WA9302A-CS 960806 (2)SHIMEK, JACOBS FINKLEA
CONSTRUCTION REPORT Project No. 94156
Date: 08/06/96
Prepared }__~ Is This A
ny: Matt Hiekey f~t Working Day? [] Yes [] No
Owner: City of Coppell Project Name: Village Parkway Pump Station Addition
Construction
Contractor: North Texas Municipal Construction Co., Inc Time Allotted: 300 Used: 173
Number
Superintendent: Bill Bigham. Men Working: 1 Hours: 9:00 am to 9:30 am
Weather Conditions: Cloudy and Hot
Site Conditions: The site contained construction debris and the pump station driveway needs to be cleaned.
WORK DESCRIPTION
1. A majority of the bricks have been placed on the pump station addition walls.
2. Larry Davis showed concerns with the condition of the pump station driveway. The driveway will need to be
cleaned and maintained for the duration of the project.
3. Preparations were being made for concrete replacement around the existing pump station doors and the pump
station additions.
4. The metal louvers have been installed.
cc: North Texas Municipal Construction Co.