Re FW USACE Project No SWF-2004-00181 (0816-002-02) (UNCLASSIFIED) (3)Loretta,
Does this mean the draft needs to go in for review prior to having it executed?
If so, see the attached draft documents. Once I hear from you that they are acceptable, we'll move forward with executing the city document. I have already contacted the representative
for the other property.
Keith
Keith Marvin, P.E.
Project Engineer
(972) 304-3681
>>> "Mokry, Loretta" <lmokry@apaienv.com> 7/1/2011 10:28 AM >>>
Keith,
Just received the email below from the USACE. Please note highlighted
section (I highlighted what the USACE bolded) that indicates the City is
not in compliance due to non-submittal of a recorded deed restriction
for the mitigation area. The draft deed restriction we prepared for you
previously that that City attorney indicated was not needed, needs to be
dusted off, submitted to the USACE (ASAP) for approval, recorded with
the County Clerk, so that the recorded deed restriction can be submitted
to the USACE for the file.
Call me if you have any questions.
Loretta
Loretta Mokry
Alan Plummer Associates, Inc.
10060 N Dowling Rd
College Station, TX 77845
979.694.7619 home office
817.806.1700 Fort Worth Office
817.845.3280 cell
www.apaienv.com <blocked::http://www.apaienv.om/>
From: Gomez, Lisa G SWF [mailto:Lisa.G.Gomez@usace.army.mil]
Sent: Friday, July 01, 2011 10:09 AM
To: Voight, Jason
Cc: Mokry, Loretta
Subject: USACE Project No. SWF-2004-00181 (0816-002-02) (UNCLASSIFIED)
Classification: UNCLASSIFIED
Caveats: NONE
Mr. Voight:
We have received and reviewed the 2010 annual compliance report
for the permit file referenced above. This is for the Modification of
Tributary G-1 Downstream of Bethel Road West in Dallas County, Texas.
According to your report, onsite construction activities are completed
and planting of the mitigation vegetation was done by July 2009.
Survival rate of the tree species observed exceeds 100%. Survival rate
of the small tree and shrub species observed is greater than 80%. Site
monitoring will continue with the next annual report due October 1,
2011.
PLEASE NOTE: This file is in NON-COMPLIANCE with permit conditions
as you have failed to provide this office with a copy of the recorded
deed restriction! Please respond within 30 days of this correspondence
with a status of the deed restriction and your plans to resolve this
issue ASAP!
The compliance project manager for this permit is Ms. Heather
Markway. Please direct any future correspondence to her attention.
Full contact information is provided below. Thank you.
Heather N. Markway
Regulatory Specialist
Compliance & Support Section | Regulatory Branch | U.S. Army Corps of
Engineers (CESWF-PER-RC)
819 Taylor Street, Rm 3A37
P.O. Box 17300
Fort Worth, Texas 76102
Heather.N.Markway@usace.army.mil | 817.886.1745
www.swf.usace.army.mil/regulatory
Please assist the Regulatory Program improve its service by completing
the survey on the following website:
http://per2.nwp.usace.army.mil/survey.html
Classification: UNCLASSIFIED
Caveats: NONE