WA9302A-CS 960813SHIMEK, JACOBS FINKLEA
CONSTRUCTION REPORT Project No. 94156
Date: 08/13/96
Prepared Is This A
Owner: City of Coppell Project Name: Village Parkway Pump Station Addition
Construction
Contractor: North Texas Municipal Construction Co., Inc Time Allotted: 360 Used: 180
Number
Superintendent: Bill Bigham. Men Working: 10_+ Hours: 9:00 am to 9:30 am
Weather Conditions: Cloudy and Mild
Site Conditions: The site was in good condition
WORK DESCRIPTION
1. Preparations were being made for the driveway concrete replacement on the north side of the pump station.
Bill indicated that the concrete may be poured on August 14, 1996.
2. The roof on the Pump Station Addition was being framed. Bill indicated that crews should be arriving on the
jobsite this week to begin preparing for the shingle removal on the existing pump station.
3. The brick mason was installing the cast stone panels.
cc: North Texas Municipal Construction Co.