manuals
b) SCADA Modifications
3. Completed or working Field Changes
a) Main Gate Entry Modifications
b) Suction Header Tap
c) Floor Drain Piping
d) Control Panel at Disinfection Bldg.
e) Valve at DWU injection vault
f) Stone casting
g) Disinfection Bldg. Slab & Floor (Panic Bar??)
· SHIMEK, JACf'3S & FINKLEA, L.L.t VageNo. 2of2
· CONSULTING ENGINEERS
Phone: (214) 361-7900
FAX: (214) 361-0204
Subject: City of Coppell
Village Parkway Pump Station Addition
Construction Progress Meeting
Memorandum To: Larry Davis, City of Coppell
Mike Daigre, North Texas Municipal Construction Co.
From: Gary Hendricks Date: September 3, 1996
4. Pending Field Changes/Change Orders
a) Pipe Insulation
b) Existing Dormers -- Painting
c) Overhead Door Lighting
d)
e)
5. Pump Pads and Base Plates -- Re: S, J & F letter dated July 19, 1996
6. Cone Valve Modifications/Orientation
7. Disinfection Building/Scrubber Operations
8. Pump Room Ventilation -- Sheet E7, Detail 4
9. Elevated Storage Tank Modifications
10. Schedule