WA9302A-CS 960521SHIMEK, JACOBS '& FINKLEA
CONSTRUCTION REPORT Project No. 941,6
Date: 5/21/96
Prepared Is This A
By: Matt Hickey ~r~ V'~ WorkingDay? [']Yes ["]No
Owner: City of Coppell Project Name: Village Parkway Pump Station Addition
Construction
Contractor: North Texas Municipal Construction Co., Inc Time Allotted: 300 Used: 96
Number
Superintendent: Bill Bigham. Men Working: 3 Hours: 9:00 am to 9:30 am
Weather Conditions: Clear and Hot
Site Conditions: Debris from excavation of the precast vaults and pump station still remains in the northwest corner
of the site.
WORK DESCRIPTION
1. Larry Davis had concerns about the plastic ball valve used on the water stunpier line that is connected to the
Dallas Water Utilities' supply line. He said that he discussed with Gary Hendricks the possible relocation of the
valve to the inside of the chemical injection vault.
2. The Chlorine and Ammonia solution lines are in place. The tapping sleeve for the fresh water supply line is
connected to the existing 16 inch water line. Both of the chemical injection vaults are in place.
3. Bill Bigham indicated that a test panel for the bricks would be constructed on May 22.
4. The steel for the pier is tentatively scheduled to be tied on May 22.
cc: North Texas Municipal Construction Co.