Subject:Utilities-Sandy Lake and Denton Tap Intersection
Attachments:1.0 Exhibits-SOUTH DENTON TAP.pdf; 2.0 Exhibits-EAST SANDY LAE.pdf; 3.0 Exhibits-
NORTH DENTON TAP.pdf
Sherri, Mike, Stephen and George,
Please find the attached layout sheets for utilities which shows proposed alignment of each underground utilities.
Please note the following,
The utilities conduits will be on top (12” separation) of ONCOR conduits although the alignments are
shown next to ONCOR conduits.
We are proposing all utilities conduits to be installed by boring.
All utilities conduits will be parallel and next to each other where possible.
There is no conduit for Time Warner Cable on Sandy Lake as the existing overhead line is abandoned.
There are few items (pull box, vaults etc.) missing. We will incorporate those after I get feedback on the
proposed alignment.
Please take a look and let me know your question or comments.