RE CHANGE ORDER 1 FOR COPPELL ROAD (2)Marty,
I think we can make this work. I would be more comfortable with this if we backfill to the top of this box with flowable fill. Would that be an additional cost, or had you planned
it that way already?
Keith
Keith Marvin, P.E.
Project Engineer
(972) 304-3681
>>> "Marty Murphy" <Martym@JRJPaving.com> 8/28/2009 10:52 AM >>>
Keith
If I understand your question correctly, we will have a piece of 36" RCP
between the manhole and the box structure for the connection just as if
it were two manholes.
I believe we will be placing a steel casing over the pipe and will have
to use ram neck or a rubber gasket around the casing. The settlement
issue should not be a problem as it will be backfilled just as would a
manhole and the adjoining RCP.
Brian, correct me if I am wrong.
Marty
-----Original Message-----
From: Keith Marvin [mailto:kmarvin@ci.coppell.tx.us]
Sent: Friday, August 28, 2009 10:40 AM
To: James Scott
Cc: Marty Murphy
Subject: RE: CHANGE ORDER 1 FOR COPPELL ROAD
James,
Do you have an option 2 for a cast in place box connected to the
existing box?
If not, how do we connect this to the existing box, and how do we ensure
no settlement, and that it will be water tight?
Keith
Keith Marvin, P.E.
Project Engineer
(972) 304-3681
>>> "James Scott" <Jamess@JRJPaving.com> 8/28/2009 9:20 AM >>>
Here it is
-----Original Message-----
From: Keith Marvin [mailto:kmarvin@ci.coppell.tx.us]
Sent: Thursday, August 27, 2009 4:06 PM
To: James Scott
Subject: RE: CHANGE ORDER 1 FOR COPPELL ROAD
Ok. The sooner the better.
Keith
Keith Marvin, P.E.
Project Engineer
(972) 304-3681
>>> "James Scott" <Jamess@JRJPaving.com> 8/27/2009 3:59 PM >>>
I just spoke to our sub contractor and he is putting the finishing
touches on it right now.
-----Original Message-----
From: Keith Marvin [mailto:kmarvin@ci.coppell.tx.us]
Sent: Thursday, August 27, 2009 3:57 PM
To: James Scott
Cc: Richard Odell; Marty Murphy
Subject: RE: CHANGE ORDER 1 FOR COPPELL ROAD
James/Marty,
We need to close out Change Order #1. I need the pricing on the
water/storm box in Bethel in order to do that. Please send it over as
soon as you can. I need the final dollar amount for this change so I
can work on the sewer line change that needs to go to City Council.
If we don't have the numbers for CO #1 by Monday, then I can't do CO#2,
and we will miss the window for the 9/8 council meeting. If we miss
that meeting, we will not be able to get the sewer line approved until
the 9/22 City Council Meeting.
Keith
Keith Marvin, P.E.
Project Engineer
(972) 304-3681
>>> "James Scott" <Jamess@JRJPaving.com> 8/26/2009 10:25 AM >>>
-----Original Message-----
From: Keith Marvin [mailto:KMARVIN@ci.coppell.tx.us]
Sent: Wednesday, August 26, 2009 10:04 AM
To: James Scott
Subject: Re: CHANGE ORDER 1 FOR COPPELL ROAD
Is there supposed to be an attachment here?
-----Original Message-----
From: "James Scott" <Jamess@JRJPaving.com>
To: Keith Marvin <KMARVIN@ci.coppell.tx.us>
Sent: 8/26/2009 9:36:41 AM
Subject: RE: CHANGE ORDER 1 FOR COPPELL ROAD
After taling with my utilitie sub, it appears that they ran into s
problem with the SS at the service center. They need to lower it to
connect it. The attached change order reflects the work that neds to be
done. Apperently this is holding up my sub right now.
Thank you
-----Original Message-----
From: Keith Marvin [mailto:kmarvin@ci.coppell.tx.us]
Sent: Wednesday, August 26, 2009 8:47 AM
To: James Scott
Cc: Richard Odell; Marty Murphy
Subject: Re: CHANGE ORDER 1 FOR COPPELL ROAD
James,
Any word on the 16" water line box?
Keith
Keith Marvin, P.E.
Project Engineer
(972) 304-3681
>>> "James Scott" <Jamess@JRJPaving.com> 8/24/2009 10:26 AM >>>
Keith,
This is the change order # 1 we will send over the pricing for the 16"
box etc... by tomorrow
This is everything else tho.
James Scott