WA9302A-CS 960409SHIMEK, JACOBS FINKLEA
CONSTRUCTION REPORT Project No. 94156
Date: 4/9/96
Prepared Is This A
By: Matt Hiekey Working Day? [] Yes [] No
Owner: City of Coppell Project Name: Village Parkway Pump Station Addition
Construction
Contractor: Noah Texas Municipal Construction Co., Inc Time Allotted: 300 Used: 54
Number
Superintendent: Bill Bigham. Men Working: 2 Hours: 9:00 am to 9:30 am
Weather Conditions: Clear and Cool
Site Conditions: Clean and well maintained
WORK DESCRIPTION
1. Several piping options for Pumps 5 & 6 were reviewed with Ted Dutt and Larry Davis. The City was in
agreement that the piping for Pump 5 shall remain the same while the taping sleeve for Pump 6 shall be placed on
the bend of the discharge header. Placing the tapping sleeve on the discharge header bend required one additional
piping bend.
2. T.U. electric has repaired the damaged transformer.
3. Ted Dutt was expecting to shut down the pump station so that the relocation and electrical connections of the
electrical duct bank could be completed.
cc: Noah Texas Municipal Construction Co.